by BABAJI CONSTRUCTION CO. · Virar East, Palghar

Possession date of GOVIND HERITAGE: 30 April 2028. This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P99000050314, and currently active. Its completion date is now April 2028, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time.

Source: GharKundli’s check of MahaRERA records, November 2026.

What do you want to know about GOVIND HERITAGE?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of GOVIND HERITAGE has moved

  1. 31 December 2027

    Completion date given when the project was registered

  2. 30 April 2028

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: GOVIND HERITAGE’s extension records on MahaRERA (P99000050314), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on GOVIND HERITAGE

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the April 2028 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P99000050314
Status
Registered and active
Builder
BABAJI CONSTRUCTION CO.
Location
Virar East, Palghar · 401303
Project type
Residential / Group Housing
Registered on
1 Apr 2023
Completion date at registration
December 2027
Latest completion date
April 2028
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
14
Sold or booked
55%
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found

Construction progress of GOVIND HERITAGE, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
GOVIND HERITAGE100%100%100%95%

Commencement certificate (CC), as filed on MahaRERA

  • GOVIND HERITAGE: covers 4 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on GOVIND HERITAGE every month.

GOVIND HERITAGE: buildings, flats and land, as filed on MahaRERA

  • Buildings: GOVIND HERITAGE (8 floors, 20 units)
  • Land: 510 sq m (about 0.1 acres) · sanctioned built-up 846 sq m
  • Boundaries filed include: State Highway

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of GOVIND HERITAGE →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

GOVIND HERITAGE: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about GOVIND HERITAGE

What is the possession date of GOVIND HERITAGE?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for GOVIND HERITAGE in Virar East, Palghar is 30 April 2028, including MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for GOVIND HERITAGE?

Builders and listing sites often quote an earlier "target" date for handover. The completion date GOVIND HERITAGE's builder has filed on MahaRERA, the official one, is 30 April 2028, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

What is the RERA number of GOVIND HERITAGE?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of GOVIND HERITAGE in Virar East, Palghar is P99000050314.

Is GOVIND HERITAGE registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), GOVIND HERITAGE is registered as P99000050314 and its status is "Registered and active".

What is the construction status of GOVIND HERITAGE?

According to GharKundli's check of MahaRERA records (updated November 2026), GOVIND HERITAGE's status on MahaRERA is "Registered and active". As filed by the builder, slab work on GOVIND HERITAGE is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.

Does GOVIND HERITAGE have complaints on MahaRERA?

No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.

Is GOVIND HERITAGE safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), GOVIND HERITAGE is registered on MahaRERA as P99000050314, its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if GOVIND HERITAGE's possession date changes?

The latest dates are on GOVIND HERITAGE's MahaRERA page (P99000050314). GharKundli's Kundli Watch sends a free WhatsApp update on GOVIND HERITAGE every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does GOVIND HERITAGE have?

According to GharKundli's check of MahaRERA records (updated November 2026), GOVIND HERITAGE has one building filed: GOVIND HERITAGE with 8 floors and 20 units.

How big is the land of GOVIND HERITAGE?

According to GharKundli's check of MahaRERA records (updated November 2026), GOVIND HERITAGE stands on 510 sq m of land (about 0.1 acres), with 846 sq m of sanctioned built-up area.

Where can I read reviews of GOVIND HERITAGE?

Google Maps has reviews of GOVIND HERITAGE written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is GOVIND HERITAGE?

GOVIND HERITAGE by BABAJI CONSTRUCTION CO. is in Virar East, Palghar (pincode 401303), Maharashtra, and is registered on MahaRERA as P99000050314, per GharKundli's check of MahaRERA records. Its boundaries filed there include State Highway.

How many homes are in GOVIND HERITAGE?

According to GharKundli's check of MahaRERA records (updated November 2026), GOVIND HERITAGE has 14 homes in 1 tower registered on MahaRERA, and 55% of them are sold or booked.

When was GOVIND HERITAGE registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), GOVIND HERITAGE was registered on MahaRERA on 1 April 2023. GharKundli did not find a title report on the land on file there.

Are there court cases on GOVIND HERITAGE?

No court cases are listed for GOVIND HERITAGE on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).

Who is the builder of GOVIND HERITAGE?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is BABAJI CONSTRUCTION CO..

All projects with possession due in 2028 in Palghar →

Other projects in pincode 401303

All 187 projects in Virar West (401303) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.