Shubh Aarambh
by Visharia Sadguru Bhoomi LLP · Umbarpada, Palghar
Possession date of Shubh Aarambh: 15 June 2024, moved from 30 June 2023 (12 months later). This is the latest completion date the builder has filed on MahaRERA, and it has already passed. How to check it yourself
Registered on MahaRERA under P99000029865. Status: Lapsed (registration period ended).
Source: GharKundli’s check of MahaRERA records, November 2026.
The latest completion date on MahaRERA (June 2024) has passed.
What do you want to know about Shubh Aarambh?
How the possession date of Shubh Aarambh has moved
30 June 2023
Completion date given when the project was registered
15 June 2024
Extended at the builder's request (MahaRERA application EXT99000016845)
Reason the builder gave MahaRERA:
“As per our RERA Certificate No. P99000029865, our project completion date is 30/06/2023, as on date we have completed our project 98% (as certified by architect) and virtually we have almost completed 100% , certificated is uploaded Current…” Read the full reason
“As per our RERA Certificate No. P99000029865, our project completion date is 30/06/2023, as on date we have completed our project 98% (as certified by architect) and virtually we have almost completed 100% , certificated is uploaded Currently we have already applyed for Electric Meters Connection with “MSEDCL” We have been given an understanding that there is a shortage of Meters and Hence the New Connection Request may take time to get activated. After completion as above we would go for Society Formation and Execution and Registration of Conveyance Deed In the light of above we request yo…”
Source: Shubh Aarambh’s extension records on MahaRERA (P99000029865), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Shubh Aarambh
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the June 2024 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P99000029865
- Status
- Lapsed (registration period ended)
- Builder
- Visharia Sadguru Bhoomi LLP
- Location
- Umbarpada, Palghar · 401102
- Project type
- Residential / Group Housing
- Registered on
- 12 Jul 2021
- Completion date at registration
- June 2023
- Latest completion date
- June 2024
- Delay so far
- 12 months
- Homes
- 35
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 2
Construction progress of Shubh Aarambh, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| Shubh Aarambh | 100% | 100% | 100% | 100% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Shubh Aarambh every month.
Shubh Aarambh: buildings, flats and land, as filed on MahaRERA
- Buildings: Shubh Aarambh (5 floors)
- Land: 818 sq m (about 0.2 acres) · sanctioned built-up 1,646 sq m
The builder’s record and reviews
Visharia Sadguru Bhoomi has 3 projects on MahaRERA since 2019, this one included. Of the 3 GharKundli has checked: 1 finished, all within the promised date; 1 still being built, none past the promised date yet; 1 lapsed. No complaints on MahaRERA.
Read Google reviews of Shubh Aarambh →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Shubh Aarambh: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about Shubh Aarambh
What is the possession date of Shubh Aarambh?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for Shubh Aarambh in Umbarpada, Palghar is 15 June 2024 — 12 months later than 30 June 2023, the date given at registration. That date has already passed.
Is the builder's possession date different from the MahaRERA date for Shubh Aarambh?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Shubh Aarambh's builder has filed on MahaRERA, the official one, is 15 June 2024, already 12 months later than the 30 June 2023 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Shubh Aarambh extended?
According to GharKundli's check of MahaRERA records (updated November 2026), Shubh Aarambh's builder applied to MahaRERA to extend the completion date once: to 15 June 2024, giving the reason "As per our RERA Certificate No. P99000029865, our project completion date is 30/06/2023, as on date we have completed our project 98% (as certified by architect) and virtually we have almost completed 100% , certificated is uploaded Currently we have already applyed for Electric Meters Connection with “MSEDCL” We have been given an understanding that there is a shortage of Meters and Hence the New Connection Request may take time to get activated. After completion as above we would go for Society Formation and Execution and Registration of Conveyance Deed In the light of above we request yo…".
What is the RERA number of Shubh Aarambh?
According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of Shubh Aarambh in Umbarpada, Palghar is P99000029865.
Is Shubh Aarambh registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), Shubh Aarambh is registered as P99000029865 and its status is "Lapsed (registration period ended)".
What is the construction status of Shubh Aarambh?
According to GharKundli's check of MahaRERA records (updated November 2026), Shubh Aarambh's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work on Shubh Aarambh is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.
Does Shubh Aarambh have complaints on MahaRERA?
No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.
Is Shubh Aarambh safe to buy?
According to GharKundli's check of MahaRERA records (updated November 2026), Shubh Aarambh is registered on MahaRERA as P99000029865, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 12 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if Shubh Aarambh's possession date changes?
The latest dates are on Shubh Aarambh's MahaRERA page (P99000029865). GharKundli's Kundli Watch sends a free WhatsApp update on Shubh Aarambh every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Shubh Aarambh have?
According to GharKundli's check of MahaRERA records (updated November 2026), Shubh Aarambh has one building filed: Shubh Aarambh with 5 floors.
How big is the land of Shubh Aarambh?
According to GharKundli's check of MahaRERA records (updated November 2026), Shubh Aarambh stands on 818 sq m of land (about 0.2 acres), with 1,646 sq m of sanctioned built-up area.
What is the track record of Shubh Aarambh's builder?
According to GharKundli's check of MahaRERA records (updated November 2026), Visharia Sadguru Bhoomi has 3 projects on MahaRERA since 2019, this one included. Of the 3 GharKundli has checked: 1 finished, all within the promised date; 1 still being built, none past the promised date yet; 1 lapsed. No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of Shubh Aarambh?
Google Maps has reviews of Shubh Aarambh written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is Shubh Aarambh?
Shubh Aarambh by Visharia Sadguru Bhoomi LLP is in Umbarpada, Palghar (pincode 401102), Maharashtra, and is registered on MahaRERA as P99000029865, per GharKundli's check of MahaRERA records.
How many homes are in Shubh Aarambh?
According to GharKundli's check of MahaRERA records (updated November 2026), Shubh Aarambh has 35 homes in 1 tower registered on MahaRERA.
When was Shubh Aarambh registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), Shubh Aarambh was registered on MahaRERA on 12 July 2021. GharKundli did not find a title report on the land on file there.
Are there court cases on Shubh Aarambh?
No court cases are listed for Shubh Aarambh on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).
Who is the builder of Shubh Aarambh?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is Visharia Sadguru Bhoomi LLP, which has 2 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of Shubh Aarambh
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in pincode 401102
- SILVER GREEN
- Sunshine Complex
- MITHILA COMPLEX
- PARIVAR RESIDENCY
- NIVETAM APARTMENT
- ASHTAVINAYAK BUILDERS AND DEVELOPERS
- SAI SANKALP BUILDING NO 01 WING A AND B
- NAYAN-VASTU HERITAGE
Other projects by Visharia Sadguru Bhoomi LLP
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.