SHREE OMKAR
by Gurumauli Developers · Mulund West, MumbaiAlso near Mulund East, Vile Parle East
Possession: SHREE OMKAR is marked completed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51800007074. Status: Completed. 3 complaints are listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about SHREE OMKAR?
How the possession date of SHREE OMKAR has moved
30 June 2021
Completion date given when the project was registered
30 June 2022
Extended at the builder's request (MahaRERA application EXT51800009815)
Reason the builder gave MahaRERA:
“The Project has been delayed on account of various reasons beyond our control and more particularly due to Lockdown announced on account of pandemic of Covid-19. Due to this unprecedented crises, we have witnessed the reverse migration of l…” Read the full reason
“The Project has been delayed on account of various reasons beyond our control and more particularly due to Lockdown announced on account of pandemic of Covid-19. Due to this unprecedented crises, we have witnessed the reverse migration of labourers and shortage of liquidity in the market. Moreover various private and Government offices have not been working at full strength and the complete supply chain has broken down. It appears that it is going to take a lot of time to normalize the real estate industry.”30 June 2023
Extended at the builder's request (MahaRERA application EXT51800013471)
Reason the builder gave MahaRERA:
“In accordance with circular no 28, we hereby apply for extension of our project u/s 7(3) in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of the pandemic of C…” Read the full reason
“In accordance with circular no 28, we hereby apply for extension of our project u/s 7(3) in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of the pandemic of Covid-19. We have consent of _____% allottees for purpose of extension of RERA registration period of the said project.”31 December 2023
Extended at the builder's request (MahaRERA application EXT51800017089)
Reason the builder gave MahaRERA:
“In accordance with circular no 28, we hereby apply for extension of our project u/s 7(3) in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of the pandemic of C…” Read the full reason
“In accordance with circular no 28, we hereby apply for extension of our project u/s 7(3) in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of the pandemic of Covid-19. We have consent of 82.35% allottees for purpose of extension of RERA registration period of the said project”30 June 2024
Extended at the builder's request (MahaRERA application EXT51800018733)
Reason the builder gave MahaRERA:
“In accordance with circular no 28, we hereby apply for extension of our project u/s 7(3) in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of the pandemic of C…” Read the full reason
“In accordance with circular no 28, we hereby apply for extension of our project u/s 7(3) in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of the pandemic of Covid-19. We have consent of 70.59% allottees for purpose of extension of RERA registration period of the said project.”
Source: SHREE OMKAR’s extension records on MahaRERA (P51800007074), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on SHREE OMKAR
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 3 complaints, and how it ended
- Construction pace against the June 2024 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51800007074
- Status
- Completed
- Builder
- Gurumauli Developers
- Location
- Mulund West, Mumbai · 400081
- Project type
- Residential / Group Housing
- Registered on
- 17 Aug 2017
- Completion date at registration
- June 2021
- Latest completion date
- June 2024
- Delay so far
- 36 months
- Homes
- 27
- Towers
- 1
- Complaints on MahaRERA
- 3
- Court cases listed
- 0
- Appeals at the tribunal
- 2
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 1
Construction progress of SHREE OMKAR, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| SHREE OMKAR | 100% | 100% | 100% | 100% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on SHREE OMKAR every month.
SHREE OMKAR: buildings, flats and land, as filed on MahaRERA
- Buildings: SHREE OMKAR (16 floors)
- Land: 1,014 sq m (about 0.3 acres) · sanctioned built-up 2,883 sq m
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
Shree Tirupati Developers (a group of 3 linked companies) has 3 projects on MahaRERA since 2017, this one included. Of the 3 GharKundli has checked: 3 finished, 0 within the promised date and 3 needed more time (typically 16 months). 3 complaints on MahaRERA across 1 project.
Read Google reviews of SHREE OMKAR →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
SHREE OMKAR: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about SHREE OMKAR
What is the possession date of SHREE OMKAR?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for SHREE OMKAR in Mulund West, Mumbai is 30 June 2024 — 36 months later than 30 June 2021, the date given at registration.
Is the builder's possession date different from the MahaRERA date for SHREE OMKAR?
Builders and listing sites often quote an earlier "target" date for handover. The completion date SHREE OMKAR's builder has filed on MahaRERA, the official one, is 30 June 2024, already 36 months later than the 30 June 2021 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of SHREE OMKAR extended?
