How the possession date of ESHAN CULTURE has moved
31 December 2019
Completion date given when the project was registered
29 February 2024
Extended at the builder's request (MahaRERA application EXT52100013973)
Reason the builder gave MahaRERA: “Extension to the project”
Source: ESHAN CULTURE’s extension records on MahaRERA (P52100009970), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on ESHAN CULTURE
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the February 2024 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P52100009970
- Status
- Completed
- Builder
- ESHAN DEVELOPERS
- Location
- Mamurdi, Pune · 412101
- Project type
- Residential / Group Housing
- Registered on
- 23 Aug 2017
- Completion date at registration
- December 2019
- Latest completion date
- February 2024
- Delay so far
- 50 months
- Homes
- 19
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 2
Construction progress of ESHAN CULTURE, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| ESSAN CULTURE | 100% | 90% | 70% | 70% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on ESHAN CULTURE every month.
ESHAN CULTURE: buildings, flats and land, as filed on MahaRERA
- Buildings: ESSAN CULTURE (6 floors)
- Land: 624 sq m (about 0.2 acres) · sanctioned built-up 531 sq m
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of ESHAN CULTURE →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
ESHAN CULTURE: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about ESHAN CULTURE
What is the possession date of ESHAN CULTURE?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for ESHAN CULTURE in Mamurdi, Pune is 29 February 2024 — 50 months later than 31 December 2019, the date given at registration.
Is the builder's possession date different from the MahaRERA date for ESHAN CULTURE?
Builders and listing sites often quote an earlier "target" date for handover. The completion date ESHAN CULTURE's builder has filed on MahaRERA, the official one, is 29 February 2024, already 50 months later than the 31 December 2019 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of ESHAN CULTURE extended?
According to GharKundli's check of MahaRERA records (updated November 2026), ESHAN CULTURE's builder applied to MahaRERA to extend the completion date once: to 29 February 2024, giving the reason "Extension to the project".
What is the RERA number of ESHAN CULTURE?
According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of ESHAN CULTURE in Mamurdi, Pune is P52100009970.
Is ESHAN CULTURE registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), ESHAN CULTURE is registered as P52100009970 and its status is "Completed".
What is the construction status of ESHAN CULTURE?
According to GharKundli's check of MahaRERA records (updated November 2026), ESHAN CULTURE's status on MahaRERA is "Completed". As filed by the builder, slab work on ESSAN CULTURE is 90% done and internal work 70%. GharKundli's full report compares construction progress with the deadline.
Does ESHAN CULTURE have complaints on MahaRERA?
No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.
Is ESHAN CULTURE safe to buy?
According to GharKundli's check of MahaRERA records (updated November 2026), ESHAN CULTURE is registered on MahaRERA as P52100009970, its MahaRERA status is "Completed", its completion date has moved 50 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if ESHAN CULTURE's possession date changes?
The latest dates are on ESHAN CULTURE's MahaRERA page (P52100009970). GharKundli's Kundli Watch sends a free WhatsApp update on ESHAN CULTURE every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does ESHAN CULTURE have?
According to GharKundli's check of MahaRERA records (updated November 2026), ESHAN CULTURE has one building filed: ESSAN CULTURE with 6 floors.
How big is the land of ESHAN CULTURE?
According to GharKundli's check of MahaRERA records (updated November 2026), ESHAN CULTURE stands on 624 sq m of land (about 0.2 acres), with 531 sq m of sanctioned built-up area.
Where can I read reviews of ESHAN CULTURE?
Google Maps has reviews of ESHAN CULTURE written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is ESHAN CULTURE?
ESHAN CULTURE by ESHAN DEVELOPERS is in Mamurdi, Pune (pincode 412101), Maharashtra, and is registered on MahaRERA as P52100009970, per GharKundli's check of MahaRERA records.
How many homes are in ESHAN CULTURE?
According to GharKundli's check of MahaRERA records (updated November 2026), ESHAN CULTURE has 19 homes in 1 tower registered on MahaRERA.
When was ESHAN CULTURE registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), ESHAN CULTURE was registered on MahaRERA on 23 August 2017. GharKundli did not find a title report on the land on file there.
Are there court cases on ESHAN CULTURE?
No court cases are listed for ESHAN CULTURE on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).
Who is the builder of ESHAN CULTURE?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is ESHAN DEVELOPERS, which has 2 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of ESHAN CULTURE
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in Mamurdi
- My Home Sanctuary Phase I
- My Home Sanctuary Phase 2
- G.N. HEIGHTS
- Lotus Florina
- Midori Towers
- Godrej Nurture
- Life Canvas Phase 1
- Shilp Shantivan
Other projects by ESHAN DEVELOPERS
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.