What’s in the report? →Possession date of Gagan Klara (MahaRERA P52100019739): 30 March 2026, moved from 30 March 2024 (24 months later), and it has already passed. It has 340 homes, 83% sold or booked. 47 complaints on MahaRERA. How to check it yourself
Registered on MahaRERA under P52100019739. Status: Lapsed (registration period ended). MahaRERA has issued a regulatory order on this project.
Source: MahaRERA website — records for P52100019739, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.
The latest completion date on MahaRERA (March 2026) has passed.
What do you want to know about Gagan Klara?
Completion date nikal chuki hai. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.
How the possession date of Gagan Klara has moved
30 March 2024
Completion date given when the project was registered
30 March 2025
Extended at the builder's request (MahaRERA application EXT52100019238)
Reason the builder gave MahaRERA:
“1) We are the Promoters of the Real Estate Project known as “GAGAN KLARA” under implementation by us on land admeasuring 00 H 89 Ares bearing Survey Nos. 38 Hissa No. 8A situate, lying and being at village Balewadi within the Registration S…” Read the full reason
“1) We are the Promoters of the Real Estate Project known as “GAGAN KLARA” under implementation by us on land admeasuring 00 H 89 Ares bearing Survey Nos. 38 Hissa No. 8A situate, lying and being at village Balewadi within the Registration Sub- District of Taluka Haveli, District- Pune. You were kind enough to grant Registration of the said Project vide your Registration Certificate No. P52100019739 dated 05/03/2019. 2) In anticipation that we would complete the said Project on or before 30/03/2024, in our application to you for Registration of our Project, we had mentioned the date of Compl…”30 March 2026
Extended at the builder's request (MahaRERA application EXT52100028041)
Reason the builder gave MahaRERA:
“We have received the part occupancy certificate bearing no. OCC/0589/24 on dated 21/08/2024 for building D. And we are in process of obtaining all NOC’s required for application of Completion Certificate to obtain the full occupancy certifi…” Read the full reason
“We have received the part occupancy certificate bearing no. OCC/0589/24 on dated 21/08/2024 for building D. And we are in process of obtaining all NOC’s required for application of Completion Certificate to obtain the full occupancy certificate for building A, B and C at earliest. Hence the completion of the project was delayed and we require extension.”
Source: Gagan Klara’s extension records on MahaRERA (P52100019739), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Gagan Klara
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 47 complaints, and how it ended
- Construction pace against the March 2026 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P52100019739
- Status
- Lapsed (registration period ended)
- Builder
- Gagan Housing And Landmarks LLP
- Location
- Balewadi, Pune · 411045
- Project type
- Others
- Registered on
- 5 Mar 2019
- Completion date at registration
- March 2024
- Latest completion date
- March 2026
- Delay so far
- 24 months
- Homes
- 340
- Sold or booked
- 83%
- Towers
- 4
- Complaints on MahaRERA
- 47
- Court cases listed
- 0
- MahaRERA regulatory orders
- 1
- Title report on file
- Not found
Construction progress of Gagan Klara, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| Building D - Commercial And MHADA | 100% | 100% | 75% | 30% |
| Wing A | 100% | 100% | 100% | 97% |
| Wing B | 100% | 100% | 96% | 96% |
| Wing C | 100% | 100% | 100% | 96% |
Commencement certificate (CC), as filed on MahaRERA
- Building D - Commercial And MHADA: covers 14 floors
- Wing A: covers 25 floors
- Wing B: covers 25 floors
- Wing C: covers 25 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Gagan Klara every 1–2 months.
Gagan Klara: buildings, flats and land, as filed on MahaRERA
- Buildings: Building D - Commercial And MHADA (14 floors, 121 units) · Wing A (25 floors, 84 units) · Wing B (25 floors, 84 units) · Wing C (25 floors, 84 units)
- Land: 8,900 sq m (about 2.2 acres) · sanctioned built-up 28,352 sq m · recreational space 829 sq m
- Land, as filed: Survey No 38 Hissa No 8A Balewadi
- Map: Get directions
The builder’s record and reviews
Gagan Landmarks (a group of 8 linked companies) has 12 projects on MahaRERA since 2017, this one included. Of the 12 GharKundli has checked: 2 finished, 0 within the promised date and 2 needed more time (typically 30 months); 5 still being built, 2 past the promised date (typically 18 months late); 5 lapsed. 103 complaints on MahaRERA across 9 projects.
Read Google reviews of Gagan Klara →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Gagan Klara: buyers & owners
Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.
Common questions about Gagan Klara
What is the possession date of Gagan Klara?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Gagan Klara in Balewadi, Pune is 30 March 2026 — 24 months later than 30 March 2024, the date given at registration. That date has already passed.
The date has already moved 24 months. Will it move again? Check the real pace of construction →
Is the builder's possession date different from the MahaRERA date for Gagan Klara?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Gagan Klara's builder has filed on MahaRERA, the official one, is 30 March 2026, already 24 months later than the 30 March 2024 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Gagan Klara extended?
