by KIRAN ENTERPRISES · Nallasopara West, Palghar

Possession date of SHRI GANESHKRIPA: 30 April 2028, moved from 31 December 2025 (24 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P99000053717, and currently active. Its completion date has moved from December 2025 to April 2028: 24 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.

Source: GharKundli’s check of MahaRERA records, October 2026.

What do you want to know about SHRI GANESHKRIPA?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of SHRI GANESHKRIPA has moved

  1. 31 December 2025

    Completion date given when the project was registered

  2. 31 December 2027

    Extended at the builder's request (MahaRERA application EA26082622396)

    Reason the builder gave MahaRERA: “Non availability of material use due to war and excessive rains caused delay in completion of finishing works”
  3. 30 April 2028

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: SHRI GANESHKRIPA’s extension records on MahaRERA (P99000053717), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on SHRI GANESHKRIPA

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the April 2028 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P99000053717
Status
Registered and active
Builder
KIRAN ENTERPRISES
Location
Nallasopara West, Palghar · 401203
Project type
Residential / Group Housing
Registered on
22 Nov 2023
Completion date at registration
December 2025
Latest completion date
April 2028
Delay so far
24 months
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
49
Sold or booked
35%
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
3

Construction progress of SHRI GANESHKRIPA, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
Building no 2 Wing A and B100%50%0%0%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on SHRI GANESHKRIPA every month.

SHRI GANESHKRIPA: buildings, flats and land, as filed on MahaRERA

  • Buildings: Building no 2 Wing A and B (8 floors, 52 units)
  • Car parking: 6 covered
  • Land: 628 sq m (about 0.2 acres) · sanctioned built-up 2,070 sq m

The builder’s record and reviews

Kiran Enterprises has 2 projects on MahaRERA since 2023, this one included. Of the 2 GharKundli has checked: 2 still being built, 2 past the promised date (typically 6 months late). No complaints on MahaRERA.

Read Google reviews of SHRI GANESHKRIPA →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

SHRI GANESHKRIPA: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about SHRI GANESHKRIPA

What is the possession date of SHRI GANESHKRIPA?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for SHRI GANESHKRIPA in Nallasopara West, Palghar is 30 April 2028 — 24 months later than 31 December 2025, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for SHRI GANESHKRIPA?

Builders and listing sites often quote an earlier "target" date for handover. The completion date SHRI GANESHKRIPA's builder has filed on MahaRERA, the official one, is 30 April 2028, already 24 months later than the 31 December 2025 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of SHRI GANESHKRIPA extended?

According to GharKundli's check of MahaRERA records (updated October 2026), SHRI GANESHKRIPA's builder applied to MahaRERA to extend the completion date once: to 31 December 2027, giving the reason "Non availability of material use due to war and excessive rains caused delay in completion of finishing works". MahaRERA also added its automatic 4-month extension for all eligible projects.

What is the RERA number of SHRI GANESHKRIPA?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of SHRI GANESHKRIPA in Nallasopara West, Palghar is P99000053717.

Is SHRI GANESHKRIPA registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), SHRI GANESHKRIPA is registered as P99000053717 and its status is "Registered and active".

What is the construction status of SHRI GANESHKRIPA?

According to GharKundli's check of MahaRERA records (updated October 2026), SHRI GANESHKRIPA's status on MahaRERA is "Registered and active". As filed by the builder, slab work on Building no 2 Wing A and B is 50% done and internal work 0%. GharKundli's full report compares construction progress with the deadline.

Does SHRI GANESHKRIPA have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is SHRI GANESHKRIPA safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), SHRI GANESHKRIPA is registered on MahaRERA as P99000053717, its completion date has moved 24 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if SHRI GANESHKRIPA's possession date changes?

The latest dates are on SHRI GANESHKRIPA's MahaRERA page (P99000053717). GharKundli's Kundli Watch sends a free WhatsApp update on SHRI GANESHKRIPA every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does SHRI GANESHKRIPA have?

According to GharKundli's check of MahaRERA records (updated October 2026), SHRI GANESHKRIPA has one building filed: Building no 2 Wing A and B with 8 floors and 52 units.

How much parking does SHRI GANESHKRIPA have?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 6 covered car parking spaces for SHRI GANESHKRIPA.

How big is the land of SHRI GANESHKRIPA?

According to GharKundli's check of MahaRERA records (updated October 2026), SHRI GANESHKRIPA stands on 628 sq m of land (about 0.2 acres), with 2,070 sq m of sanctioned built-up area.

What is the track record of SHRI GANESHKRIPA's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Kiran Enterprises has 2 projects on MahaRERA since 2023, this one included. Of the 2 GharKundli has checked: 2 still being built, 2 past the promised date (typically 6 months late). No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.

Where can I read reviews of SHRI GANESHKRIPA?

Google Maps has reviews of SHRI GANESHKRIPA written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is SHRI GANESHKRIPA?

SHRI GANESHKRIPA by KIRAN ENTERPRISES is in Nallasopara West, Palghar (pincode 401203), Maharashtra, and is registered on MahaRERA as P99000053717, per GharKundli's check of MahaRERA records.

How many homes are in SHRI GANESHKRIPA?

According to GharKundli's check of MahaRERA records (updated October 2026), SHRI GANESHKRIPA has 49 homes in 1 tower registered on MahaRERA, and 35% of them are sold or booked.

When was SHRI GANESHKRIPA registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), SHRI GANESHKRIPA was registered on MahaRERA on 22 November 2023. GharKundli did not find a title report on the land on file there.

Are there court cases on SHRI GANESHKRIPA?

No court cases are listed for SHRI GANESHKRIPA on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder of SHRI GANESHKRIPA?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is KIRAN ENTERPRISES, which has 3 other projects registered on MahaRERA.

All projects with possession due in 2028 in Palghar →

Other projects in pincode 401203

All 154 projects in Nallasopara West (401203) →

Other projects by KIRAN ENTERPRISES

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.