Virmati Villa CHS Ltd
by Shamik Enterprises Pvt Ltd. · Vile Parle East, MumbaiAlso near Borivali West, I C Colony, Kandivali
Possession date of Virmati Villa CHS Ltd: 29 December 2020, moved from 30 June 2019 (18 months later). This is the latest completion date the builder has filed on MahaRERA, and it has already passed. How to check it yourself
Registered on MahaRERA under P51800001564. Status: Lapsed (registration period ended). 5 complaints are listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, November 2026.
The latest completion date on MahaRERA (December 2020) has passed.
On MahaRERA's insolvency (NCLT) list
MahaRERA lists this project among those before the National Company Law Tribunal (NCLT), the insolvency court. Its list shows no completion certificate (Form 4) uploaded. Ask the builder, in writing, about the case before paying anything.
On MahaRERA’s list since at least 23 Oct 2026See MahaRERA’s list
What do you want to know about Virmati Villa CHS Ltd?
How the possession date of Virmati Villa CHS Ltd has moved
30 June 2019
Completion date given when the project was registered
29 June 2020
Extended at the builder's request (MahaRERA application EXT51800001940)
Reason the builder gave MahaRERA:
“The project is registered in MahaRERA vide registration No. P51800001564. The proposed date of completion as per RERA registration is 30/06/2019. The development work of "Virmati Villa Chs Ltd" project is in progress and the entire RCC work…” Read the full reason
“The project is registered in MahaRERA vide registration No. P51800001564. The proposed date of completion as per RERA registration is 30/06/2019. The development work of "Virmati Villa Chs Ltd" project is in progress and the entire RCC work is completed. The brick work and plastering of walls is in progress. The application for extension to CC is submitted to the competent authority to MCGM. The promoter could not complete the work due to site constrains and various other reasons. But now the major RCC work is completed and rest work will be completed in a extended time. Therefore, the prom…”29 December 2020
Revised completion date on MahaRERA
Source: Virmati Villa CHS Ltd’s extension records on MahaRERA (P51800001564), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Virmati Villa CHS Ltd
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 5 complaints, and how it ended
- Construction pace against the December 2020 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51800001564
- Status
- Lapsed (registration period ended)
- Builder
- Shamik Enterprises Pvt Ltd.
- Location
- Vile Parle East, Mumbai · 400103
- Project type
- Residential / Group Housing
- Registered on
- 28 Jul 2017
- Completion date at registration
- June 2019
- Latest completion date
- December 2020
- Delay so far
- 18 months
- Homes
- 14
- Towers
- 1
- Complaints on MahaRERA
- 5
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 7
Construction progress of Virmati Villa CHS Ltd, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| Shamik Esteem | 100% | 100% | 28% | 0% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Virmati Villa CHS Ltd every month.
Virmati Villa CHS Ltd: buildings, flats and land, as filed on MahaRERA
- Buildings: Shamik Esteem (16 floors)
- Land: 424 sq m (about 0.1 acres) · sanctioned built-up 1,139 sq m
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
Shamik Enterprises has 8 projects on MahaRERA since 2017, this one included. Of the 6 GharKundli has checked: 4 finished, 0 within the promised date and 4 needed more time (typically 10 months); 2 lapsed. 7 complaints on MahaRERA across 2 projects.
Read Google reviews of Virmati Villa CHS Ltd →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Virmati Villa CHS Ltd: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about Virmati Villa CHS Ltd
What is the possession date of Virmati Villa CHS Ltd?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for Virmati Villa CHS Ltd in Vile Parle East, Mumbai is 29 December 2020 — 18 months later than 30 June 2019, the date given at registration. That date has already passed.
Is the builder's possession date different from the MahaRERA date for Virmati Villa CHS Ltd?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Virmati Villa CHS Ltd's builder has filed on MahaRERA, the official one, is 29 December 2020, already 18 months later than the 30 June 2019 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Virmati Villa CHS Ltd extended?
