Shiv Sai Krupa

by KT CONSTRUCTION & DEVELOPERS · Bhise Colony, Talegaon, Pune 410507

What’s in the report? →

Possession date of Shiv Sai Krupa (MahaRERA P52100016069): 30 January 2023, and it has already passed. It has 16 homes. No complaints on MahaRERA. How to check it yourself

Registered on MahaRERA under P52100016069. Status: Lapsed (registration period ended).

Source: MahaRERA website — records for P52100016069, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

The latest completion date on MahaRERA (January 2023) has passed.

What do you want to know about Shiv Sai Krupa?

Completion date nikal chuki hai. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

GharKundli’s full report on Shiv Sai Krupa

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the January 2023 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P52100016069
Status
Lapsed (registration period ended)
Builder
KT CONSTRUCTION & DEVELOPERS
Location
Bhise Colony, Talegaon, Pune · 410507
Project type
Residential / Group Housing
Registered on
16 Apr 2018
Completion date at registration
January 2023
Latest completion date
January 2023
Homes
16
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found

Construction progress of Shiv Sai Krupa, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
SHIV SAI KRUPA0%0%0%0%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Shiv Sai Krupa every 1–2 months.

Shiv Sai Krupa: buildings, flats and land, as filed on MahaRERA

  • Buildings: SHIV SAI KRUPA (5 floors)
  • Land: 470 sq m (about 0.1 acres) · sanctioned built-up 564 sq m · recreational space 290 sq m
  • Land, as filed: PLOT NO 36, SR NO 51,70 AND 71
  • Map: Get directions

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of Shiv Sai Krupa →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Shiv Sai Krupa: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about Shiv Sai Krupa

What is the possession date of Shiv Sai Krupa?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for Shiv Sai Krupa in Bhise Colony, Talegaon, Pune is 30 January 2023. That date has already passed.

Is the builder's possession date different from the MahaRERA date for Shiv Sai Krupa?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Shiv Sai Krupa's builder has filed on MahaRERA, the official one, is 30 January 2023, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

What is the RERA number of Shiv Sai Krupa?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of Shiv Sai Krupa in Bhise Colony, Talegaon, Pune is P52100016069.

Is Shiv Sai Krupa registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Shiv Sai Krupa is registered as P52100016069 and its status is "Lapsed (registration period ended)".

What is the current construction status of Shiv Sai Krupa? How much work is done?

According to GharKundli's check of MahaRERA records (updated November 2026), Shiv Sai Krupa's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work on SHIV SAI KRUPA is 0% done and internal work 0%. GharKundli's full report compares construction progress with the deadline.

Does Shiv Sai Krupa have complaints on MahaRERA?

No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.

Is Shiv Sai Krupa safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), Shiv Sai Krupa is registered on MahaRERA as P52100016069, its MahaRERA status is "Lapsed (registration period ended)", its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in Shiv Sai Krupa?

Shiv Sai Krupa isn't marked completed on MahaRERA, so until the occupancy certificate is issued GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 90 sq m (about 969 sq ft) outside the Mumbai region, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.

What is the stamp duty and registration cost for a flat in Shiv Sai Krupa?

In Maharashtra, stamp duty is between 3% and 7% of the agreement value (or the ready reckoner value, if higher), depending on the city's local cesses: about 6–7% in big cities, less in municipal-council and village areas. A woman buying in her own name pays 1% less. Registration is 1%, capped at ₹30,000. GharKundli's property cost calculator works it out for the price of a flat in Shiv Sai Krupa: gharkundli.com/tools/property-cost-calculator

Has Shiv Sai Krupa received its OC? Is it ready to move in?

Not yet. According to GharKundli's check of MahaRERA records (updated November 2026), Shiv Sai Krupa isn't completed: its MahaRERA status is "Lapsed (registration period ended)", with 30 January 2023 as the latest completion date filed on MahaRERA, and that date has passed. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.

What does "lapsed" mean for Shiv Sai Krupa?

According to GharKundli's check of MahaRERA records (updated November 2026), Shiv Sai Krupa's registration shows as lapsed on MahaRERA. Lapsed means the completion date on MahaRERA (30 January 2023) passed without the project being marked complete or the registration being extended. Before paying anything, ask the builder in writing whether an extension has been applied for.

Has Shiv Sai Krupa uploaded its title report on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), no title report for Shiv Sai Krupa was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.

No title report is on MahaRERA for this project. See which documents are missing →

How can I get updates if Shiv Sai Krupa's possession date changes?

The latest dates are on Shiv Sai Krupa's MahaRERA page (P52100016069). GharKundli's Kundli Watch sends a free WhatsApp update on Shiv Sai Krupa every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Shiv Sai Krupa have?

According to GharKundli's check of MahaRERA records (updated November 2026), Shiv Sai Krupa has one building filed: SHIV SAI KRUPA with 5 floors.

How big is the land of Shiv Sai Krupa?

According to GharKundli's check of MahaRERA records (updated November 2026), Shiv Sai Krupa stands on 470 sq m of land (about 0.1 acres), with 564 sq m of sanctioned built-up area and 290 sq m of recreational open space.

What are the reviews of Shiv Sai Krupa?

Google Maps has reviews of Shiv Sai Krupa written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of Shiv Sai Krupa?

Shiv Sai Krupa by KT CONSTRUCTION & DEVELOPERS is in Bhise Colony, Talegaon, Pune, pincode 410507, Maharashtra, and is registered on MahaRERA as P52100016069, per GharKundli's check of MahaRERA records. Its land is filed as PLOT NO 36, SR NO 51,70 AND 71. GharKundli lists all 236 MahaRERA projects in Talegaon G H (410507).

How many flats are in Shiv Sai Krupa?

According to GharKundli's check of MahaRERA records (updated November 2026), Shiv Sai Krupa has 16 homes in 1 tower registered on MahaRERA.

When was Shiv Sai Krupa registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Shiv Sai Krupa was registered on MahaRERA on 16 April 2018. GharKundli did not find a title report on the land on file there.

Does Shiv Sai Krupa have any legal issues or court cases?

No court cases are listed for Shiv Sai Krupa on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).

Who is the builder / developer of Shiv Sai Krupa?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is KT CONSTRUCTION & DEVELOPERS.

Other projects in Mawal

All 236 projects in Talegaon G H (410507) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.