by NARAYANI ESTATE · Saphale, Palghar

Possession date of Narayani Arcade: 30 April 2028, moved from 30 December 2022 (60 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P99000018225, and currently active. Its completion date has moved from December 2022 to April 2028: 60 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.

Source: GharKundli’s check of MahaRERA records, October 2026.

What do you want to know about Narayani Arcade?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of Narayani Arcade has moved

  1. 30 December 2022

    Completion date given when the project was registered

  2. 31 December 2024

    Extended at the builder's request (MahaRERA application EXT99000013902)

    Reason the builder gave MahaRERA: “Due to covid 19 delay in avalibality of material and labour.”
  3. 31 March 2026

    Extended at the builder's request (MahaRERA application EXT99000028072)

    Reason the builder gave MahaRERA:
    “1. While registering the project with MahaRERA,we had underestimated the project completion time which proved to be less for such a project. 2. Still the project progress was on track but to slackness in sale and due between due to some iss…” Read the full reason“1. While registering the project with MahaRERA,we had underestimated the project completion time which proved to be less for such a project. 2. Still the project progress was on track but to slackness in sale and due between due to some issues with our labour contractor led to delay of works. 3. But rest assured,now the works are in full swing & will be completed with in the stipulated time lines of this extended date and OC will be obtained. 4. Also,we are uploading the PERTChart/work completion schedule of the project. 5. Hence,we request you to consider our request & justification & gran…”
  4. 31 December 2027

    Extended at the builder's request (MahaRERA application EA01052620800)

    Reason the builder gave MahaRERA:
    “1. While registering the project with MahaRERA,we had underestimated the project completion time which proved to be less for such a project. 2. Project got delayed which lead to lack of sales and Financial Difficulties 3. Still the project…” Read the full reason“1. While registering the project with MahaRERA,we had underestimated the project completion time which proved to be less for such a project. 2. Project got delayed which lead to lack of sales and Financial Difficulties 3. Still the project progress was on track but in between due to some issues with our labour contractor led to few months delay of works. 4. But rest assured,now the works are in full swing & will be completed with in the stipulated time lines of this extended date and OC will be obtained. 5. Also,we are uploading the PERTChart/work completion schedule of the project. 6. Henc…”
  5. 30 April 2028

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: Narayani Arcade’s extension records on MahaRERA (P99000018225), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Narayani Arcade

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the April 2028 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P99000018225
Status
Registered and active
Builder
NARAYANI ESTATE
Location
Saphale, Palghar · 401402
Project type
Residential / Group Housing
Registered on
16 Oct 2018
Completion date at registration
December 2022
Latest completion date
April 2028
Delay so far
60 months
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
84
Sold or booked
25%
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found

Construction progress of Narayani Arcade, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
Narayani Arcade100%95%100%40%

Commencement certificate (CC), as filed on MahaRERA

  • Narayani Arcade: covers 8 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Narayani Arcade every month.

Narayani Arcade: buildings, flats and land, as filed on MahaRERA

  • Buildings: Narayani Arcade (9 floors, 89 units)
  • Car parking: 5 covered, 7 open
  • Land: 3,500 sq m (about 0.9 acres) · sanctioned built-up 4,383 sq m · recreational space 522 sq m

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of Narayani Arcade →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Narayani Arcade: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about Narayani Arcade

What is the possession date of Narayani Arcade?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Narayani Arcade in Saphale, Palghar is 30 April 2028 — 60 months later than 30 December 2022, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for Narayani Arcade?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Narayani Arcade's builder has filed on MahaRERA, the official one, is 30 April 2028, already 60 months later than the 30 December 2022 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Narayani Arcade extended?

According to GharKundli's check of MahaRERA records (updated October 2026), Narayani Arcade's builder applied to MahaRERA to extend the completion date 3 times: to 31 December 2024, giving the reason "Due to covid 19 delay in avalibality of material and labour."; to 31 March 2026, giving the reason "1. While registering the project with MahaRERA,we had underestimated the project completion time which proved to be less for such a project. 2. Still the project progress was on track but to slackness in sale and due between due to some issues with our labour contractor led to delay of works. 3. But rest assured,now the works are in full swing & will be completed with in the stipulated time lines of this extended date and OC will be obtained. 4. Also,we are uploading the PERTChart/work completion schedule of the project. 5. Hence,we request you to consider our request & justification & gran…"; to 31 December 2027, giving the reason "1. While registering the project with MahaRERA,we had underestimated the project completion time which proved to be less for such a project. 2. Project got delayed which lead to lack of sales and Financial Difficulties 3. Still the project progress was on track but in between due to some issues with our labour contractor led to few months delay of works. 4. But rest assured,now the works are in full swing & will be completed with in the stipulated time lines of this extended date and OC will be obtained. 5. Also,we are uploading the PERTChart/work completion schedule of the project. 6. Henc…". MahaRERA also added its automatic 4-month extension for all eligible projects.

What is the RERA number of Narayani Arcade?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Narayani Arcade in Saphale, Palghar is P99000018225.

Is Narayani Arcade registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Narayani Arcade is registered as P99000018225 and its status is "Registered and active".

What is the construction status of Narayani Arcade?

According to GharKundli's check of MahaRERA records (updated October 2026), Narayani Arcade's status on MahaRERA is "Registered and active". As filed by the builder, slab work on Narayani Arcade is 95% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.

Does Narayani Arcade have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is Narayani Arcade safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Narayani Arcade is registered on MahaRERA as P99000018225, its completion date has moved 60 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if Narayani Arcade's possession date changes?

The latest dates are on Narayani Arcade's MahaRERA page (P99000018225). GharKundli's Kundli Watch sends a free WhatsApp update on Narayani Arcade every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Narayani Arcade have?

According to GharKundli's check of MahaRERA records (updated October 2026), Narayani Arcade has one building filed: Narayani Arcade with 9 floors and 89 units.

How much parking does Narayani Arcade have?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 5 covered and 7 open car parking spaces for Narayani Arcade.

How big is the land of Narayani Arcade?

According to GharKundli's check of MahaRERA records (updated October 2026), Narayani Arcade stands on 3,500 sq m of land (about 0.9 acres), with 4,383 sq m of sanctioned built-up area and 522 sq m of recreational open space.

Where can I read reviews of Narayani Arcade?

Google Maps has reviews of Narayani Arcade written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is Narayani Arcade?

Narayani Arcade by NARAYANI ESTATE is in Saphale, Palghar (pincode 401402), Maharashtra, and is registered on MahaRERA as P99000018225, per GharKundli's check of MahaRERA records.

How many homes are in Narayani Arcade?

According to GharKundli's check of MahaRERA records (updated October 2026), Narayani Arcade has 84 homes in 1 tower registered on MahaRERA, and 25% of them are sold or booked.

When was Narayani Arcade registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Narayani Arcade was registered on MahaRERA on 16 October 2018. GharKundli did not find a title report on the land on file there.

Are there court cases on Narayani Arcade?

No court cases are listed for Narayani Arcade on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder of Narayani Arcade?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is NARAYANI ESTATE.

All projects with possession due in 2028 in Palghar →

Other projects in Palghar

All 14 projects in Kelwa Mahim (401402) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.