Grace Meadows

by Grace Suburban Development Venture · Dahisar East, Mumbai 400068Also near Dahisar West, Borivali West, Mandapeshwar

What’s in the report? →

Possession date of Grace Meadows (MahaRERA P51800007583): 31 July 2027, moved from 30 November 2020 (76 months later). It has 117 homes. No complaints on MahaRERA. How to check it yourself

Registered on MahaRERA under P51800007583, and currently active. Its completion date has moved from November 2020 to July 2027: 76 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.

Source: MahaRERA website — records for P51800007583, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

What do you want to know about Grace Meadows?

2 court cases MahaRERA par listed. Kya jaanna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

How the possession date of Grace Meadows has moved

  1. 30 November 2020

    Completion date given when the project was registered

  2. 30 November 2021

    Extended at the builder's request (MahaRERA application EXT51800008473)

    Reason the builder gave MahaRERA:
    “as layout for the property submitted to department dated 01-02-2018 and approved by the department dated 27-02-2020 which lost considerable time. and work was halted due to the approval process. we received further IOD approval only after t…” Read the full reason“as layout for the property submitted to department dated 01-02-2018 and approved by the department dated 27-02-2020 which lost considerable time. and work was halted due to the approval process. we received further IOD approval only after the approval of the layout.”
  3. 30 September 2022

    Extended at the builder's request (MahaRERA application EXT51800012011)

    Reason the builder gave MahaRERA:
    “DUE TO NEW RULE APPLIED FOR CIVIL AVIATION, OCCUPATION CERTIFICATE PROCESS DELAYED. WE HAVE COMPLETED THE 95.00% OF WORK AS PER ARCHITECT AND ENGINEER CERTIFICATE UPLOADED. WE REQUEST YOU TO EXTEND THE TIME PERIOD FOR THE REQUIRED OCCUPATIO…” Read the full reason“DUE TO NEW RULE APPLIED FOR CIVIL AVIATION, OCCUPATION CERTIFICATE PROCESS DELAYED. WE HAVE COMPLETED THE 95.00% OF WORK AS PER ARCHITECT AND ENGINEER CERTIFICATE UPLOADED. WE REQUEST YOU TO EXTEND THE TIME PERIOD FOR THE REQUIRED OCCUPATION CERTIFICATE PROCESS”
  4. 31 March 2023

    Extended at the builder's request (MahaRERA application EXT51800013485)

    Reason the builder gave MahaRERA: “Architect Completion Certificate already issued for the Project. We are completing the formalities to obtain the OC.”
  5. 31 March 2024

    Extended at the builder's request (MahaRERA application EXT51800016478)

    Reason the builder gave MahaRERA:
    “OCCUPANCY CERTIFICATE IS APPLIED FOR AND IS PENDING DUE TO CIVIL AVIATION MATTER OF DAHISAR AREA We have updated all the details as per your requirement. Form B updated with the entended date of completion. Form 2 signed by the architect an…” Read the full reason“OCCUPANCY CERTIFICATE IS APPLIED FOR AND IS PENDING DUE TO CIVIL AVIATION MATTER OF DAHISAR AREA We have updated all the details as per your requirement. Form B updated with the entended date of completion. Form 2 signed by the architect and agreed and accepted by the promoter. Project details such as sold units, etc also updated.”
  6. 31 March 2027

    Extended at the builder's request (MahaRERA application EXT51800024389)

    Reason the builder gave MahaRERA:
    “In accordance with circular no 28, we hereby apply for extension of our project u/s 7(3) in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of the pandemic of C…” Read the full reason“In accordance with circular no 28, we hereby apply for extension of our project u/s 7(3) in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of the pandemic of Covid-19. We have consent of 65.05% allottees for purpose of extension of RERA registration period of the said project.”
  7. 31 July 2027

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: Grace Meadows’s extension records on MahaRERA (P51800007583), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Grace Meadows

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 2 court cases, and how it ended
  • Construction pace against the July 2027 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51800007583
Status
Registered and active
Builder
Grace Suburban Development Venture
Location
Dahisar East, Mumbai · 400068
Project type
Residential / Group Housing
Registered on
17 Aug 2017
Completion date at registration
November 2020
Latest completion date
July 2027
Delay so far
76 months
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
117
Towers
1
Complaints on MahaRERA
0
Court cases listed
2
Title report on file
Not found

Construction progress of Grace Meadows, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
Grace Meadows100%100%100%100%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Grace Meadows every 1–2 months.

