Enigma Towers A and B

by Oberoi Constructions Limited · Mulund, MumbaiAlso near Sion, Off Dmart

Possession: Enigma Towers A and B is marked completed on MahaRERA. How to check it yourself

Registered on MahaRERA under P51800002656. Status: Completed. 14 complaints are listed against it on MahaRERA.

Source: GharKundli’s check of MahaRERA records, October 2026.

What do you want to know about Enigma Towers A and B?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of Enigma Towers A and B has moved

  1. 30 December 2022

    Completion date given when the project was registered

  2. 30 December 2023

    Extended at the builder's request (MahaRERA application EXT51800012831)

    Reason the builder gave MahaRERA:
    “a. On account of the Covid 19 pandemic and the ensuing lockdown, the supply chains and logistics were disrupted, as a consequence whereof, supply of material, equipment and machinery etc. needed for construction was not available and the pr…” Read the full reason“a. On account of the Covid 19 pandemic and the ensuing lockdown, the supply chains and logistics were disrupted, as a consequence whereof, supply of material, equipment and machinery etc. needed for construction was not available and the projected timelines for progress in construction could not be met. b. Despite relaxation of the lockdown on account of the Covid 19 pandemic, and the consequent gradual opening up, there continues to be an acute shortage of labour, especially for large construction projects like the said Project, which not only requires labourers with a certain level of exp…”
  3. 1 August 2024

    Extended at the builder's request (MahaRERA application EXT51800018544)

    Reason the builder gave MahaRERA:
    “Once the lockdown was relaxed around August, 2020 kickstarting construction work immediately was a challenge due to reverse migration of labourers during the lockdown. The restriction in movements had also led to disruption in supply chains…” Read the full reason“Once the lockdown was relaxed around August, 2020 kickstarting construction work immediately was a challenge due to reverse migration of labourers during the lockdown. The restriction in movements had also led to disruption in supply chains which led to difficulty in obtaining construction material and equipment and therefore construction work could not be commenced. By the time Promoter could arrange mobilization of labour and supply of construction material, the second wave of the pandemic struck at the end of February, 2021. The situation aggravated by March, 2021 and second phase of loc…”

Source: Enigma Towers A and B’s extension records on MahaRERA (P51800002656), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Enigma Towers A and B

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 14 complaints and 2 court cases, and how it ended
  • Construction pace against the August 2024 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51800002656
Status
Completed
Builder
Oberoi Constructions Limited
Location
Mulund, Mumbai · 400080
Project type
Residential / Group Housing
Registered on
2 Aug 2017
Completion date at registration
December 2022
Latest completion date
August 2024
Delay so far
20 months
Homes
693
Towers
2
Complaints on MahaRERA
14
Court cases listed
2
Appeals at the tribunal
8
Title report on file
Not found
Builder's other MahaRERA projects
3

Construction progress of Enigma Towers A and B, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
Tower A100%100%100%100%
Tower B100%100%100%100%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Enigma Towers A and B every month.

Enigma Towers A and B: buildings, flats and land, as filed on MahaRERA

The builder’s record and reviews

Oberoi Realty (a group of 4 linked companies) has 17 projects on MahaRERA since 2017, this one included. Of the 17 GharKundli has checked: 7 finished, 6 within the promised date and 1 needed more time (typically 7 months); 10 still being built, none past the promised date yet. 56 complaints on MahaRERA across 9 projects.

Read Google reviews of Enigma Towers A and B →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Enigma Towers A and B: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about Enigma Towers A and B

What is the possession date of Enigma Towers A and B?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Enigma Towers A and B in Mulund, Mumbai is 1 August 2024 — 20 months later than 30 December 2022, the date given at registration.

Is the builder's possession date different from the MahaRERA date for Enigma Towers A and B?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Enigma Towers A and B's builder has filed on MahaRERA, the official one, is 1 August 2024, already 20 months later than the 30 December 2022 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Enigma Towers A and B extended?