According to GharKundli's check of MahaRERA records (updated October 2026), Gagan Klara's builder applied to MahaRERA to extend the completion date 2 times: to 30 March 2025, giving the reason "1) We are the Promoters of the Real Estate Project known as “GAGAN KLARA” under implementation by us on land admeasuring 00 H 89 Ares bearing Survey Nos. 38 Hissa No. 8A situate, lying and being at village Balewadi within the Registration Sub- District of Taluka Haveli, District- Pune. You were kind enough to grant Registration of the said Project vide your Registration Certificate No. P52100019739 dated 05/03/2019. 2) In anticipation that we would complete the said Project on or before 30/03/2024, in our application to you for Registration of our Project, we had mentioned the date of Compl…"; to 30 March 2026, giving the reason "We have received the part occupancy certificate bearing no. OCC/0589/24 on dated 21/08/2024 for building D. And we are in process of obtaining all NOC’s required for application of Completion Certificate to obtain the full occupancy certificate for building A, B and C at earliest. Hence the completion of the project was delayed and we require extension.".
What is the RERA number of Gagan Klara?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Gagan Klara in Balewadi, Pune is P52100019739.
Is Gagan Klara registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Gagan Klara is registered as P52100019739 and its status is "Lapsed (registration period ended)".
What is the current construction status of Gagan Klara? How much work is done?
According to GharKundli's check of MahaRERA records (updated October 2026), Gagan Klara's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work is 100% done across 4 towers. GharKundli's full report compares construction progress with the deadline.
Does Gagan Klara have complaints on MahaRERA?
47 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
47 complaints are filed on this project. Know what went wrong before you pay a token. See how each complaint ended →
Is Gagan Klara safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Gagan Klara is registered on MahaRERA as P52100019739, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 24 months since registration and 47 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How much GST is payable on a flat in Gagan Klara?
Gagan Klara isn't marked completed on MahaRERA, so until the occupancy certificate is issued GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 90 sq m (about 969 sq ft) outside the Mumbai region, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.
What is the stamp duty and registration cost for a flat in Gagan Klara?
In Maharashtra, stamp duty is between 3% and 7% of the agreement value (or the ready reckoner value, if higher), depending on the city's local cesses: about 6–7% in big cities, less in municipal-council and village areas. A woman buying in her own name pays 1% less. Registration is 1%, capped at ₹30,000. GharKundli's property cost calculator works it out for the price of a flat in Gagan Klara: gharkundli.com/tools/property-cost-calculator
Has Gagan Klara received its OC? Is it ready to move in?
Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Gagan Klara isn't completed: its MahaRERA status is "Lapsed (registration period ended)", with 30 March 2026 as the latest completion date filed on MahaRERA, and that date has passed. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.
What does "lapsed" mean for Gagan Klara?
According to GharKundli's check of MahaRERA records (updated October 2026), Gagan Klara's registration shows as lapsed on MahaRERA. Lapsed means the completion date on MahaRERA (30 March 2026) passed without the project being marked complete or the registration being extended. Before paying anything, ask the builder in writing whether an extension has been applied for.
Has Gagan Klara uploaded its title report on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Gagan Klara was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.
No title report is on MahaRERA for this project. See which documents are missing →
How can I get updates if Gagan Klara's possession date changes?
The latest dates are on Gagan Klara's MahaRERA page (P52100019739). GharKundli's Kundli Watch sends a free WhatsApp update on Gagan Klara every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Gagan Klara have?
According to GharKundli's check of MahaRERA records (updated October 2026), Gagan Klara has 4 buildings filed: Building D - Commercial And MHADA with 14 floors and 121 units; Wing A with 25 floors and 84 units; Wing B with 25 floors and 84 units; Wing C with 25 floors and 84 units.
How big is the land of Gagan Klara?
According to GharKundli's check of MahaRERA records (updated October 2026), Gagan Klara stands on 8,900 sq m of land (about 2.2 acres), with 28,352 sq m of sanctioned built-up area and 829 sq m of recreational open space.
What is the track record of Gagan Klara's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Gagan Landmarks (a group of 8 linked companies) has 12 projects on MahaRERA since 2017, this one included. Of the 12 GharKundli has checked: 2 finished, 0 within the promised date and 2 needed more time (typically 30 months); 5 still being built, 2 past the promised date (typically 18 months late); 5 lapsed. 103 complaints on MahaRERA across 9 projects. GharKundli's full report covers the builder's record in detail.
What are the reviews of Gagan Klara?
Google Maps has reviews of Gagan Klara written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 47 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
What is the address and pincode of Gagan Klara?
Gagan Klara by Gagan Housing And Landmarks LLP is in Balewadi, Pune, pincode 411045, Maharashtra, and is registered on MahaRERA as P52100019739, per GharKundli's check of MahaRERA records. Its land is filed as Survey No 38 Hissa No 8A Balewadi. GharKundli lists all 713 MahaRERA projects in Baner (411045).
How many flats are in Gagan Klara, and how many are sold?
According to GharKundli's check of MahaRERA records (updated October 2026), Gagan Klara has 340 homes in 4 towers registered on MahaRERA, and 83% of them are sold or booked.
When was Gagan Klara registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Gagan Klara was registered on MahaRERA on 5 March 2019. GharKundli did not find a title report on the land on file there.
Does Gagan Klara have any legal issues or court cases?
No court cases are listed for Gagan Klara on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder / developer of Gagan Klara?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Gagan Housing And Landmarks LLP.
Check it yourself on MahaRERA
- How to check the possession date of Gagan Klara
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2026 in Pune →
Other projects in Baner (411045)
- One 45
- Palladio Presidential Suites Balewadi RiverFront
- Rohan Ekam Phase 1
- Galaxis Biz Port
- Lake Ridge City
- Kakkad Oneworld
- Signis
- Dream Velmore
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.