Simran Heights
by VIKAS NARAYAN RAIKAR · Govandi, Mumbai 400071Also near Chembur, Kurla, Ghatla
What’s in the report? →Possession date of Simran Heights (MahaRERA P51800002238): 31 March 2025, moved from 24 September 2019 (66 months later), and it has already passed. No complaints on MahaRERA. How to check it yourself
Registered on MahaRERA under P51800002238. Status: Lapsed (registration period ended).
Source: MahaRERA website — records for P51800002238, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.
The latest completion date on MahaRERA (March 2025) has passed.
What do you want to know about Simran Heights?
Completion date nikal chuki hai. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.
How the possession date of Simran Heights has moved
24 September 2019
Completion date given when the project was registered
23 September 2020
Extended at the builder's request (MahaRERA application EXT51800002537)
Reason the builder gave MahaRERA:
“Vide our Application for RERA Registration on 31/7/2017, we had estimated that we will be able to complete the Project by Sept’19. This Project is under S.R.A Authority. At the time of amendment to Letter of Intent (L.O.I.) in April, 2017,…” Read the full reason
“Vide our Application for RERA Registration on 31/7/2017, we had estimated that we will be able to complete the Project by Sept’19. This Project is under S.R.A Authority. At the time of amendment to Letter of Intent (L.O.I.) in April, 2017, the file went CFO, S.R.A and was approved in June, 2017. However, since the particular C.E.O. was to retire on 30/06/2017 and had approved more than 65 to 75 files just before his retirement , there were allegations against the CEO and all approvals issued by the CEO in the last fortnight before his retirement were to be verified by the committee appointe…”21 September 2021
Extended at the builder's request (MahaRERA application EXT51800009326)
Reason the builder gave MahaRERA:
“This is a S.R.A project wherein Bldg is Stilt + 22 upper floors. The entire construction work is completed. However, some Revenue matters relating to S.R.A are remaining. Since, the entire development work is completed S.R.A authorities hav…” Read the full reason
“This is a S.R.A project wherein Bldg is Stilt + 22 upper floors. The entire construction work is completed. However, some Revenue matters relating to S.R.A are remaining. Since, the entire development work is completed S.R.A authorities have granted us Part Occupation certificate for Bldg. with Stilt + 18 upper floors. We are following up with S.R.A Authorities to complete the remaining Revenue matters and we expect to complete the same and obtain full Occupation Certificate within a period of 3 to 4 months time.”31 March 2025
Extended at the builder's request (MahaRERA application EXT51800017647)
Reason the builder gave MahaRERA:
“Our Bldg consist of Stilt + 22 upper Floors. We have obtained occupation certificate upto 21st Floor and have given possession to all purchasers except 2 unsold Flats. 22nd Floor consists of 5 flats for which we have applied for O.C. but no…” Read the full reason
“Our Bldg consist of Stilt + 22 upper Floors. We have obtained occupation certificate upto 21st Floor and have given possession to all purchasers except 2 unsold Flats. 22nd Floor consists of 5 flats for which we have applied for O.C. but not yet received. We have taken consent of of 4 flats that are sold.”
Source: Simran Heights’s extension records on MahaRERA (P51800002238), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Simran Heights
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the March 2025 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51800002238
- Status
- Lapsed (registration period ended)
- Builder
- VIKAS NARAYAN RAIKAR
- Location
- Govandi, Mumbai · 400071
- Project type
- Residential / Group Housing
- Registered on
- 31 Jul 2017
- Completion date at registration
- September 2019
- Latest completion date
- March 2025
- Delay so far
- 66 months
- Towers
- 2
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 2
Construction progress of Simran Heights, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| SIMRAN HEIGHTS - PHASE I | 100% | 70% | 15% | 0% |
| SIMRAN HEIGHTS - Phase II | 100% | 0% | 0% | 0% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Simran Heights every 1–2 months.
Simran Heights: buildings, flats and land, as filed on MahaRERA
- Buildings: SIMRAN HEIGHTS - PHASE I (23 floors)
- Land: 4,867 sq m (about 1.2 acres) · sanctioned built-up 3,394 sq m
- Land, as filed: 373, 374, 374/1 TO 374/24, 375, 376, 376/1 TO 3, 377, 378, 378/1 TO 3, 379, 379/1, 380, 380/1 TO 3,
- Map: the location the builder filed on MahaRERA · Get directions
The builder’s record and reviews
Vikas Narayan Raikar has 4 projects on MahaRERA since 2017, this one included. Of the 4 GharKundli has checked: 2 finished, 0 within the promised date and 2 needed more time (typically 26 months); 2 still being built, none past the promised date yet. No complaints on MahaRERA.
Read Google reviews of Simran Heights →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Simran Heights: buyers & owners
Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.
Common questions about Simran Heights
What is the possession date of Simran Heights?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Simran Heights in Govandi, Mumbai is 31 March 2025 — 66 months later than 24 September 2019, the date given at registration. That date has already passed.
The date has already moved 66 months. Will it move again? Check the real pace of construction →
Is the builder's possession date different from the MahaRERA date for Simran Heights?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Simran Heights's builder has filed on MahaRERA, the official one, is 31 March 2025, already 66 months later than the 24 September 2019 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Simran Heights extended?
