Possession date of Puneville Phase III Cluster C: 30 April 2030. This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P52100051020, and currently active. Its completion date is now April 2030, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time.

Source: GharKundli’s check of MahaRERA records, November 2026.

What do you want to know about Puneville Phase III Cluster C?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of Puneville Phase III Cluster C has moved

  1. 30 December 2029

    Completion date given when the project was registered

  2. 30 April 2030

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: Puneville Phase III Cluster C’s extension records on MahaRERA (P52100051020), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Puneville Phase III Cluster C

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the April 2030 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay

Other wings and phases of this project

Each is registered on MahaRERA separately, with its own possession date. Check the one your flat is in.

MahaRERA registration
P52100051020
Status
Registered and active
Builder
Benchmarrk Realty LLP
Location
Punawale, Pune · 411033
Project type
Residential / Group Housing
Registered on
22 May 2023
Completion date at registration
December 2029
Latest completion date
April 2030
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
104
Sold or booked
91%
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
10

Construction progress of Puneville Phase III Cluster C, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
P Wing100%14%3%0%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Puneville Phase III Cluster C every month.

Puneville Phase III Cluster C: buildings, flats and land, as filed on MahaRERA

The builder’s record and reviews

Pharande Promoters And Builders (a group of 4 linked companies) has 43 projects on MahaRERA since 2017, this one included. Of the 23 GharKundli has checked: 1 finished, all within the promised date; 21 still being built, 1 past the promised date (typically 3 months late); 1 lapsed. 17 complaints on MahaRERA across 6 projects.

Read Google reviews of Puneville Phase III Cluster C →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Puneville Phase III Cluster C: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about Puneville Phase III Cluster C

What is the possession date of Puneville Phase III Cluster C?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for Puneville Phase III Cluster C in Punawale, Pune is 30 April 2030, including MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for Puneville Phase III Cluster C?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Puneville Phase III Cluster C's builder has filed on MahaRERA, the official one, is 30 April 2030, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

What is the RERA number of Puneville Phase III Cluster C?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of Puneville Phase III Cluster C in Punawale, Pune is P52100051020.

Is Puneville Phase III Cluster C registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Puneville Phase III Cluster C is registered as P52100051020 and its status is "Registered and active".

What is the construction status of Puneville Phase III Cluster C?

According to GharKundli's check of MahaRERA records (updated November 2026), Puneville Phase III Cluster C's status on MahaRERA is "Registered and active". As filed by the builder, slab work on P Wing is 14% done and internal work 3%. GharKundli's full report compares construction progress with the deadline.

Does Puneville Phase III Cluster C have complaints on MahaRERA?

No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.

Is Puneville Phase III Cluster C safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), Puneville Phase III Cluster C is registered on MahaRERA as P52100051020, its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

Does Puneville Phase III Cluster C have other wings or phases?

Yes. MahaRERA lists 6 other registrations of the same project, each with its own possession date: Puneville Phase I (P52100000441); Puneville Phase II Cluster A (P52100000440, possession 29 Dec 2023); Puneville Phase II Cluster B (PR1265052601245, possession 30 Sep 2031); Puneville Phase III Cluster A (P52100029522); Puneville Phase III Cluster B (P52100047694, possession 30 Oct 2029); Puneville Phase III Cluster D (P52100077431, possession 30 Jul 2031). Check that your agreement names the registration of your own wing.

How can I get updates if Puneville Phase III Cluster C's possession date changes?

The latest dates are on Puneville Phase III Cluster C's MahaRERA page (P52100051020). GharKundli's Kundli Watch sends a free WhatsApp update on Puneville Phase III Cluster C every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Puneville Phase III Cluster C have?

According to GharKundli's check of MahaRERA records (updated November 2026), Puneville Phase III Cluster C has one building filed: P Wing with 28 floors.

How big is the land of Puneville Phase III Cluster C?

According to GharKundli's check of MahaRERA records (updated November 2026), Puneville Phase III Cluster C stands on 1,890 sq m of land (about 0.5 acres), with 14,327 sq m of sanctioned built-up area and 3,455 sq m of recreational open space.

What is the track record of Puneville Phase III Cluster C's builder?

According to GharKundli's check of MahaRERA records (updated November 2026), Pharande Promoters And Builders (a group of 4 linked companies) has 43 projects on MahaRERA since 2017, this one included. Of the 23 GharKundli has checked: 1 finished, all within the promised date; 21 still being built, 1 past the promised date (typically 3 months late); 1 lapsed. 17 complaints on MahaRERA across 6 projects. GharKundli's full report covers the builder's record in detail.

Where can I read reviews of Puneville Phase III Cluster C?

Google Maps has reviews of Puneville Phase III Cluster C written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is Puneville Phase III Cluster C?

Puneville Phase III Cluster C by Benchmarrk Realty LLP is in Punawale, Pune (pincode 411033), near Tathawade, Maharashtra, and is registered on MahaRERA as P52100051020, per GharKundli's check of MahaRERA records.

How many homes are in Puneville Phase III Cluster C?

According to GharKundli's check of MahaRERA records (updated November 2026), Puneville Phase III Cluster C has 104 homes in 1 tower registered on MahaRERA, and 91% of them are sold or booked.

When was Puneville Phase III Cluster C registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Puneville Phase III Cluster C was registered on MahaRERA on 22 May 2023. GharKundli did not find a title report on the land on file there.

Are there court cases on Puneville Phase III Cluster C?

No court cases are listed for Puneville Phase III Cluster C on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).

Who is the builder of Puneville Phase III Cluster C?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is Benchmarrk Realty LLP, which has 10 other projects registered on MahaRERA.

All projects with possession due in 2030 in Pune →

Other projects in pincode 411033

All 431 projects in Chinchwadgaon (411033) →

Other projects by Benchmarrk Realty LLP

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.