Haware Nakshatra Phase 4
by Haware Infotech Ltd · Opp Dandekar College, Palghar 401404
What’s in the report? →Possession date of Haware Nakshatra Phase 4 (MahaRERA P99000022324): 30 April 2027. It has 342 homes, 0% sold or booked. No complaints on MahaRERA. How to check it yourself
Registered on MahaRERA under P99000022324, and currently active. Its completion date is now April 2027, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time.
Source: MahaRERA website — records for P99000022324, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.
What do you want to know about Haware Nakshatra Phase 4?
Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.
How the possession date of Haware Nakshatra Phase 4 has moved
30 December 2026
Completion date given when the project was registered
30 April 2027
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: Haware Nakshatra Phase 4’s extension records on MahaRERA (P99000022324), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Haware Nakshatra Phase 4
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the April 2027 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
Other wings and phases of this project
Each is registered on MahaRERA separately, with its own possession date. Check the one your flat is in.
- Haware Nakshatra Phase 2P99000022309 · possession 30 Dec 2021
- Haware Nakshatra Phase 3P99000022307 · possession 30 Apr 2027
- MahaRERA registration
- P99000022324
- Status
- Registered and active
- Builder
- Haware Infotech Ltd
- Location
- Opp Dandekar College, Palghar · 401404
- Project type
- Residential / Group Housing
- Registered on
- 16 Sep 2019
- Completion date at registration
- December 2026
- Latest completion date
- April 2027
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 342
- Sold or booked
- 0%
- Towers
- 3
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 2
Construction progress of Haware Nakshatra Phase 4, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| Bldg No 21 | 0% | 0% | 0% | 0% |
| Bldg No 23 | 0% | 0% | 0% | 0% |
| Bldg No 29 | 0% | 0% | 0% | 0% |
Commencement certificate (CC), as filed on MahaRERA
- Bldg No 21: covers 16 floors
- Bldg No 23: covers 8 floors
- Bldg No 29: covers 12 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Haware Nakshatra Phase 4 every 1–2 months.
Haware Nakshatra Phase 4: buildings, flats and land, as filed on MahaRERA
- Buildings: Bldg No 21 (6 floors, 192 units) · Bldg No 23 (6 floors, 37 units) · Bldg No 29 (5 floors, 140 units)
- Land: 4,002 sq m (about 1.0 acres) · sanctioned built-up 4,561 sq m · recreational space 402 sq m
- Land, as filed: 66/1
- Map: Get directions
The builder’s record and reviews
Haware Properties (a group of 7 linked companies) has 26 projects on MahaRERA since 2017, this one included. Of the 26 GharKundli has checked: 5 finished, all within the promised date; 18 still being built, 1 past the promised date (typically 6 months late); 3 lapsed. 11 complaints on MahaRERA across 10 projects.
Read Google reviews of Haware Nakshatra Phase 4 →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Haware Nakshatra Phase 4: buyers & owners
Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.
Common questions about Haware Nakshatra Phase 4
What is the possession date of Haware Nakshatra Phase 4?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for Haware Nakshatra Phase 4 in Opp Dandekar College, Palghar is 30 April 2027, including MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for Haware Nakshatra Phase 4?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Haware Nakshatra Phase 4's builder has filed on MahaRERA, the official one, is 30 April 2027, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
What is the RERA number of Haware Nakshatra Phase 4?
According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of Haware Nakshatra Phase 4 in Opp Dandekar College, Palghar is P99000022324.
Is Haware Nakshatra Phase 4 registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), Haware Nakshatra Phase 4 is registered as P99000022324 and its status is "Registered and active".
What is the current construction status of Haware Nakshatra Phase 4? How much work is done?
According to GharKundli's check of MahaRERA records (updated November 2026), Haware Nakshatra Phase 4's status on MahaRERA is "Registered and active". As filed by the builder, slab work is 0% done across 3 towers. GharKundli's full report compares construction progress with the deadline.
Does Haware Nakshatra Phase 4 have complaints on MahaRERA?
No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.
Is Haware Nakshatra Phase 4 safe to buy?
According to GharKundli's check of MahaRERA records (updated November 2026), Haware Nakshatra Phase 4 is registered on MahaRERA as P99000022324, its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How much GST is payable on a flat in Haware Nakshatra Phase 4?
Haware Nakshatra Phase 4 is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) inside the Mumbai Metropolitan Region, or 90 sq m elsewhere, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.