According to GharKundli's check of MahaRERA records (updated October 2026), Simran Heights's builder applied to MahaRERA to extend the completion date 3 times: to 23 September 2020, giving the reason "Vide our Application for RERA Registration on 31/7/2017, we had estimated that we will be able to complete the Project by Sept’19. This Project is under S.R.A Authority. At the time of amendment to Letter of Intent (L.O.I.) in April, 2017, the file went CFO, S.R.A and was approved in June, 2017. However, since the particular C.E.O. was to retire on 30/06/2017 and had approved more than 65 to 75 files just before his retirement , there were allegations against the CEO and all approvals issued by the CEO in the last fortnight before his retirement were to be verified by the committee appointe…"; to 21 September 2021, giving the reason "This is a S.R.A project wherein Bldg is Stilt + 22 upper floors. The entire construction work is completed. However, some Revenue matters relating to S.R.A are remaining. Since, the entire development work is completed S.R.A authorities have granted us Part Occupation certificate for Bldg. with Stilt + 18 upper floors. We are following up with S.R.A Authorities to complete the remaining Revenue matters and we expect to complete the same and obtain full Occupation Certificate within a period of 3 to 4 months time."; to 31 March 2025, giving the reason "Our Bldg consist of Stilt + 22 upper Floors. We have obtained occupation certificate upto 21st Floor and have given possession to all purchasers except 2 unsold Flats. 22nd Floor consists of 5 flats for which we have applied for O.C. but not yet received. We have taken consent of of 4 flats that are sold.".
What is the RERA number of Simran Heights?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Simran Heights in Govandi, Mumbai is P51800002238.
Is Simran Heights registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Simran Heights is registered as P51800002238 and its status is "Lapsed (registration period ended)".
What is the current construction status of Simran Heights? How much work is done?
According to GharKundli's check of MahaRERA records (updated October 2026), Simran Heights's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work ranges from 0% to 70% across 2 towers. GharKundli's full report compares construction progress with the deadline.
Does Simran Heights have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is Simran Heights safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Simran Heights is registered on MahaRERA as P51800002238, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 66 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How much GST is payable on a flat in Simran Heights?
Simran Heights isn't marked completed on MahaRERA, so until the occupancy certificate is issued GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) in the Mumbai region, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.
What is the stamp duty and registration cost for a flat in Simran Heights?
For a flat in Simran Heights (Mumbai), stamp duty is 6% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess. A woman buying in her own name pays 5%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹6 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator
Has Simran Heights received its OC? Is it ready to move in?
Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Simran Heights isn't completed: its MahaRERA status is "Lapsed (registration period ended)", with 31 March 2025 as the latest completion date filed on MahaRERA, and that date has passed. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.
What does "lapsed" mean for Simran Heights?
According to GharKundli's check of MahaRERA records (updated October 2026), Simran Heights's registration shows as lapsed on MahaRERA. Lapsed means the completion date on MahaRERA (31 March 2025) passed without the project being marked complete or the registration being extended. Before paying anything, ask the builder in writing whether an extension has been applied for.
Has Simran Heights uploaded its title report on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Simran Heights was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.
No title report is on MahaRERA for this project. See which documents are missing →
How can I get updates if Simran Heights's possession date changes?
The latest dates are on Simran Heights's MahaRERA page (P51800002238). GharKundli's Kundli Watch sends a free WhatsApp update on Simran Heights every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Simran Heights have?
According to GharKundli's check of MahaRERA records (updated October 2026), Simran Heights has one building filed: SIMRAN HEIGHTS - PHASE I with 23 floors.
How big is the land of Simran Heights?
According to GharKundli's check of MahaRERA records (updated October 2026), Simran Heights stands on 4,867 sq m of land (about 1.2 acres), with 3,394 sq m of sanctioned built-up area.
What is the track record of Simran Heights's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Vikas Narayan Raikar has 4 projects on MahaRERA since 2017, this one included. Of the 4 GharKundli has checked: 2 finished, 0 within the promised date and 2 needed more time (typically 26 months); 2 still being built, none past the promised date yet. No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.
What are the reviews of Simran Heights?
Google Maps has reviews of Simran Heights written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
What is the address and pincode of Simran Heights?
Simran Heights by VIKAS NARAYAN RAIKAR is in Govandi, Mumbai, pincode 400071 (near Chembur, Kurla, Ghatla), Maharashtra, and is registered on MahaRERA as P51800002238, per GharKundli's check of MahaRERA records. Its land is filed as 373, 374, 374/1 TO 374/24, 375, 376, 376/1 TO 3, 377, 378, 378/1 TO 3, 379, 379/1, 380, 380/1 TO 3,. GharKundli lists all 318 MahaRERA projects in Chembur (400071).
When was Simran Heights registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Simran Heights was registered on MahaRERA on 31 July 2017. GharKundli did not find a title report on the land on file there.
Does Simran Heights have any legal issues or court cases?
No court cases are listed for Simran Heights on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder / developer of Simran Heights?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is VIKAS NARAYAN RAIKAR, which has 2 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of Simran Heights
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in Kurla
- Pardis Prosperity
- Saptashringi
- Jai Arihant
- Sudhanshu Heights
- Privilon
- Kanakdhara
- Heritage Lakeside
- Kalyan Kutir Co-operative Housing Society Limited
Other projects by VIKAS NARAYAN RAIKAR
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.