Skip to content
GharKundli

Sadguru Aarambh

by Visharia Sadguru Bhoomi LLP · Saphale West, Palghar

Possession: Sadguru Aarambh is marked completed on MahaRERA. How to check it yourself

Registered on MahaRERA under P99000021488. Status: Completed.

Source: GharKundli’s check of MahaRERA records, November 2026.

What do you want to know about Sadguru Aarambh?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of Sadguru Aarambh has moved

  1. 30 March 2023

    Completion date given when the project was registered

  2. 30 September 2023

    Extended at the builder's request (MahaRERA application EXT99000015121)

    Reason the builder gave MahaRERA:
    “We have obtained OC of the Building and uploaded the same. We have Started process of Society Formation, However we have not been able to form the Society due to some reason or the other That is why we are requesting you to give extension o…” Read the full reason“We have obtained OC of the Building and uploaded the same. We have Started process of Society Formation, However we have not been able to form the Society due to some reason or the other That is why we are requesting you to give extension of 6 (six) months so we can complete the process.”

Source: Sadguru Aarambh’s extension records on MahaRERA (P99000021488), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Sadguru Aarambh

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the September 2023 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P99000021488
Status
Completed
Builder
Visharia Sadguru Bhoomi LLP
Location
Saphale West, Palghar · 401102
Project type
Residential / Group Housing
Registered on
5 Jul 2019
Completion date at registration
March 2023
Latest completion date
September 2023
Delay so far
6 months
Homes
60
Towers
2
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
2

Construction progress of Sadguru Aarambh, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
Sadguru Aarambh-A wing100%100%100%100%
Sadguru Aarambh-B wing100%100%100%100%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Sadguru Aarambh every month.

Sadguru Aarambh: buildings, flats and land, as filed on MahaRERA

  • Buildings: Sadguru Aarambh-A wing (5 floors) · Sadguru Aarambh-B wing (5 floors)
  • Land: 2,218 sq m (about 0.5 acres) · sanctioned built-up 2,218 sq m
  • Boundaries filed include: 9mt Wide Layout Road

The builder’s record and reviews

Visharia Sadguru Bhoomi has 3 projects on MahaRERA since 2019, this one included. Of the 3 GharKundli has checked: 1 finished, all within the promised date; 1 still being built, none past the promised date yet; 1 lapsed. No complaints on MahaRERA.

Read Google reviews of Sadguru Aarambh →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Sadguru Aarambh: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about Sadguru Aarambh

What is the possession date of Sadguru Aarambh?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for Sadguru Aarambh in Saphale West, Palghar is 30 September 2023 — 6 months later than 30 March 2023, the date given at registration.

Is the builder's possession date different from the MahaRERA date for Sadguru Aarambh?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Sadguru Aarambh's builder has filed on MahaRERA, the official one, is 30 September 2023, already 6 months later than the 30 March 2023 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Sadguru Aarambh extended?

According to GharKundli's check of MahaRERA records (updated November 2026), Sadguru Aarambh's builder applied to MahaRERA to extend the completion date once: to 30 September 2023, giving the reason "We have obtained OC of the Building and uploaded the same. We have Started process of Society Formation, However we have not been able to form the Society due to some reason or the other That is why we are requesting you to give extension of 6 (six) months so we can complete the process.".

What is the RERA number of Sadguru Aarambh?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of Sadguru Aarambh in Saphale West, Palghar is P99000021488.

Is Sadguru Aarambh registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Sadguru Aarambh is registered as P99000021488 and its status is "Completed".

What is the construction status of Sadguru Aarambh?

According to GharKundli's check of MahaRERA records (updated November 2026), Sadguru Aarambh's status on MahaRERA is "Completed". As filed by the builder, slab work is 100% done across 2 towers. GharKundli's full report compares construction progress with the deadline.

Does Sadguru Aarambh have complaints on MahaRERA?

No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.

Is Sadguru Aarambh safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), Sadguru Aarambh is registered on MahaRERA as P99000021488, its MahaRERA status is "Completed", its completion date has moved 6 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if Sadguru Aarambh's possession date changes?

The latest dates are on Sadguru Aarambh's MahaRERA page (P99000021488). GharKundli's Kundli Watch sends a free WhatsApp update on Sadguru Aarambh every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Sadguru Aarambh have?

According to GharKundli's check of MahaRERA records (updated November 2026), Sadguru Aarambh has 2 buildings filed: Sadguru Aarambh-A wing with 5 floors; Sadguru Aarambh-B wing with 5 floors.

How big is the land of Sadguru Aarambh?

According to GharKundli's check of MahaRERA records (updated November 2026), Sadguru Aarambh stands on 2,218 sq m of land (about 0.5 acres), with 2,218 sq m of sanctioned built-up area.

What is the track record of Sadguru Aarambh's builder?

According to GharKundli's check of MahaRERA records (updated November 2026), Visharia Sadguru Bhoomi has 3 projects on MahaRERA since 2019, this one included. Of the 3 GharKundli has checked: 1 finished, all within the promised date; 1 still being built, none past the promised date yet; 1 lapsed. No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.

Where can I read reviews of Sadguru Aarambh?

Google Maps has reviews of Sadguru Aarambh written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is Sadguru Aarambh?

Sadguru Aarambh by Visharia Sadguru Bhoomi LLP is in Saphale West, Palghar (pincode 401102), Maharashtra, and is registered on MahaRERA as P99000021488, per GharKundli's check of MahaRERA records. Its boundaries filed there include 9mt Wide Layout Road.

How many homes are in Sadguru Aarambh?

According to GharKundli's check of MahaRERA records (updated November 2026), Sadguru Aarambh has 60 homes in 2 towers registered on MahaRERA.

When was Sadguru Aarambh registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Sadguru Aarambh was registered on MahaRERA on 5 July 2019. GharKundli did not find a title report on the land on file there.

Are there court cases on Sadguru Aarambh?

No court cases are listed for Sadguru Aarambh on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).

Who is the builder of Sadguru Aarambh?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is Visharia Sadguru Bhoomi LLP, which has 2 other projects registered on MahaRERA.

Other projects in Palghar

All 92 projects in Umbarpada (401102) →

Other projects by Visharia Sadguru Bhoomi LLP

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.