According to GharKundli's check of MahaRERA records (updated November 2026), Virmati Villa CHS Ltd's builder applied to MahaRERA to extend the completion date once: to 29 June 2020, giving the reason "The project is registered in MahaRERA vide registration No. P51800001564. The proposed date of completion as per RERA registration is 30/06/2019. The development work of "Virmati Villa Chs Ltd" project is in progress and the entire RCC work is completed. The brick work and plastering of walls is in progress. The application for extension to CC is submitted to the competent authority to MCGM. The promoter could not complete the work due to site constrains and various other reasons. But now the major RCC work is completed and rest work will be completed in a extended time. Therefore, the prom…".
What is the RERA number of Virmati Villa CHS Ltd?
According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of Virmati Villa CHS Ltd in Vile Parle East, Mumbai is P51800001564.
Is Virmati Villa CHS Ltd registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), Virmati Villa CHS Ltd is registered as P51800001564 and its status is "Lapsed (registration period ended)". On MahaRERA's own list: On MahaRERA's insolvency (NCLT) list. MahaRERA lists this project among those before the National Company Law Tribunal (NCLT), the insolvency court. Its list shows no completion certificate (Form 4) uploaded. Ask the builder, in writing, about the case before paying anything.
What is the construction status of Virmati Villa CHS Ltd?
According to GharKundli's check of MahaRERA records (updated November 2026), Virmati Villa CHS Ltd's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work on Shamik Esteem is 100% done and internal work 28%. GharKundli's full report compares construction progress with the deadline.
Does Virmati Villa CHS Ltd have complaints on MahaRERA?
5 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is Virmati Villa CHS Ltd safe to buy?
According to GharKundli's check of MahaRERA records (updated November 2026), Virmati Villa CHS Ltd is registered on MahaRERA as P51800001564, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 18 months since registration, 5 complaints are listed against it and it is on MahaRERA's list "On MahaRERA's insolvency (NCLT) list". GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if Virmati Villa CHS Ltd's possession date changes?
The latest dates are on Virmati Villa CHS Ltd's MahaRERA page (P51800001564). GharKundli's Kundli Watch sends a free WhatsApp update on Virmati Villa CHS Ltd every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Virmati Villa CHS Ltd have?
According to GharKundli's check of MahaRERA records (updated November 2026), Virmati Villa CHS Ltd has one building filed: Shamik Esteem with 16 floors.
How big is the land of Virmati Villa CHS Ltd?
According to GharKundli's check of MahaRERA records (updated November 2026), Virmati Villa CHS Ltd stands on 424 sq m of land (about 0.1 acres), with 1,139 sq m of sanctioned built-up area.
What is the track record of Virmati Villa CHS Ltd's builder?
According to GharKundli's check of MahaRERA records (updated November 2026), Shamik Enterprises has 8 projects on MahaRERA since 2017, this one included. Of the 6 GharKundli has checked: 4 finished, 0 within the promised date and 4 needed more time (typically 10 months); 2 lapsed. 7 complaints on MahaRERA across 2 projects. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of Virmati Villa CHS Ltd?
Google Maps has reviews of Virmati Villa CHS Ltd written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 5 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is Virmati Villa CHS Ltd?
Virmati Villa CHS Ltd by Shamik Enterprises Pvt Ltd. is in Vile Parle East, Mumbai (pincode 400103), near Borivali West, I C Colony, Kandivali, Maharashtra, and is registered on MahaRERA as P51800001564, per GharKundli's check of MahaRERA records.
How many homes are in Virmati Villa CHS Ltd?
According to GharKundli's check of MahaRERA records (updated November 2026), Virmati Villa CHS Ltd has 14 homes in 1 tower registered on MahaRERA.
When was Virmati Villa CHS Ltd registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), Virmati Villa CHS Ltd was registered on MahaRERA on 28 July 2017. GharKundli did not find a title report on the land on file there.
Are there court cases on Virmati Villa CHS Ltd?
No court cases are listed for Virmati Villa CHS Ltd on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).
Who is the builder of Virmati Villa CHS Ltd?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is Shamik Enterprises Pvt Ltd., which has 7 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of Virmati Villa CHS Ltd
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in Vile Parle East
- Pruthvi Symphony
- PARIMAL
- Sunbeam Emerald
- ZEE HAPPY VEENA
- Nirmaan Heena
- Parleshwar Aangan
- SAI CHAMUNDA
- MOTI MADHAV
Other projects by Shamik Enterprises Pvt Ltd.
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.