Eternia Towers A to D

by Oberoi Constructions Limited · Mulund, MumbaiAlso near Bhandup West, Sion, Off Dmart

Possession date of Eternia Towers A to D: 10 May 2026, moved from 30 December 2022 (41 months later). This is the latest completion date the builder has filed on MahaRERA, and it has already passed. How to check it yourself

Registered on MahaRERA under P51800006141. Status: Lapsed (registration period ended). 12 complaints are listed against it on MahaRERA.

Source: GharKundli’s check of MahaRERA records, October 2026.

The latest completion date on MahaRERA (May 2026) has passed.

What do you want to know about Eternia Towers A to D?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of Eternia Towers A to D has moved

  1. 30 December 2022

    Completion date given when the project was registered

  2. 30 December 2023

    Extended at the builder's request (MahaRERA application EXT51800012832)

    Reason the builder gave MahaRERA:
    “a. On account of the Covid 19 pandemic and the ensuing lockdown, the supply chains and logistics were disrupted, as a consequence whereof, supply of material, equipment and machinery etc. needed for construction was not available and the pr…” Read the full reason“a. On account of the Covid 19 pandemic and the ensuing lockdown, the supply chains and logistics were disrupted, as a consequence whereof, supply of material, equipment and machinery etc. needed for construction was not available and the projected timelines for progress in construction could not be met. b. Despite relaxation of the lockdown on account of the Covid 19 pandemic, and the consequent gradual opening up, there continues to be an acute shortage of labour, especially for large construction projects like the said Project, which not only requires labourers with a certain level of exp…”
  3. 10 May 2026

    Extended at the builder's request (MahaRERA application EA30012619642)

    Reason the builder gave MahaRERA: “As directed by MahaRERA, a declaration on 500Rs Stamp Paper has been submitted seeking extension for 100 days from the date of Extension Application i.e. till 10th May 2026.”

Source: Eternia Towers A to D’s extension records on MahaRERA (P51800006141), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Eternia Towers A to D

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 12 complaints and 2 court cases, and how it ended
  • Construction pace against the May 2026 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51800006141
Status
Lapsed (registration period ended)
Builder
Oberoi Constructions Limited
Location
Mulund, Mumbai · 400080
Project type
Residential / Group Housing
Registered on
14 Aug 2017
Completion date at registration
December 2022
Latest completion date
May 2026
Delay so far
41 months
Homes
1,312
Sold or booked
70%
Towers
4
Complaints on MahaRERA
12
Court cases listed
2
Appeals at the tribunal
4
Title report on file
Not found
Builder's other MahaRERA projects
3

Construction progress of Eternia Towers A to D, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
Tower A100%100%100%100%
Tower B100%100%100%100%
Tower C100%100%100%100%
Tower D100%100%100%100%

Commencement certificate (CC), as filed on MahaRERA

  • Tower A: covers 66 floors
  • Tower B: covers 66 floors
  • Tower C: covers 65 floors
  • Tower D: covers 64 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Eternia Towers A to D every month.

Eternia Towers A to D: buildings, flats and land, as filed on MahaRERA

TypeCarpet area (sq ft)Units
Other913 – 1,2041312
  • Buildings: Tower A (79 floors, 332 units) · Tower B (79 floors, 332 units) · Tower C (79 floors, 320 units) · Tower D (79 floors, 328 units)
  • Car parking: 850 covered
  • Land: 3,367 sq m (about 0.8 acres) · sanctioned built-up 1,40,756 sq m
  • Map: the location the builder filed on MahaRERA

The builder’s record and reviews

Oberoi Realty (a group of 4 linked companies) has 17 projects on MahaRERA since 2017, this one included. Of the 17 GharKundli has checked: 7 finished, 6 within the promised date and 1 needed more time (typically 7 months); 10 still being built, none past the promised date yet. 56 complaints on MahaRERA across 9 projects.

Read Google reviews of Eternia Towers A to D →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Eternia Towers A to D: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about Eternia Towers A to D

What is the possession date of Eternia Towers A to D?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Eternia Towers A to D in Mulund, Mumbai is 10 May 2026 — 41 months later than 30 December 2022, the date given at registration. That date has already passed.

Is the builder's possession date different from the MahaRERA date for Eternia Towers A to D?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Eternia Towers A to D's builder has filed on MahaRERA, the official one, is 10 May 2026, already 41 months later than the 30 December 2022 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Eternia Towers A to D extended?