According to GharKundli's check of MahaRERA records (updated October 2026), SHREE OMKAR's builder applied to MahaRERA to extend the completion date 4 times: to 30 June 2022, giving the reason "The Project has been delayed on account of various reasons beyond our control and more particularly due to Lockdown announced on account of pandemic of Covid-19. Due to this unprecedented crises, we have witnessed the reverse migration of labourers and shortage of liquidity in the market. Moreover various private and Government offices have not been working at full strength and the complete supply chain has broken down. It appears that it is going to take a lot of time to normalize the real estate industry."; to 30 June 2023, giving the reason "In accordance with circular no 28, we hereby apply for extension of our project u/s 7(3) in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of the pandemic of Covid-19. We have consent of _____% allottees for purpose of extension of RERA registration period of the said project."; to 31 December 2023, giving the reason "In accordance with circular no 28, we hereby apply for extension of our project u/s 7(3) in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of the pandemic of Covid-19. We have consent of 82.35% allottees for purpose of extension of RERA registration period of the said project"; to 30 June 2024, giving the reason "In accordance with circular no 28, we hereby apply for extension of our project u/s 7(3) in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of the pandemic of Covid-19. We have consent of 70.59% allottees for purpose of extension of RERA registration period of the said project.".
What is the RERA number of SHREE OMKAR?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of SHREE OMKAR in Mulund West, Mumbai is P51800007074.
Is SHREE OMKAR registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), SHREE OMKAR is registered as P51800007074 and its status is "Completed".
What is the construction status of SHREE OMKAR?
According to GharKundli's check of MahaRERA records (updated October 2026), SHREE OMKAR's status on MahaRERA is "Completed". As filed by the builder, slab work on SHREE OMKAR is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.
Does SHREE OMKAR have complaints on MahaRERA?
3 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is SHREE OMKAR safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), SHREE OMKAR is registered on MahaRERA as P51800007074, its MahaRERA status is "Completed", its completion date has moved 36 months since registration and 3 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if SHREE OMKAR's possession date changes?
The latest dates are on SHREE OMKAR's MahaRERA page (P51800007074). GharKundli's Kundli Watch sends a free WhatsApp update on SHREE OMKAR every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does SHREE OMKAR have?
According to GharKundli's check of MahaRERA records (updated October 2026), SHREE OMKAR has one building filed: SHREE OMKAR with 16 floors.
How big is the land of SHREE OMKAR?
According to GharKundli's check of MahaRERA records (updated October 2026), SHREE OMKAR stands on 1,014 sq m of land (about 0.3 acres), with 2,883 sq m of sanctioned built-up area.
What is the track record of SHREE OMKAR's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Shree Tirupati Developers (a group of 3 linked companies) has 3 projects on MahaRERA since 2017, this one included. Of the 3 GharKundli has checked: 3 finished, 0 within the promised date and 3 needed more time (typically 16 months). 3 complaints on MahaRERA across 1 project. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of SHREE OMKAR?
Google Maps has reviews of SHREE OMKAR written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 3 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is SHREE OMKAR?
SHREE OMKAR by Gurumauli Developers is in Mulund West, Mumbai (pincode 400081), near Mulund East, Vile Parle East, Maharashtra, and is registered on MahaRERA as P51800007074, per GharKundli's check of MahaRERA records.
How many homes are in SHREE OMKAR?
According to GharKundli's check of MahaRERA records (updated October 2026), SHREE OMKAR has 27 homes in 1 tower registered on MahaRERA.
When was SHREE OMKAR registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), SHREE OMKAR was registered on MahaRERA on 17 August 2017. GharKundli did not find a title report on the land on file there.
Are there court cases on SHREE OMKAR?
No court cases are listed for SHREE OMKAR on MahaRERA, and 2 appeals at the tribunal, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.
Who is the builder of SHREE OMKAR?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Gurumauli Developers, which has 1 other project registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of SHREE OMKAR
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in pincode 400081
- Kam Ganesh Co-operative Housing Society Ltd and Nav Amardeep Co-operative Housing Society Limited
- RBI EMPLOYEES SHREE SAHAWAS CO OP HSG SOC LTD
- GOVIND PRAKASH SRA CHS LTD
- BIMAL APARTMENT CHSL
- Ganesh Dham
- SATRE ELITE
- PEARL
- New Usha Vihar Chsl
Other projects by Gurumauli Developers
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.