Vanalika - Paradise - Phase - Iii-3a
by M/S. AVIOR MAJESTIQUE PROPERTIES · Paud Road, Pune 412108
What’s in the report? →Possession date of Vanalika - Paradise - Phase - Iii-3a (MahaRERA P52100019038): 30 April 2028, moved from 30 December 2024 (36 months later). It has 166 homes, 98% sold or booked. No complaints on MahaRERA. How to check it yourself
Registered on MahaRERA under P52100019038, and currently active. Its completion date has moved from December 2024 to April 2028: 36 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.
Source: MahaRERA website — records for P52100019038, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.
What do you want to know about Vanalika - Paradise - Phase - Iii-3a?
Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.
How the possession date of Vanalika - Paradise - Phase - Iii-3a has moved
30 December 2024
Completion date given when the project was registered
30 December 2025
Extended at the builder's request (MahaRERA application EXT52100025233)
Reason the builder gave MahaRERA:
“As we are completed the said Project construction up to 93%. Thus due to the lebour's problems and material shortage, this has been causing delay in completing the remaining construction of the said Project and taking completion certificate…” Read the full reason
“As we are completed the said Project construction up to 93%. Thus due to the lebour's problems and material shortage, this has been causing delay in completing the remaining construction of the said Project and taking completion certificate.”31 December 2027
Extended at the builder's request (MahaRERA application EA14052620955)
Reason the builder gave MahaRERA:
“Due to acute shortage of construction materials in the market and persistent labour issues including non-availability of skilled and unskilled workers during the course of the project, the construction of Vanalika Project has been delayed.…” Read the full reason
“Due to acute shortage of construction materials in the market and persistent labour issues including non-availability of skilled and unskilled workers during the course of the project, the construction of Vanalika Project has been delayed. These factors are beyond the control of the promoter, because of this reason it has become necessary for us to seek for extension of the project”30 April 2028
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: Vanalika - Paradise - Phase - Iii-3a’s extension records on MahaRERA (P52100019038), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Vanalika - Paradise - Phase - Iii-3a
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the April 2028 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
Other wings and phases of this project
Each is registered on MahaRERA separately, with its own possession date. Check the one your flat is in.
- VANALIKA-PARADISE- III -3BP52100016963 · possession 30 Dec 2023
- MahaRERA registration
- P52100019038
- Status
- Registered and active
- Builder
- M/S. AVIOR MAJESTIQUE PROPERTIES
- Location
- Paud Road, Pune · 412108
- Project type
- Residential / Group Housing
- Registered on
- 28 Dec 2018
- Completion date at registration
- December 2024
- Latest completion date
- April 2028
- Delay so far
- 36 months
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 166
- Sold or booked
- 98%
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 2
Construction progress of Vanalika - Paradise - Phase - Iii-3a, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| BUILDING - 3A | 100% | 100% | 100% | 100% |
Commencement certificate (CC), as filed on MahaRERA
- BUILDING - 3A: covers 16 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Vanalika - Paradise - Phase - Iii-3a every 1–2 months.
Vanalika - Paradise - Phase - Iii-3a: buildings, flats and land, as filed on MahaRERA
- Buildings: BUILDING - 3A (16 floors, 166 units)
- Land: 5,436 sq m (about 1.3 acres) · sanctioned built-up 6,736 sq m · recreational space 544 sq m
- Land, as filed: GAT NO. 124 -PART
- Map: Get directions
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of Vanalika - Paradise - Phase - Iii-3a →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Vanalika - Paradise - Phase - Iii-3a: buyers & owners
Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.
Common questions about Vanalika - Paradise - Phase - Iii-3a
What is the possession date of Vanalika - Paradise - Phase - Iii-3a?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Vanalika - Paradise - Phase - Iii-3a in Paud Road, Pune is 30 April 2028 — 36 months later than 30 December 2024, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.
The date has already moved 36 months. Will it move again? Check the real pace of construction →
Is the builder's possession date different from the MahaRERA date for Vanalika - Paradise - Phase - Iii-3a?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Vanalika - Paradise - Phase - Iii-3a's builder has filed on MahaRERA, the official one, is 30 April 2028, already 36 months later than the 30 December 2024 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Vanalika - Paradise - Phase - Iii-3a extended?
According to GharKundli's check of MahaRERA records (updated October 2026), Vanalika - Paradise - Phase - Iii-3a's builder applied to MahaRERA to extend the completion date 2 times: to 30 December 2025, giving the reason "As we are completed the said Project construction up to 93%. Thus due to the lebour's problems and material shortage, this has been causing delay in completing the remaining construction of the said Project and taking completion certificate."; to 31 December 2027, giving the reason "Due to acute shortage of construction materials in the market and persistent labour issues including non-availability of skilled and unskilled workers during the course of the project, the construction of Vanalika Project has been delayed. These factors are beyond the control of the promoter, because of this reason it has become necessary for us to seek for extension of the project". MahaRERA also added its automatic 4-month extension for all eligible projects.
