AMBROSIA 13
by THDC NAGRI LLP · Kanchan Universe, Palghar
Possession date of AMBROSIA 13: 30 April 2028, moved from 31 March 2026 (21 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P99000045376, and currently active. Its completion date has moved from March 2026 to April 2028: 21 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about AMBROSIA 13?
How the possession date of AMBROSIA 13 has moved
31 March 2026
Completion date given when the project was registered
31 December 2027
Extended at the builder's request (MahaRERA application EA25022620008)
Reason the builder gave MahaRERA:
“1. While registering the project with MahaRERA,we had underestimated the project completion time which proved to be less for such a project. 2. Also to lack of sales and Financial Difficulties project got delayed 3. Still the project progre…” Read the full reason
“1. While registering the project with MahaRERA,we had underestimated the project completion time which proved to be less for such a project. 2. Also to lack of sales and Financial Difficulties project got delayed 3. Still the project progress was on track but in between due to some issues with our labour contractor led to few months delay of works. 4. But rest assured,now the works are in full swing & will be completed with in the stipulated time lines of this extended date and OC will be obtained. 5. Also,we are uploading the PERTChart/work completion schedule of the project. 6. Hence,we r…”30 April 2028
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: AMBROSIA 13’s extension records on MahaRERA (P99000045376), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on AMBROSIA 13
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the April 2028 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P99000045376
- Status
- Registered and active
- Builder
- THDC NAGRI LLP
- Location
- Kanchan Universe, Palghar · 401402
- Project type
- Residential / Group Housing
- Registered on
- 18 May 2022
- Completion date at registration
- March 2026
- Latest completion date
- April 2028
- Delay so far
- 21 months
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 89
- Sold or booked
- 100%
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of AMBROSIA 13, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| AMBROSIA 13 | 100% | 100% | 75% | 0% |
Commencement certificate (CC), as filed on MahaRERA
- AMBROSIA 13: covers 8 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on AMBROSIA 13 every month.
AMBROSIA 13: buildings, flats and land, as filed on MahaRERA
- Buildings: AMBROSIA 13 (9 floors, 89 units)
- Car parking: 1 covered, 28 open
- Land: 2,843 sq m (about 0.7 acres) · sanctioned built-up 3,127 sq m · recreational space 284 sq m
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of AMBROSIA 13 →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
AMBROSIA 13: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about AMBROSIA 13
What is the possession date of AMBROSIA 13?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for AMBROSIA 13 in Kanchan Universe, Palghar is 30 April 2028 — 21 months later than 31 March 2026, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for AMBROSIA 13?
Builders and listing sites often quote an earlier "target" date for handover. The completion date AMBROSIA 13's builder has filed on MahaRERA, the official one, is 30 April 2028, already 21 months later than the 31 March 2026 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of AMBROSIA 13 extended?
According to GharKundli's check of MahaRERA records (updated October 2026), AMBROSIA 13's builder applied to MahaRERA to extend the completion date once: to 31 December 2027, giving the reason "1. While registering the project with MahaRERA,we had underestimated the project completion time which proved to be less for such a project. 2. Also to lack of sales and Financial Difficulties project got delayed 3. Still the project progress was on track but in between due to some issues with our labour contractor led to few months delay of works. 4. But rest assured,now the works are in full swing & will be completed with in the stipulated time lines of this extended date and OC will be obtained. 5. Also,we are uploading the PERTChart/work completion schedule of the project. 6. Hence,we r…". MahaRERA also added its automatic 4-month extension for all eligible projects.
What is the RERA number of AMBROSIA 13?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of AMBROSIA 13 in Kanchan Universe, Palghar is P99000045376.
Is AMBROSIA 13 registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), AMBROSIA 13 is registered as P99000045376 and its status is "Registered and active".
What is the construction status of AMBROSIA 13?
According to GharKundli's check of MahaRERA records (updated October 2026), AMBROSIA 13's status on MahaRERA is "Registered and active". As filed by the builder, slab work on AMBROSIA 13 is 100% done and internal work 75%. GharKundli's full report compares construction progress with the deadline.
Does AMBROSIA 13 have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is AMBROSIA 13 safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), AMBROSIA 13 is registered on MahaRERA as P99000045376, its completion date has moved 21 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if AMBROSIA 13's possession date changes?
The latest dates are on AMBROSIA 13's MahaRERA page (P99000045376). GharKundli's Kundli Watch sends a free WhatsApp update on AMBROSIA 13 every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does AMBROSIA 13 have?
According to GharKundli's check of MahaRERA records (updated October 2026), AMBROSIA 13 has one building filed: AMBROSIA 13 with 9 floors and 89 units.
How much parking does AMBROSIA 13 have?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 1 covered and 28 open car parking spaces for AMBROSIA 13.
How big is the land of AMBROSIA 13?
According to GharKundli's check of MahaRERA records (updated October 2026), AMBROSIA 13 stands on 2,843 sq m of land (about 0.7 acres), with 3,127 sq m of sanctioned built-up area and 284 sq m of recreational open space.
Where can I read reviews of AMBROSIA 13?
Google Maps has reviews of AMBROSIA 13 written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is AMBROSIA 13?
AMBROSIA 13 by THDC NAGRI LLP is in Kanchan Universe, Palghar (pincode 401402), Maharashtra, and is registered on MahaRERA as P99000045376, per GharKundli's check of MahaRERA records.
How many homes are in AMBROSIA 13?
According to GharKundli's check of MahaRERA records (updated October 2026), AMBROSIA 13 has 89 homes in 1 tower registered on MahaRERA, and 100% of them are sold or booked.
When was AMBROSIA 13 registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), AMBROSIA 13 was registered on MahaRERA on 18 May 2022. GharKundli did not find a title report on the land on file there.
Are there court cases on AMBROSIA 13?
No court cases are listed for AMBROSIA 13 on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder of AMBROSIA 13?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is THDC NAGRI LLP.
Check it yourself on MahaRERA
- How to check the possession date of AMBROSIA 13
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2028 in Palghar →
Other projects in Palghar
- Elite Residency
- Sunshine Complex
- Rubicon Shinde Heritage
- V SQUARE ARCADE
- KUSUM EKDANT
- PARAMOUNT ENCLAVE PHASE - 2
- SAPPHIRE ENCLAVES BLDG NO 5 TYPE F
- K Bafna Estatess
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.