What’s in the report? →Possession date of Agami Infinity Park (MahaRERA P99000027009): 30 August 2028. It has 372 homes, 0% sold or booked. No complaints on MahaRERA. How to check it yourself
Registered on MahaRERA under P99000027009, and currently active. Its completion date is now August 2028, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time.
Source: MahaRERA website — records for P99000027009, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.
Deregistered by MahaRERA
MahaRERA has deregistered this project by order. Builders often apply for this themselves when a project doesn't go ahead -- read the order before paying anything.
On MahaRERA’s list since at least 17 Nov 2026See MahaRERA’s list Read the order
What do you want to know about Agami Infinity Park?
MahaRERA ki red-flag list mein hai. Kya jaanna hai?Tap a question. We’ll answer you on WhatsApp, free.
How the possession date of Agami Infinity Park has moved
30 April 2028
Completion date given when the project was registered
30 August 2028
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: Agami Infinity Park’s extension records on MahaRERA (P99000027009), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Agami Infinity Park
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the August 2028 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
Other wings and phases of this project
Each is registered on MahaRERA separately, with its own possession date. Check the one your flat is in.
- AGAMI INFINITY PARKP99000024826 · possession 30 Mar 2025
- Agami Infinity Park 3P99000078729 · possession 30 Apr 2030
- MahaRERA registration
- P99000027009
- Status
- Registered and active
- Builder
- MAYURESH REALTY PRIVATE LIMITED
- Location
- Boisar, Palghar · 401501
- Project type
- Residential / Group Housing
- Registered on
- 10 Nov 2020
- Completion date at registration
- April 2028
- Latest completion date
- August 2028
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 372
- Sold or booked
- 0%
- Towers
- 6
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 1
Construction progress of Agami Infinity Park, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| BUILDING NO 16 H | 0% | 0% | 0% | 0% |
| BUILDING NO 16 H1 | 0% | 0% | 0% | 0% |
| BUILDING NO 17 H | 0% | 0% | 0% | 0% |
| BUILDING NO 17 H1 | 0% | 0% | 0% | 0% |
| BUILDING NO 18 H | 0% | 0% | 0% | 0% |
| BUILDING NO 18 H1 | 0% | 0% | 0% | 0% |
Commencement certificate (CC), as filed on MahaRERA
- BUILDING NO 16 H: covers 7 floors
- BUILDING NO 16 H1: covers 7 floors
- BUILDING NO 17 H: covers 7 floors
- BUILDING NO 17 H1: covers 7 floors
- BUILDING NO 18 H: covers 7 floors
- BUILDING NO 18 H1: covers 7 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Agami Infinity Park every 1–2 months.
Agami Infinity Park: buildings, flats and land, as filed on MahaRERA
- Buildings: BUILDING NO 16 H (9 floors, 62 units) · BUILDING NO 16 H1 (9 floors, 62 units) · BUILDING NO 17 H (9 floors, 62 units) · BUILDING NO 17 H1 (9 floors, 62 units) · BUILDING NO 18 H (9 floors, 62 units) · BUILDING NO 18 H1 (9 floors, 62 units)
- Land: 18,618 sq m (about 4.6 acres) · sanctioned built-up 18,618 sq m · recreational space 3,838 sq m
- Map: Get directions
The builder’s record and reviews
Agami Enterprises (a group of 4 linked companies) has 7 projects on MahaRERA since 2019, this one included. Of the 7 GharKundli has checked: 1 finished, all within the promised date; 5 still being built, none past the promised date yet; 1 lapsed. 1 complaint on MahaRERA across 1 project.
Read Google reviews of Agami Infinity Park →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Agami Infinity Park: buyers & owners
Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.
Common questions about Agami Infinity Park
What is the possession date of Agami Infinity Park?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for Agami Infinity Park in Boisar, Palghar is 30 August 2028, including MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for Agami Infinity Park?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Agami Infinity Park's builder has filed on MahaRERA, the official one, is 30 August 2028, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
What is the RERA number of Agami Infinity Park?
According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of Agami Infinity Park in Boisar, Palghar is P99000027009.
Is Agami Infinity Park registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), Agami Infinity Park is registered as P99000027009 and its status is "Registered and active". On MahaRERA's own list: Deregistered by MahaRERA. MahaRERA has deregistered this project by order. Builders often apply for this themselves when a project doesn't go ahead -- read the order before paying anything.
What is the current construction status of Agami Infinity Park? How much work is done?
According to GharKundli's check of MahaRERA records (updated November 2026), Agami Infinity Park's status on MahaRERA is "Registered and active". As filed by the builder, slab work is 0% done across 6 towers. GharKundli's full report compares construction progress with the deadline.
