Possession date of KAUSHIK RESIDENCY: 30 April 2028. This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P99000049076, and currently active. Its completion date is now April 2028, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time.

Source: GharKundli’s check of MahaRERA records, November 2026.

What do you want to know about KAUSHIK RESIDENCY?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of KAUSHIK RESIDENCY has moved

  1. 31 December 2027

    Completion date given when the project was registered

  2. 30 April 2028

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: KAUSHIK RESIDENCY’s extension records on MahaRERA (P99000049076), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on KAUSHIK RESIDENCY

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the April 2028 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P99000049076
Status
Registered and active
Builder
MUSKAAN DEVELOPERS
Location
At Vevoor, Palghar · 401404
Project type
Residential / Group Housing
Registered on
30 Jan 2023
Completion date at registration
December 2027
Latest completion date
April 2028
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
58
Sold or booked
10%
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found

Construction progress of KAUSHIK RESIDENCY, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
KAUSHIK RESIDENCY100%62.5%20%0%

Commencement certificate (CC), as filed on MahaRERA

  • KAUSHIK RESIDENCY: covers 8 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on KAUSHIK RESIDENCY every month.

KAUSHIK RESIDENCY: buildings, flats and land, as filed on MahaRERA

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of KAUSHIK RESIDENCY →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

KAUSHIK RESIDENCY: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about KAUSHIK RESIDENCY

What is the possession date of KAUSHIK RESIDENCY?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for KAUSHIK RESIDENCY in At Vevoor, Palghar is 30 April 2028, including MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for KAUSHIK RESIDENCY?

Builders and listing sites often quote an earlier "target" date for handover. The completion date KAUSHIK RESIDENCY's builder has filed on MahaRERA, the official one, is 30 April 2028, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

What is the RERA number of KAUSHIK RESIDENCY?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of KAUSHIK RESIDENCY in At Vevoor, Palghar is P99000049076.

Is KAUSHIK RESIDENCY registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), KAUSHIK RESIDENCY is registered as P99000049076 and its status is "Registered and active".

What is the construction status of KAUSHIK RESIDENCY?

According to GharKundli's check of MahaRERA records (updated November 2026), KAUSHIK RESIDENCY's status on MahaRERA is "Registered and active". As filed by the builder, slab work on KAUSHIK RESIDENCY is 62.5% done and internal work 20%. GharKundli's full report compares construction progress with the deadline.

Does KAUSHIK RESIDENCY have complaints on MahaRERA?

No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.

Is KAUSHIK RESIDENCY safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), KAUSHIK RESIDENCY is registered on MahaRERA as P99000049076, its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if KAUSHIK RESIDENCY's possession date changes?

The latest dates are on KAUSHIK RESIDENCY's MahaRERA page (P99000049076). GharKundli's Kundli Watch sends a free WhatsApp update on KAUSHIK RESIDENCY every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does KAUSHIK RESIDENCY have?

According to GharKundli's check of MahaRERA records (updated November 2026), KAUSHIK RESIDENCY has one building filed: KAUSHIK RESIDENCY with 8 floors and 58 units.

How much parking does KAUSHIK RESIDENCY have?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder has filed 1 covered car parking spaces for KAUSHIK RESIDENCY.

How big is the land of KAUSHIK RESIDENCY?

According to GharKundli's check of MahaRERA records (updated November 2026), KAUSHIK RESIDENCY stands on 1,100 sq m of land (about 0.3 acres), with 2,590 sq m of sanctioned built-up area.

Where can I read reviews of KAUSHIK RESIDENCY?

Google Maps has reviews of KAUSHIK RESIDENCY written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is KAUSHIK RESIDENCY?

KAUSHIK RESIDENCY by MUSKAAN DEVELOPERS is in At Vevoor, Palghar (pincode 401404), near Palghar East, Navali, Palghar West, Maharashtra, and is registered on MahaRERA as P99000049076, per GharKundli's check of MahaRERA records.

How many homes are in KAUSHIK RESIDENCY?

According to GharKundli's check of MahaRERA records (updated November 2026), KAUSHIK RESIDENCY has 58 homes in 1 tower registered on MahaRERA, and 10% of them are sold or booked.

When was KAUSHIK RESIDENCY registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), KAUSHIK RESIDENCY was registered on MahaRERA on 30 January 2023. GharKundli did not find a title report on the land on file there.

Are there court cases on KAUSHIK RESIDENCY?

No court cases are listed for KAUSHIK RESIDENCY on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).

Who is the builder of KAUSHIK RESIDENCY?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is MUSKAAN DEVELOPERS.

All projects with possession due in 2028 in Palghar →

Other projects in Palghar

All 391 projects in Palghar (401404) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.