What is the stamp duty and registration cost for a flat in Haware Nakshatra Phase 4?
In Maharashtra, stamp duty is between 3% and 7% of the agreement value (or the ready reckoner value, if higher), depending on the city's local cesses: about 6–7% in big cities, less in municipal-council and village areas. A woman buying in her own name pays 1% less. Registration is 1%, capped at ₹30,000. GharKundli's property cost calculator works it out for the price of a flat in Haware Nakshatra Phase 4: gharkundli.com/tools/property-cost-calculator
Has Haware Nakshatra Phase 4 received its OC? Is it ready to move in?
Not yet. According to GharKundli's check of MahaRERA records (updated November 2026), Haware Nakshatra Phase 4 is still under construction, with 30 April 2027 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.
Has Haware Nakshatra Phase 4 uploaded its title report on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), no title report for Haware Nakshatra Phase 4 was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.
No title report is on MahaRERA for this project. See which documents are missing →
Does Haware Nakshatra Phase 4 have other wings or phases?
Yes. MahaRERA lists 2 other registrations of the same project, each with its own possession date: Haware Nakshatra Phase 2 (P99000022309, possession 30 Dec 2021); Haware Nakshatra Phase 3 (P99000022307, possession 30 Apr 2027). Check that your agreement names the registration of your own wing.
How can I get updates if Haware Nakshatra Phase 4's possession date changes?
The latest dates are on Haware Nakshatra Phase 4's MahaRERA page (P99000022324). GharKundli's Kundli Watch sends a free WhatsApp update on Haware Nakshatra Phase 4 every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Haware Nakshatra Phase 4 have?
According to GharKundli's check of MahaRERA records (updated November 2026), Haware Nakshatra Phase 4 has 3 buildings filed: Bldg No 21 with 6 floors and 192 units; Bldg No 23 with 6 floors and 37 units; Bldg No 29 with 5 floors and 140 units.
How big is the land of Haware Nakshatra Phase 4?
According to GharKundli's check of MahaRERA records (updated November 2026), Haware Nakshatra Phase 4 stands on 4,002 sq m of land (about 1.0 acres), with 4,561 sq m of sanctioned built-up area and 402 sq m of recreational open space.
What is the track record of Haware Nakshatra Phase 4's builder?
According to GharKundli's check of MahaRERA records (updated November 2026), Haware Properties (a group of 7 linked companies) has 26 projects on MahaRERA since 2017, this one included. Of the 26 GharKundli has checked: 5 finished, all within the promised date; 18 still being built, 1 past the promised date (typically 6 months late); 3 lapsed. 11 complaints on MahaRERA across 10 projects. GharKundli's full report covers the builder's record in detail.
What are the reviews of Haware Nakshatra Phase 4?
Google Maps has reviews of Haware Nakshatra Phase 4 written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
What is the address and pincode of Haware Nakshatra Phase 4?
Haware Nakshatra Phase 4 by Haware Infotech Ltd is in Opp Dandekar College, Palghar, pincode 401404, Maharashtra, and is registered on MahaRERA as P99000022324, per GharKundli's check of MahaRERA records. Its land is filed as 66/1. GharKundli lists all 621 MahaRERA projects in Palghar (401404).
How many flats are in Haware Nakshatra Phase 4, and how many are sold?
According to GharKundli's check of MahaRERA records (updated November 2026), Haware Nakshatra Phase 4 has 342 homes in 3 towers registered on MahaRERA, and 0% of them are sold or booked.
When was Haware Nakshatra Phase 4 registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), Haware Nakshatra Phase 4 was registered on MahaRERA on 16 September 2019. GharKundli did not find a title report on the land on file there.
Does Haware Nakshatra Phase 4 have any legal issues or court cases?
No court cases are listed for Haware Nakshatra Phase 4 on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).
Who is the builder / developer of Haware Nakshatra Phase 4?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is Haware Infotech Ltd, which has 2 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of Haware Nakshatra Phase 4
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2027 in Palghar →
Other projects in Palghar
- Haware Nakshatra Phase 3
- Haware Nakshatra Phase 2
- Sunshine Complex
- Elite Residency
- V Square Arcade
- Rubicon Shinde Heritage
- Kusum Ekdant
- Paramount Enclave Phase - 2
Other projects by Haware Infotech Ltd
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.