VTP DOLCE VITA Phase 1

by Ashdan Developers Private Limited (VTP) · Manjari Kh, Pune 412307Also near Manjri Khurd

What’s in the report? →

Possession date of VTP DOLCE VITA Phase 1 (MahaRERA P52100051819): 30 April 2029. It has 704 homes, 93% sold or booked. 16 complaints on MahaRERA. How to check it yourself

Registered on MahaRERA under P52100051819, and currently active. Its completion date is now April 2029, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time.

Source: MahaRERA website — records for P52100051819, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

What do you want to know about VTP DOLCE VITA Phase 1?

3 court cases MahaRERA par listed. Kya jaanna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

How the possession date of VTP DOLCE VITA Phase 1 has moved

  1. 31 December 2028

    Completion date given when the project was registered

  2. 30 April 2029

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: VTP DOLCE VITA Phase 1’s extension records on MahaRERA (P52100051819), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on VTP DOLCE VITA Phase 1

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 16 complaints and 3 court cases, and how it ended
  • Construction pace against the April 2029 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay

Other wings and phases of this project

Each is registered on MahaRERA separately, with its own possession date. Check the one your flat is in.

MahaRERA registration
P52100051819
Status
Registered and active
Builder
Ashdan Developers Private Limited
Location
Manjari Kh, Pune · 412307
Project type
Others
Registered on
7 Jul 2023
Completion date at registration
December 2028
Latest completion date
April 2029
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
704
Sold or booked
93%
Towers
4
Complaints on MahaRERA
16
Court cases listed
3
Title report on file
Not found
Builder's other MahaRERA projects
15

Construction progress of VTP DOLCE VITA Phase 1, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
Tower 1100%89%40.6%0%
Tower 2100%97%41.3%0%
Tower 3100%83%36.9%0%
Tower 4100%77%32.5%0%

Commencement certificate (CC), as filed on MahaRERA

  • Tower 1: covers 35 floors
  • Tower 2: covers 35 floors
  • Tower 3: covers 35 floors
  • Tower 4: covers 36 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on VTP DOLCE VITA Phase 1 every 1–2 months.

VTP DOLCE VITA Phase 1: buildings, flats and land, as filed on MahaRERA

  • Buildings: Tower 1 (35 floors, 192 units) · Tower 2 (35 floors, 203 units) · Tower 3 (35 floors, 137 units) · Tower 4 (36 floors, 204 units)
  • Land: 4,425 sq m (about 1.1 acres) · sanctioned built-up 84,056 sq m
  • Land, as filed: Out of Sr No 124, 125, 131, 132
  • Map: the location the builder filed on MahaRERA · Get directions

The builder’s record and reviews

VTP Corporation (a group of 18 linked companies) has 74 projects on MahaRERA since 2017, this one included. Of the 74 GharKundli has checked: 32 finished, 19 within the promised date and 13 needed more time (typically 9 months); 29 still being built, 7 past the promised date (typically 6 months late); 13 lapsed. 695 complaints on MahaRERA across 59 projects.

Read Google reviews of VTP DOLCE VITA Phase 1 →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

VTP DOLCE VITA Phase 1: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about VTP DOLCE VITA Phase 1

What is the possession date of VTP DOLCE VITA Phase 1?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for VTP DOLCE VITA Phase 1 in Manjari Kh, Pune is 30 April 2029, including MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for VTP DOLCE VITA Phase 1?

Builders and listing sites often quote an earlier "target" date for handover. The completion date VTP DOLCE VITA Phase 1's builder has filed on MahaRERA, the official one, is 30 April 2029, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

What is the RERA number of VTP DOLCE VITA Phase 1?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of VTP DOLCE VITA Phase 1 in Manjari Kh, Pune is P52100051819.

Is VTP DOLCE VITA Phase 1 registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), VTP DOLCE VITA Phase 1 is registered as P52100051819 and its status is "Registered and active".

What is the current construction status of VTP DOLCE VITA Phase 1? How much work is done?

According to GharKundli's check of MahaRERA records (updated October 2026), VTP DOLCE VITA Phase 1's status on MahaRERA is "Registered and active". As filed by the builder, slab work ranges from 77% to 97% across 4 towers. GharKundli's full report compares construction progress with the deadline.

Does VTP DOLCE VITA Phase 1 have complaints on MahaRERA?

16 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

16 complaints are filed on this project. Know what went wrong before you pay a token. See how each complaint ended →

Is VTP DOLCE VITA Phase 1 safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), VTP DOLCE VITA Phase 1 is registered on MahaRERA as P52100051819, its completion date has not been moved by the builder and 16 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in VTP DOLCE VITA Phase 1?