What is the RERA number of Vanalika - Paradise - Phase - Iii-3a?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Vanalika - Paradise - Phase - Iii-3a in Paud Road, Pune is P52100019038.
Is Vanalika - Paradise - Phase - Iii-3a registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Vanalika - Paradise - Phase - Iii-3a is registered as P52100019038 and its status is "Registered and active".
What is the current construction status of Vanalika - Paradise - Phase - Iii-3a? How much work is done?
According to GharKundli's check of MahaRERA records (updated October 2026), Vanalika - Paradise - Phase - Iii-3a's status on MahaRERA is "Registered and active". As filed by the builder, slab work on BUILDING - 3A is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.
Does Vanalika - Paradise - Phase - Iii-3a have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is Vanalika - Paradise - Phase - Iii-3a safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Vanalika - Paradise - Phase - Iii-3a is registered on MahaRERA as P52100019038, its completion date has moved 36 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How much GST is payable on a flat in Vanalika - Paradise - Phase - Iii-3a?
Vanalika - Paradise - Phase - Iii-3a is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 90 sq m (about 969 sq ft) outside the Mumbai region, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.
What is the stamp duty and registration cost for a flat in Vanalika - Paradise - Phase - Iii-3a?
In Maharashtra, stamp duty is between 3% and 7% of the agreement value (or the ready reckoner value, if higher), depending on the city's local cesses: about 6–7% in big cities, less in municipal-council and village areas. A woman buying in her own name pays 1% less. Registration is 1%, capped at ₹30,000. GharKundli's property cost calculator works it out for the price of a flat in Vanalika - Paradise - Phase - Iii-3a: gharkundli.com/tools/property-cost-calculator
Has Vanalika - Paradise - Phase - Iii-3a received its OC? Is it ready to move in?
Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Vanalika - Paradise - Phase - Iii-3a is still under construction, with 30 April 2028 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.
Has Vanalika - Paradise - Phase - Iii-3a uploaded its title report on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Vanalika - Paradise - Phase - Iii-3a was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.
No title report is on MahaRERA for this project. See which documents are missing →
Does Vanalika - Paradise - Phase - Iii-3a have other wings or phases?
Yes. MahaRERA lists 1 other registration of the same project, each with its own possession date: VANALIKA-PARADISE- III -3B (P52100016963, possession 30 Dec 2023). Check that your agreement names the registration of your own wing.
How can I get updates if Vanalika - Paradise - Phase - Iii-3a's possession date changes?
The latest dates are on Vanalika - Paradise - Phase - Iii-3a's MahaRERA page (P52100019038). GharKundli's Kundli Watch sends a free WhatsApp update on Vanalika - Paradise - Phase - Iii-3a every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Vanalika - Paradise - Phase - Iii-3a have?
According to GharKundli's check of MahaRERA records (updated October 2026), Vanalika - Paradise - Phase - Iii-3a has one building filed: BUILDING - 3A with 16 floors and 166 units.
How big is the land of Vanalika - Paradise - Phase - Iii-3a?
According to GharKundli's check of MahaRERA records (updated October 2026), Vanalika - Paradise - Phase - Iii-3a stands on 5,436 sq m of land (about 1.3 acres), with 6,736 sq m of sanctioned built-up area and 544 sq m of recreational open space.
What are the reviews of Vanalika - Paradise - Phase - Iii-3a?
Google Maps has reviews of Vanalika - Paradise - Phase - Iii-3a written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
What is the address and pincode of Vanalika - Paradise - Phase - Iii-3a?
Vanalika - Paradise - Phase - Iii-3a by M/S. AVIOR MAJESTIQUE PROPERTIES is in Paud Road, Pune, pincode 412108, Maharashtra, and is registered on MahaRERA as P52100019038, per GharKundli's check of MahaRERA records. Its land is filed as GAT NO. 124 -PART. GharKundli lists all 73 MahaRERA projects in Paud (412108).
How many flats are in Vanalika - Paradise - Phase - Iii-3a, and how many are sold?
According to GharKundli's check of MahaRERA records (updated October 2026), Vanalika - Paradise - Phase - Iii-3a has 166 homes in 1 tower registered on MahaRERA, and 98% of them are sold or booked.
When was Vanalika - Paradise - Phase - Iii-3a registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Vanalika - Paradise - Phase - Iii-3a was registered on MahaRERA on 28 December 2018. GharKundli did not find a title report on the land on file there.
Does Vanalika - Paradise - Phase - Iii-3a have any legal issues or court cases?
No court cases are listed for Vanalika - Paradise - Phase - Iii-3a on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder / developer of Vanalika - Paradise - Phase - Iii-3a?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is M/S. AVIOR MAJESTIQUE PROPERTIES, which has 2 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of Vanalika - Paradise - Phase - Iii-3a
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2028 in Pune →
Other projects in Paud (412108)
- Aryan Brentwood
- Foresta Phase I
- Satvam Hills C1
- Satvam Hills B7
- Satvam Hills C5
- Satvam Hills A5
- Satvam Hills A6
- Apex Ambar
Other projects by M/S. AVIOR MAJESTIQUE PROPERTIES
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.