NAVKAR HILLS - RAINBOW VIEW - PART 1
by NAVKAR HOLIDAY HOMES & WATER PARK LLP · Vada, Palghar
Possession date of NAVKAR HILLS - RAINBOW VIEW - PART 1: 30 April 2028. This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P99000049526, and currently active. Its completion date is now April 2028, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time.
Source: GharKundli’s check of MahaRERA records, November 2026.
What do you want to know about NAVKAR HILLS - RAINBOW VIEW - PART 1?
How the possession date of NAVKAR HILLS - RAINBOW VIEW - PART 1 has moved
31 December 2027
Completion date given when the project was registered
30 April 2028
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: NAVKAR HILLS - RAINBOW VIEW - PART 1’s extension records on MahaRERA (P99000049526), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on NAVKAR HILLS - RAINBOW VIEW - PART 1
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the April 2028 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P99000049526
- Status
- Registered and active
- Builder
- NAVKAR HOLIDAY HOMES & WATER PARK LLP
- Location
- Vada, Palghar · 421303
- Project type
- Plotted
- Registered on
- 15 Feb 2023
- Completion date at registration
- December 2027
- Latest completion date
- April 2028
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 3
NAVKAR HILLS - RAINBOW VIEW - PART 1: buildings, flats and land, as filed on MahaRERA
- Land: 4,943 sq m (about 1.2 acres) · sanctioned built-up 2,290 sq m
The builder’s record and reviews
Navkar Estate And Homes (a group of 4 linked companies) has 13 projects on MahaRERA since 2017, this one included. Of the 10 GharKundli has checked: 10 still being built, 7 past the promised date (typically 22 months late). 2 complaints on MahaRERA across 2 projects.
Read Google reviews of NAVKAR HILLS - RAINBOW VIEW - PART 1 →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
NAVKAR HILLS - RAINBOW VIEW - PART 1: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about NAVKAR HILLS - RAINBOW VIEW - PART 1
What is the possession date of NAVKAR HILLS - RAINBOW VIEW - PART 1?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for NAVKAR HILLS - RAINBOW VIEW - PART 1 in Vada, Palghar is 30 April 2028, including MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for NAVKAR HILLS - RAINBOW VIEW - PART 1?
Builders and listing sites often quote an earlier "target" date for handover. The completion date NAVKAR HILLS - RAINBOW VIEW - PART 1's builder has filed on MahaRERA, the official one, is 30 April 2028, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
What is the RERA number of NAVKAR HILLS - RAINBOW VIEW - PART 1?
According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of NAVKAR HILLS - RAINBOW VIEW - PART 1 in Vada, Palghar is P99000049526.
Is NAVKAR HILLS - RAINBOW VIEW - PART 1 registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), NAVKAR HILLS - RAINBOW VIEW - PART 1 is registered as P99000049526 and its status is "Registered and active".
What is the construction status of NAVKAR HILLS - RAINBOW VIEW - PART 1?
According to GharKundli's check of MahaRERA records (updated November 2026), NAVKAR HILLS - RAINBOW VIEW - PART 1's status on MahaRERA is "Registered and active". GharKundli's full report compares construction progress with the deadline.
Does NAVKAR HILLS - RAINBOW VIEW - PART 1 have complaints on MahaRERA?
No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.
Is NAVKAR HILLS - RAINBOW VIEW - PART 1 safe to buy?
According to GharKundli's check of MahaRERA records (updated November 2026), NAVKAR HILLS - RAINBOW VIEW - PART 1 is registered on MahaRERA as P99000049526, its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if NAVKAR HILLS - RAINBOW VIEW - PART 1's possession date changes?
The latest dates are on NAVKAR HILLS - RAINBOW VIEW - PART 1's MahaRERA page (P99000049526). GharKundli's Kundli Watch sends a free WhatsApp update on NAVKAR HILLS - RAINBOW VIEW - PART 1 every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How big is the land of NAVKAR HILLS - RAINBOW VIEW - PART 1?
According to GharKundli's check of MahaRERA records (updated November 2026), NAVKAR HILLS - RAINBOW VIEW - PART 1 stands on 4,943 sq m of land (about 1.2 acres), with 2,290 sq m of sanctioned built-up area.
What is the track record of NAVKAR HILLS - RAINBOW VIEW - PART 1's builder?
According to GharKundli's check of MahaRERA records (updated November 2026), Navkar Estate And Homes (a group of 4 linked companies) has 13 projects on MahaRERA since 2017, this one included. Of the 10 GharKundli has checked: 10 still being built, 7 past the promised date (typically 22 months late). 2 complaints on MahaRERA across 2 projects. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of NAVKAR HILLS - RAINBOW VIEW - PART 1?
Google Maps has reviews of NAVKAR HILLS - RAINBOW VIEW - PART 1 written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is NAVKAR HILLS - RAINBOW VIEW - PART 1?
NAVKAR HILLS - RAINBOW VIEW - PART 1 by NAVKAR HOLIDAY HOMES & WATER PARK LLP is in Vada, Palghar (pincode 421303), Maharashtra, and is registered on MahaRERA as P99000049526, per GharKundli's check of MahaRERA records.
When was NAVKAR HILLS - RAINBOW VIEW - PART 1 registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), NAVKAR HILLS - RAINBOW VIEW - PART 1 was registered on MahaRERA on 15 February 2023. GharKundli did not find a title report on the land on file there.
Are there court cases on NAVKAR HILLS - RAINBOW VIEW - PART 1?
No court cases are listed for NAVKAR HILLS - RAINBOW VIEW - PART 1 on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).
Who is the builder of NAVKAR HILLS - RAINBOW VIEW - PART 1?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is NAVKAR HOLIDAY HOMES & WATER PARK LLP, which has 3 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of NAVKAR HILLS - RAINBOW VIEW - PART 1
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2028 in Palghar →
Other projects in Vada
- Navkar Hills River Bay View-Part-1
- Status Pride - Phase 1
- Sontakke Arcade
- SWAPNAPURTI COMPLEX
- Parnkuti Row House
- WOLLYWOOD PHASE II
- Swastik Heights
- DREAM PARK
Other projects by NAVKAR HOLIDAY HOMES & WATER PARK LLP
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.