VTP DOLCE VITA Phase 1 is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 90 sq m (about 969 sq ft) outside the Mumbai region, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.

What is the stamp duty and registration cost for a flat in VTP DOLCE VITA Phase 1?

In Maharashtra, stamp duty is between 3% and 7% of the agreement value (or the ready reckoner value, if higher), depending on the city's local cesses: about 6–7% in big cities, less in municipal-council and village areas. A woman buying in her own name pays 1% less. Registration is 1%, capped at ₹30,000. GharKundli's property cost calculator works it out for the price of a flat in VTP DOLCE VITA Phase 1: gharkundli.com/tools/property-cost-calculator

Has VTP DOLCE VITA Phase 1 received its OC? Is it ready to move in?

Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), VTP DOLCE VITA Phase 1 is still under construction, with 30 April 2029 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.

Has VTP DOLCE VITA Phase 1 uploaded its title report on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), no title report for VTP DOLCE VITA Phase 1 was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.

No title report is on MahaRERA for this project. See which documents are missing →

Does VTP DOLCE VITA Phase 1 have other wings or phases?

Yes. MahaRERA lists 3 other registrations of the same project, each with its own possession date: VTP DOLCE VITA PHASE 2 (P52100055405, possession 30 Oct 2029); VTP DOLCE VITA PHASE 3 (P52100055407, possession 30 Oct 2029); VTP DOLCE VITA PHASE 4 (P52100055619, possession 30 Oct 2029). Check that your agreement names the registration of your own wing.

How can I get updates if VTP DOLCE VITA Phase 1's possession date changes?

The latest dates are on VTP DOLCE VITA Phase 1's MahaRERA page (P52100051819). GharKundli's Kundli Watch sends a free WhatsApp update on VTP DOLCE VITA Phase 1 every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does VTP DOLCE VITA Phase 1 have?

According to GharKundli's check of MahaRERA records (updated October 2026), VTP DOLCE VITA Phase 1 has 4 buildings filed: Tower 1 with 35 floors and 192 units; Tower 2 with 35 floors and 203 units; Tower 3 with 35 floors and 137 units; Tower 4 with 36 floors and 204 units.

How big is the land of VTP DOLCE VITA Phase 1?

According to GharKundli's check of MahaRERA records (updated October 2026), VTP DOLCE VITA Phase 1 stands on 4,425 sq m of land (about 1.1 acres), with 84,056 sq m of sanctioned built-up area.

What is the track record of VTP DOLCE VITA Phase 1's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), VTP Corporation (a group of 18 linked companies) has 74 projects on MahaRERA since 2017, this one included. Of the 74 GharKundli has checked: 32 finished, 19 within the promised date and 13 needed more time (typically 9 months); 29 still being built, 7 past the promised date (typically 6 months late); 13 lapsed. 695 complaints on MahaRERA across 59 projects. GharKundli's full report covers the builder's record in detail.

What are the reviews of VTP DOLCE VITA Phase 1?

Google Maps has reviews of VTP DOLCE VITA Phase 1 written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 16 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of VTP DOLCE VITA Phase 1?

VTP DOLCE VITA Phase 1 by Ashdan Developers Private Limited (VTP) is in Manjari Kh, Pune, pincode 412307 (near Manjri Khurd), Maharashtra, and is registered on MahaRERA as P52100051819, per GharKundli's check of MahaRERA records. Its land is filed as Out of Sr No 124, 125, 131, 132. GharKundli lists all 136 MahaRERA projects in Manjari Farm (412307).

How many flats are in VTP DOLCE VITA Phase 1, and how many are sold?

According to GharKundli's check of MahaRERA records (updated October 2026), VTP DOLCE VITA Phase 1 has 704 homes in 4 towers registered on MahaRERA, and 93% of them are sold or booked.

When was VTP DOLCE VITA Phase 1 registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), VTP DOLCE VITA Phase 1 was registered on MahaRERA on 7 July 2023. GharKundli did not find a title report on the land on file there.

Does VTP DOLCE VITA Phase 1 have any legal issues or court cases?

3 court cases are listed for VTP DOLCE VITA Phase 1 on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.

A court case can stall a project or tie up the land. See what each case is about →

Who is the builder / developer of VTP DOLCE VITA Phase 1?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Ashdan Developers Private Limited, the company VTP files this project under, which has 15 other projects registered on MahaRERA.

All projects with possession due in 2029 in Pune →

Other projects in Manjari Farm (412307)

All 136 projects in Manjari Farm (412307) →

Other projects by Ashdan Developers Private Limited

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.