Does Agami Infinity Park have complaints on MahaRERA?
No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.
Is Agami Infinity Park safe to buy?
According to GharKundli's check of MahaRERA records (updated November 2026), Agami Infinity Park is registered on MahaRERA as P99000027009, its completion date has not been moved by the builder, no complaints are listed against it and it is on MahaRERA's list "Deregistered by MahaRERA". GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How much GST is payable on a flat in Agami Infinity Park?
Agami Infinity Park is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) inside the Mumbai Metropolitan Region, or 90 sq m elsewhere, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.
What is the stamp duty and registration cost for a flat in Agami Infinity Park?
In Maharashtra, stamp duty is between 3% and 7% of the agreement value (or the ready reckoner value, if higher), depending on the city's local cesses: about 6–7% in big cities, less in municipal-council and village areas. A woman buying in her own name pays 1% less. Registration is 1%, capped at ₹30,000. GharKundli's property cost calculator works it out for the price of a flat in Agami Infinity Park: gharkundli.com/tools/property-cost-calculator
Has Agami Infinity Park received its OC? Is it ready to move in?
Not yet. According to GharKundli's check of MahaRERA records (updated November 2026), Agami Infinity Park is still under construction, with 30 August 2028 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.
Has Agami Infinity Park uploaded its title report on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), no title report for Agami Infinity Park was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.
No title report is on MahaRERA for this project. See which documents are missing →
Does Agami Infinity Park have other wings or phases?
Yes. MahaRERA lists 2 other registrations of the same project, each with its own possession date: AGAMI INFINITY PARK (P99000024826, possession 30 Mar 2025); Agami Infinity Park 3 (P99000078729, possession 30 Apr 2030). Check that your agreement names the registration of your own wing.
How can I get updates if Agami Infinity Park's possession date changes?
The latest dates are on Agami Infinity Park's MahaRERA page (P99000027009). GharKundli's Kundli Watch sends a free WhatsApp update on Agami Infinity Park every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Agami Infinity Park have?
According to GharKundli's check of MahaRERA records (updated November 2026), Agami Infinity Park has 6 buildings filed: BUILDING NO 16 H with 9 floors and 62 units; BUILDING NO 16 H1 with 9 floors and 62 units; BUILDING NO 17 H with 9 floors and 62 units; BUILDING NO 17 H1 with 9 floors and 62 units; BUILDING NO 18 H with 9 floors and 62 units; BUILDING NO 18 H1 with 9 floors and 62 units.
How big is the land of Agami Infinity Park?
According to GharKundli's check of MahaRERA records (updated November 2026), Agami Infinity Park stands on 18,618 sq m of land (about 4.6 acres), with 18,618 sq m of sanctioned built-up area and 3,838 sq m of recreational open space.
What is the track record of Agami Infinity Park's builder?
According to GharKundli's check of MahaRERA records (updated November 2026), Agami Enterprises (a group of 4 linked companies) has 7 projects on MahaRERA since 2019, this one included. Of the 7 GharKundli has checked: 1 finished, all within the promised date; 5 still being built, none past the promised date yet; 1 lapsed. 1 complaint on MahaRERA across 1 project. GharKundli's full report covers the builder's record in detail.
What are the reviews of Agami Infinity Park?
Google Maps has reviews of Agami Infinity Park written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
What is the address and pincode of Agami Infinity Park?
Agami Infinity Park by MAYURESH REALTY PRIVATE LIMITED (Agami) is in Boisar, Palghar, pincode 401501, Maharashtra, and is registered on MahaRERA as P99000027009, per GharKundli's check of MahaRERA records. GharKundli lists all 180 MahaRERA projects in Boisar (401501).
How many flats are in Agami Infinity Park, and how many are sold?
According to GharKundli's check of MahaRERA records (updated November 2026), Agami Infinity Park has 372 homes in 6 towers registered on MahaRERA, and 0% of them are sold or booked.
When was Agami Infinity Park registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), Agami Infinity Park was registered on MahaRERA on 10 November 2020. GharKundli did not find a title report on the land on file there.
Does Agami Infinity Park have any legal issues or court cases?
No court cases are listed for Agami Infinity Park on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).
Who is the builder / developer of Agami Infinity Park?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is MAYURESH REALTY PRIVATE LIMITED, the company Agami files this project under, which has 1 other project registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of Agami Infinity Park
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2028 in Palghar →
Other projects in Boisar (401501)
- Shree Galaxy
- Om Sai Complex
- Yosh Empire
- Shree Aadinath Park
- Mahavir Sapphire
- Value Homes
- Sai Shraddha Apartment
- Luxury Empire Township Phase I
Other projects by MAYURESH REALTY PRIVATE LIMITED
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.