KELVA
by UVA HOMES LLP · Kelwa S.O (Thane), Palghar
Possession date of KELVA: 30 April 2027, moved from 28 August 2022 (52 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P99000017341, and currently active. Its completion date has moved from August 2022 to April 2027: 52 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about KELVA?
How the possession date of KELVA has moved
28 August 2022
Completion date given when the project was registered
28 August 2023
Extended at the builder's request (MahaRERA application EXT99000012391)
Reason the builder gave MahaRERA: “Labour unavailable”
31 December 2025
Extended at the builder's request (MahaRERA application EXT99000017469)
Reason the builder gave MahaRERA: “Work is hold”
31 December 2026
Extended at the builder's request (MahaRERA application EA27032620402)
Reason the builder gave MahaRERA: “some small work”
30 April 2027
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: KELVA’s extension records on MahaRERA (P99000017341), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on KELVA
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the April 2027 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P99000017341
- Status
- Registered and active
- Builder
- UVA HOMES LLP
- Location
- Kelwa S.O (Thane), Palghar · 401401
- Project type
- Residential / Group Housing
- Registered on
- 7 Aug 2018
- Completion date at registration
- August 2022
- Latest completion date
- April 2027
- Delay so far
- 52 months
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 20
- Sold or booked
- 33%
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of KELVA, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| KELVA PARADISE | 100% | 100% | 85% | 0% |
Commencement certificate (CC), as filed on MahaRERA
- KELVA PARADISE: covers 5 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on KELVA every month.
KELVA: buildings, flats and land, as filed on MahaRERA
- Buildings: KELVA PARADISE (5 floors, 27 units)
- Land: 598 sq m (about 0.1 acres) · sanctioned built-up 598 sq m · recreational space 60 sq m
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of KELVA →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
KELVA: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about KELVA
What is the possession date of KELVA?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for KELVA in Kelwa S.O (Thane), Palghar is 30 April 2027 — 52 months later than 28 August 2022, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for KELVA?
Builders and listing sites often quote an earlier "target" date for handover. The completion date KELVA's builder has filed on MahaRERA, the official one, is 30 April 2027, already 52 months later than the 28 August 2022 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of KELVA extended?
According to GharKundli's check of MahaRERA records (updated October 2026), KELVA's builder applied to MahaRERA to extend the completion date 3 times: to 28 August 2023, giving the reason "Labour unavailable"; to 31 December 2025, giving the reason "Work is hold"; to 31 December 2026, giving the reason "some small work". MahaRERA also added its automatic 4-month extension for all eligible projects.
What is the RERA number of KELVA?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of KELVA in Kelwa S.O (Thane), Palghar is P99000017341.
Is KELVA registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), KELVA is registered as P99000017341 and its status is "Registered and active".
What is the construction status of KELVA?
According to GharKundli's check of MahaRERA records (updated October 2026), KELVA's status on MahaRERA is "Registered and active". As filed by the builder, slab work on KELVA PARADISE is 100% done and internal work 85%. GharKundli's full report compares construction progress with the deadline.
Does KELVA have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is KELVA safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), KELVA is registered on MahaRERA as P99000017341, its completion date has moved 52 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if KELVA's possession date changes?
The latest dates are on KELVA's MahaRERA page (P99000017341). GharKundli's Kundli Watch sends a free WhatsApp update on KELVA every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does KELVA have?
According to GharKundli's check of MahaRERA records (updated October 2026), KELVA has one building filed: KELVA PARADISE with 5 floors and 27 units.
How big is the land of KELVA?
According to GharKundli's check of MahaRERA records (updated October 2026), KELVA stands on 598 sq m of land (about 0.1 acres), with 598 sq m of sanctioned built-up area and 60 sq m of recreational open space.
Where can I read reviews of KELVA?
Google Maps has reviews of KELVA written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is KELVA?
KELVA by UVA HOMES LLP is in Kelwa S.O (Thane), Palghar (pincode 401401), Maharashtra, and is registered on MahaRERA as P99000017341, per GharKundli's check of MahaRERA records.
How many homes are in KELVA?
According to GharKundli's check of MahaRERA records (updated October 2026), KELVA has 20 homes in 1 tower registered on MahaRERA, and 33% of them are sold or booked.
When was KELVA registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), KELVA was registered on MahaRERA on 7 August 2018. GharKundli did not find a title report on the land on file there.
Are there court cases on KELVA?
No court cases are listed for KELVA on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder of KELVA?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is UVA HOMES LLP.
Check it yourself on MahaRERA
- How to check the possession date of KELVA
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2027 in Palghar →
Other projects in pincode 401401
All 15 projects in Kelwa (401401) →Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.