PRISH APARTMENT
by RAJESH D YADAV · Kelve East, Palghar
Possession date of PRISH APARTMENT: 30 July 2027, moved from 30 March 2025 (24 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P99000028590, and currently active. Its completion date has moved from March 2025 to July 2027: 24 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about PRISH APARTMENT?
How the possession date of PRISH APARTMENT has moved
30 March 2025
Completion date given when the project was registered
30 March 2027
Extended at the builder's request (MahaRERA application EXT99000027677)
Reason the builder gave MahaRERA: “duration we can’t available the labours , materials and other required Essentials to Complete the Project.”
30 July 2027
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: PRISH APARTMENT’s extension records on MahaRERA (P99000028590), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on PRISH APARTMENT
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the July 2027 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P99000028590
- Status
- Registered and active
- Builder
- RAJESH D YADAV
- Location
- Kelve East, Palghar · 401401
- Project type
- Residential / Group Housing
- Registered on
- 25 Mar 2021
- Completion date at registration
- March 2025
- Latest completion date
- July 2027
- Delay so far
- 24 months
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 30
- Sold or booked
- 85%
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of PRISH APARTMENT, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| PRISH APARTMENT | 100% | 100% | 65% | 0% |
Commencement certificate (CC), as filed on MahaRERA
- PRISH APARTMENT: covers 6 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on PRISH APARTMENT every month.
PRISH APARTMENT: buildings, flats and land, as filed on MahaRERA
- Buildings: PRISH APARTMENT (10 floors, 34 units)
- Car parking: 3 covered, 7 open
- Land: 922 sq m (about 0.2 acres) · sanctioned built-up 922 sq m
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of PRISH APARTMENT →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
PRISH APARTMENT: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about PRISH APARTMENT
What is the possession date of PRISH APARTMENT?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for PRISH APARTMENT in Kelve East, Palghar is 30 July 2027 — 24 months later than 30 March 2025, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for PRISH APARTMENT?
Builders and listing sites often quote an earlier "target" date for handover. The completion date PRISH APARTMENT's builder has filed on MahaRERA, the official one, is 30 July 2027, already 24 months later than the 30 March 2025 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of PRISH APARTMENT extended?
According to GharKundli's check of MahaRERA records (updated October 2026), PRISH APARTMENT's builder applied to MahaRERA to extend the completion date once: to 30 March 2027, giving the reason "duration we can’t available the labours , materials and other required Essentials to Complete the Project.". MahaRERA also added its automatic 4-month extension for all eligible projects.
What is the RERA number of PRISH APARTMENT?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of PRISH APARTMENT in Kelve East, Palghar is P99000028590.
Is PRISH APARTMENT registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), PRISH APARTMENT is registered as P99000028590 and its status is "Registered and active".
What is the construction status of PRISH APARTMENT?
According to GharKundli's check of MahaRERA records (updated October 2026), PRISH APARTMENT's status on MahaRERA is "Registered and active". As filed by the builder, slab work on PRISH APARTMENT is 100% done and internal work 65%. GharKundli's full report compares construction progress with the deadline.
Does PRISH APARTMENT have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is PRISH APARTMENT safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), PRISH APARTMENT is registered on MahaRERA as P99000028590, its completion date has moved 24 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if PRISH APARTMENT's possession date changes?
The latest dates are on PRISH APARTMENT's MahaRERA page (P99000028590). GharKundli's Kundli Watch sends a free WhatsApp update on PRISH APARTMENT every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does PRISH APARTMENT have?
According to GharKundli's check of MahaRERA records (updated October 2026), PRISH APARTMENT has one building filed: PRISH APARTMENT with 10 floors and 34 units.
How much parking does PRISH APARTMENT have?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 3 covered and 7 open car parking spaces for PRISH APARTMENT.
How big is the land of PRISH APARTMENT?
According to GharKundli's check of MahaRERA records (updated October 2026), PRISH APARTMENT stands on 922 sq m of land (about 0.2 acres), with 922 sq m of sanctioned built-up area.
Where can I read reviews of PRISH APARTMENT?
Google Maps has reviews of PRISH APARTMENT written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is PRISH APARTMENT?
PRISH APARTMENT by RAJESH D YADAV is in Kelve East, Palghar (pincode 401401), Maharashtra, and is registered on MahaRERA as P99000028590, per GharKundli's check of MahaRERA records.
How many homes are in PRISH APARTMENT?
According to GharKundli's check of MahaRERA records (updated October 2026), PRISH APARTMENT has 30 homes in 1 tower registered on MahaRERA, and 85% of them are sold or booked.
When was PRISH APARTMENT registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), PRISH APARTMENT was registered on MahaRERA on 25 March 2021. GharKundli did not find a title report on the land on file there.
Are there court cases on PRISH APARTMENT?
No court cases are listed for PRISH APARTMENT on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder of PRISH APARTMENT?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is RAJESH D YADAV.
Check it yourself on MahaRERA
- How to check the possession date of PRISH APARTMENT
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2027 in Palghar →
Other projects in pincode 401401
All 15 projects in Kelwa (401401) →Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.