According to GharKundli's check of MahaRERA records (updated October 2026), Enigma Towers A and B's builder applied to MahaRERA to extend the completion date 2 times: to 30 December 2023, giving the reason "a. On account of the Covid 19 pandemic and the ensuing lockdown, the supply chains and logistics were disrupted, as a consequence whereof, supply of material, equipment and machinery etc. needed for construction was not available and the projected timelines for progress in construction could not be met. b. Despite relaxation of the lockdown on account of the Covid 19 pandemic, and the consequent gradual opening up, there continues to be an acute shortage of labour, especially for large construction projects like the said Project, which not only requires labourers with a certain level of exp…"; to 1 August 2024, giving the reason "Once the lockdown was relaxed around August, 2020 kickstarting construction work immediately was a challenge due to reverse migration of labourers during the lockdown. The restriction in movements had also led to disruption in supply chains which led to difficulty in obtaining construction material and equipment and therefore construction work could not be commenced. By the time Promoter could arrange mobilization of labour and supply of construction material, the second wave of the pandemic struck at the end of February, 2021. The situation aggravated by March, 2021 and second phase of loc…".

What is the RERA number of Enigma Towers A and B?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Enigma Towers A and B in Mulund, Mumbai is P51800002656.

Is Enigma Towers A and B registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Enigma Towers A and B is registered as P51800002656 and its status is "Completed".

What is the construction status of Enigma Towers A and B?

According to GharKundli's check of MahaRERA records (updated October 2026), Enigma Towers A and B's status on MahaRERA is "Completed". As filed by the builder, slab work is 100% done across 2 towers. GharKundli's full report compares construction progress with the deadline.

Does Enigma Towers A and B have complaints on MahaRERA?

14 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Is Enigma Towers A and B safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Enigma Towers A and B is registered on MahaRERA as P51800002656, its MahaRERA status is "Completed", its completion date has moved 20 months since registration and 14 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if Enigma Towers A and B's possession date changes?

The latest dates are on Enigma Towers A and B's MahaRERA page (P51800002656). GharKundli's Kundli Watch sends a free WhatsApp update on Enigma Towers A and B every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Enigma Towers A and B have?

According to GharKundli's check of MahaRERA records (updated October 2026), Enigma Towers A and B has 2 buildings filed: Tower A with 81 floors; Tower B with 81 floors.

How big is the land of Enigma Towers A and B?

According to GharKundli's check of MahaRERA records (updated October 2026), Enigma Towers A and B stands on 2,634 sq m of land (about 0.7 acres), with 1,27,448 sq m of sanctioned built-up area.

What is the track record of Enigma Towers A and B's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Oberoi Realty (a group of 4 linked companies) has 17 projects on MahaRERA since 2017, this one included. Of the 17 GharKundli has checked: 7 finished, 6 within the promised date and 1 needed more time (typically 7 months); 10 still being built, none past the promised date yet. 56 complaints on MahaRERA across 9 projects. GharKundli's full report covers the builder's record in detail.

Where can I read reviews of Enigma Towers A and B?

Google Maps has reviews of Enigma Towers A and B written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 14 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is Enigma Towers A and B?

Enigma Towers A and B by Oberoi Constructions Limited is in Mulund, Mumbai (pincode 400080), near Sion, Off Dmart, Maharashtra, and is registered on MahaRERA as P51800002656, per GharKundli's check of MahaRERA records.

How many homes are in Enigma Towers A and B?

According to GharKundli's check of MahaRERA records (updated October 2026), Enigma Towers A and B has 693 homes in 2 towers registered on MahaRERA.

When was Enigma Towers A and B registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Enigma Towers A and B was registered on MahaRERA on 2 August 2017. GharKundli did not find a title report on the land on file there.

Are there court cases on Enigma Towers A and B?

2 court cases are listed for Enigma Towers A and B on MahaRERA, and 8 appeals at the tribunal, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.

Who is the builder of Enigma Towers A and B?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Oberoi Constructions Limited, which has 3 other projects registered on MahaRERA.

Other projects in pincode 400080

All 303 projects in Mulund West (400080) →

Other projects by Oberoi Constructions Limited

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.