Possession date of Sai Twin Tower (MahaRERA P51800052553): 30 April 2028. It has 36 homes (1 BHK, 1 Room Kitchen and 2 BHK, 141–1012 sq ft carpet), 93% sold or booked. No complaints on MahaRERA. How to check it yourself

Registered on MahaRERA under P51800052553, and currently active. Its completion date is now April 2028, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time.

Source: MahaRERA website — records for P51800052553, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

What do you want to know about Sai Twin Tower?

Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

How the possession date of Sai Twin Tower has moved

  1. 31 December 2027

    Completion date given when the project was registered

  2. 30 April 2028

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: Sai Twin Tower’s extension records on MahaRERA (P51800052553), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Sai Twin Tower

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the April 2028 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51800052553
Status
Registered and active
Builder
Shree Sai Enterprises
Location
Ghatkopar East, Mumbai · 400077
Project type
Others
Registered on
11 Sep 2023
Completion date at registration
December 2027
Latest completion date
April 2028
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
36
Sold or booked
93%
Towers
2
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
8

Construction progress of Sai Twin Tower, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
Sai Twin Tower A Wing100%90%50%0%
Sai Twin Tower B Wing100%100%70%0%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Sai Twin Tower every 1–2 months.

Sai Twin Tower: buildings, flats and land, as filed on MahaRERA

TypeCarpet area (sq ft)Units
Office Space392 – 3,44774
1 BHK374 – 48017
2 BHK553 – 7599
1 Room Kitchen141 – 2237
3 BHK933 – 1,0123
Shops1,021 – 1,4042
  • Buildings: Sai Twin Tower A Wing (17 floors) · Sai Twin Tower B Wing (19 floors)
  • Land: 1,395 sq m (about 0.3 acres) · sanctioned built-up 5,833 sq m · recreational space 102 sq m
  • Boundaries filed include: Tilak Road
  • Land, as filed: Plot No 29 CTS NO 5951
  • Map: Get directions

The builder’s record and reviews

Shree Sai Realtors (a group of 3 linked companies) has 5 projects on MahaRERA since 2017, this one included. Of the 5 GharKundli has checked: 2 finished, all within the promised date; 3 still being built, none past the promised date yet. 1 complaint on MahaRERA across 1 project.

Read Google reviews of Sai Twin Tower →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Sai Twin Tower: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about Sai Twin Tower

What is the possession date of Sai Twin Tower?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Sai Twin Tower in Ghatkopar East, Mumbai is 30 April 2028, including MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for Sai Twin Tower?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Sai Twin Tower's builder has filed on MahaRERA, the official one, is 30 April 2028, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

What is the RERA number of Sai Twin Tower?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Sai Twin Tower in Ghatkopar East, Mumbai is P51800052553.

Is Sai Twin Tower registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Sai Twin Tower is registered as P51800052553 and its status is "Registered and active".

What is the current construction status of Sai Twin Tower? How much work is done?

According to GharKundli's check of MahaRERA records (updated October 2026), Sai Twin Tower's status on MahaRERA is "Registered and active". As filed by the builder, slab work ranges from 90% to 100% across 2 towers. GharKundli's full report compares construction progress with the deadline.

Does Sai Twin Tower have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is Sai Twin Tower safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Sai Twin Tower is registered on MahaRERA as P51800052553, its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in Sai Twin Tower?

Sai Twin Tower is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) in the Mumbai region, and price up to ₹45 lakh. Some flats in Sai Twin Tower are 141 sq ft carpet, small enough for 1% if the price is ₹45 lakh or less. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.

What is the stamp duty and registration cost for a flat in Sai Twin Tower?

For a flat in Sai Twin Tower (Mumbai), stamp duty is 6% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess. A woman buying in her own name pays 5%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹6 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator

Has Sai Twin Tower received its OC? Is it ready to move in?

Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Sai Twin Tower is still under construction, with 30 April 2028 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.

Is Sai Twin Tower a redevelopment or SRA project?

According to GharKundli's check of MahaRERA records (updated October 2026), Sai Twin Tower is a redevelopment: 36 of its flats are set aside for existing occupants (rehab), and the rest are for sale.

Has Sai Twin Tower uploaded its title report on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Sai Twin Tower was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.

No title report is on MahaRERA for this project. See which documents are missing →

How can I get updates if Sai Twin Tower's possession date changes?

The latest dates are on Sai Twin Tower's MahaRERA page (P51800052553). GharKundli's Kundli Watch sends a free WhatsApp update on Sai Twin Tower every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Sai Twin Tower have?

According to GharKundli's check of MahaRERA records (updated October 2026), Sai Twin Tower has 2 buildings filed: Sai Twin Tower A Wing with 17 floors; Sai Twin Tower B Wing with 19 floors.

What are the flat sizes (carpet area) in Sai Twin Tower?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for Sai Twin Tower: 1 BHK: 374 to 480 sq ft carpet (17 homes); 2 BHK: 553 to 759 sq ft carpet (9 homes); 1 Room Kitchen: 141 to 223 sq ft carpet (7 homes); 3 BHK: 933 to 1012 sq ft carpet (3 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.

How big is the land of Sai Twin Tower?

According to GharKundli's check of MahaRERA records (updated October 2026), Sai Twin Tower stands on 1,395 sq m of land (about 0.3 acres), with 5,833 sq m of sanctioned built-up area and 102 sq m of recreational open space.

What is the track record of Sai Twin Tower's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Shree Sai Realtors (a group of 3 linked companies) has 5 projects on MahaRERA since 2017, this one included. Of the 5 GharKundli has checked: 2 finished, all within the promised date; 3 still being built, none past the promised date yet. 1 complaint on MahaRERA across 1 project. GharKundli's full report covers the builder's record in detail.

What are the reviews of Sai Twin Tower?

Google Maps has reviews of Sai Twin Tower written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of Sai Twin Tower?

Sai Twin Tower by Shree Sai Enterprises is in Ghatkopar East, Mumbai, pincode 400077, Maharashtra, and is registered on MahaRERA as P51800052553, per GharKundli's check of MahaRERA records. Its boundaries filed there include Tilak Road. Its land is filed as Plot No 29 CTS NO 5951. GharKundli lists all 228 MahaRERA projects in Ghatkopar East (400077).

How many flats are in Sai Twin Tower, and how many are sold?

According to GharKundli's check of MahaRERA records (updated October 2026), Sai Twin Tower has 36 homes in 2 towers registered on MahaRERA, and 93% of them are sold or booked.

When was Sai Twin Tower registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Sai Twin Tower was registered on MahaRERA on 11 September 2023. GharKundli did not find a title report on the land on file there.

Does Sai Twin Tower have any legal issues or court cases?

No court cases are listed for Sai Twin Tower on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder / developer of Sai Twin Tower?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Shree Sai Enterprises, which has 8 other projects registered on MahaRERA.

All projects with possession due in 2028 in Mumbai Suburban →

Other projects in Ghatkopar East (400077)

All 228 projects in Ghatkopar East (400077) →

Other projects by Shree Sai Enterprises