According to GharKundli's check of MahaRERA records (updated October 2026), Eternia Towers A to D's builder applied to MahaRERA to extend the completion date 2 times: to 30 December 2023, giving the reason "a. On account of the Covid 19 pandemic and the ensuing lockdown, the supply chains and logistics were disrupted, as a consequence whereof, supply of material, equipment and machinery etc. needed for construction was not available and the projected timelines for progress in construction could not be met. b. Despite relaxation of the lockdown on account of the Covid 19 pandemic, and the consequent gradual opening up, there continues to be an acute shortage of labour, especially for large construction projects like the said Project, which not only requires labourers with a certain level of exp…"; to 10 May 2026, giving the reason "As directed by MahaRERA, a declaration on 500Rs Stamp Paper has been submitted seeking extension for 100 days from the date of Extension Application i.e. till 10th May 2026.".

What is the RERA number of Eternia Towers A to D?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Eternia Towers A to D in Mulund, Mumbai is P51800006141.

Is Eternia Towers A to D registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Eternia Towers A to D is registered as P51800006141 and its status is "Lapsed (registration period ended)".

What is the construction status of Eternia Towers A to D?

According to GharKundli's check of MahaRERA records (updated October 2026), Eternia Towers A to D's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work is 100% done across 4 towers. GharKundli's full report compares construction progress with the deadline.

Does Eternia Towers A to D have complaints on MahaRERA?

12 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Is Eternia Towers A to D safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Eternia Towers A to D is registered on MahaRERA as P51800006141, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 41 months since registration and 12 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if Eternia Towers A to D's possession date changes?

The latest dates are on Eternia Towers A to D's MahaRERA page (P51800006141). GharKundli's Kundli Watch sends a free WhatsApp update on Eternia Towers A to D every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Eternia Towers A to D have?

According to GharKundli's check of MahaRERA records (updated October 2026), Eternia Towers A to D has 4 buildings filed: Tower A with 79 floors and 332 units; Tower B with 79 floors and 332 units; Tower C with 79 floors and 320 units; Tower D with 79 floors and 328 units.

What are the flat sizes (carpet area) in Eternia Towers A to D?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for Eternia Towers A to D: Other: 913 to 1204 sq ft carpet (1312 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.

How much parking does Eternia Towers A to D have?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 850 covered car parking spaces for Eternia Towers A to D.

How big is the land of Eternia Towers A to D?

According to GharKundli's check of MahaRERA records (updated October 2026), Eternia Towers A to D stands on 3,367 sq m of land (about 0.8 acres), with 1,40,756 sq m of sanctioned built-up area.

What is the track record of Eternia Towers A to D's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Oberoi Realty (a group of 4 linked companies) has 17 projects on MahaRERA since 2017, this one included. Of the 17 GharKundli has checked: 7 finished, 6 within the promised date and 1 needed more time (typically 7 months); 10 still being built, none past the promised date yet. 56 complaints on MahaRERA across 9 projects. GharKundli's full report covers the builder's record in detail.

Where can I read reviews of Eternia Towers A to D?

Google Maps has reviews of Eternia Towers A to D written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 12 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is Eternia Towers A to D?

Eternia Towers A to D by Oberoi Constructions Limited is in Mulund, Mumbai (pincode 400080), near Bhandup West, Sion, Off Dmart, Maharashtra, and is registered on MahaRERA as P51800006141, per GharKundli's check of MahaRERA records.

How many homes are in Eternia Towers A to D?

According to GharKundli's check of MahaRERA records (updated October 2026), Eternia Towers A to D has 1,312 homes in 4 towers registered on MahaRERA, and 70% of them are sold or booked.

When was Eternia Towers A to D registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Eternia Towers A to D was registered on MahaRERA on 14 August 2017. GharKundli did not find a title report on the land on file there.

Are there court cases on Eternia Towers A to D?

2 court cases are listed for Eternia Towers A to D on MahaRERA, and 4 appeals at the tribunal, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.

Who is the builder of Eternia Towers A to D?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Oberoi Constructions Limited, which has 3 other projects registered on MahaRERA.

All projects with possession due in 2026 in Mumbai Suburban →

Other projects in pincode 400080

All 303 projects in Mulund West (400080) →

Other projects by Oberoi Constructions Limited

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.