Grace Meadows: buildings, flats and land, as filed on MahaRERA

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of Grace Meadows →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Grace Meadows: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about Grace Meadows

What is the possession date of Grace Meadows?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Grace Meadows in Dahisar East, Mumbai is 31 July 2027 — 76 months later than 30 November 2020, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.

The date has already moved 76 months. Will it move again? Check the real pace of construction →

Is the builder's possession date different from the MahaRERA date for Grace Meadows?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Grace Meadows's builder has filed on MahaRERA, the official one, is 31 July 2027, already 76 months later than the 30 November 2020 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Grace Meadows extended?

According to GharKundli's check of MahaRERA records (updated October 2026), Grace Meadows's builder applied to MahaRERA to extend the completion date 5 times: to 30 November 2021, giving the reason "as layout for the property submitted to department dated 01-02-2018 and approved by the department dated 27-02-2020 which lost considerable time. and work was halted due to the approval process. we received further IOD approval only after the approval of the layout."; to 30 September 2022, giving the reason "DUE TO NEW RULE APPLIED FOR CIVIL AVIATION, OCCUPATION CERTIFICATE PROCESS DELAYED. WE HAVE COMPLETED THE 95.00% OF WORK AS PER ARCHITECT AND ENGINEER CERTIFICATE UPLOADED. WE REQUEST YOU TO EXTEND THE TIME PERIOD FOR THE REQUIRED OCCUPATION CERTIFICATE PROCESS"; to 31 March 2023, giving the reason "Architect Completion Certificate already issued for the Project. We are completing the formalities to obtain the OC."; to 31 March 2024, giving the reason "OCCUPANCY CERTIFICATE IS APPLIED FOR AND IS PENDING DUE TO CIVIL AVIATION MATTER OF DAHISAR AREA We have updated all the details as per your requirement. Form B updated with the entended date of completion. Form 2 signed by the architect and agreed and accepted by the promoter. Project details such as sold units, etc also updated."; to 31 March 2027, giving the reason "In accordance with circular no 28, we hereby apply for extension of our project u/s 7(3) in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of the pandemic of Covid-19. We have consent of 65.05% allottees for purpose of extension of RERA registration period of the said project.". MahaRERA also added its automatic 4-month extension for all eligible projects.

What is the RERA number of Grace Meadows?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Grace Meadows in Dahisar East, Mumbai is P51800007583.

Is Grace Meadows registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Grace Meadows is registered as P51800007583 and its status is "Registered and active".

What is the current construction status of Grace Meadows? How much work is done?

According to GharKundli's check of MahaRERA records (updated October 2026), Grace Meadows's status on MahaRERA is "Registered and active". As filed by the builder, slab work on Grace Meadows is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.

Does Grace Meadows have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is Grace Meadows safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Grace Meadows is registered on MahaRERA as P51800007583, its completion date has moved 76 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in Grace Meadows?

Grace Meadows is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) in the Mumbai region, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.

What is the stamp duty and registration cost for a flat in Grace Meadows?

For a flat in Grace Meadows (Mumbai), stamp duty is 6% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess. A woman buying in her own name pays 5%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹6 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator

Has Grace Meadows received its OC? Is it ready to move in?

Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Grace Meadows is still under construction, with 31 July 2027 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.

Has Grace Meadows uploaded its title report on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Grace Meadows was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.

No title report is on MahaRERA for this project. See which documents are missing →

How can I get updates if Grace Meadows's possession date changes?

The latest dates are on Grace Meadows's MahaRERA page (P51800007583). GharKundli's Kundli Watch sends a free WhatsApp update on Grace Meadows every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Grace Meadows have?

According to GharKundli's check of MahaRERA records (updated October 2026), Grace Meadows has one building filed: Grace Meadows with 18 floors.

How big is the land of Grace Meadows?

According to GharKundli's check of MahaRERA records (updated October 2026), Grace Meadows stands on 3,189 sq m of land (about 0.8 acres), with 2,828 sq m of sanctioned built-up area and 478 sq m of recreational open space.

What are the reviews of Grace Meadows?

Google Maps has reviews of Grace Meadows written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of Grace Meadows?

Grace Meadows by Grace Suburban Development Venture is in Dahisar East, Mumbai, pincode 400068 (near Dahisar West, Borivali West, Mandapeshwar), Maharashtra, and is registered on MahaRERA as P51800007583, per GharKundli's check of MahaRERA records. Its land is filed as 2728/2736/2748/2750/2752. GharKundli lists all 180 MahaRERA projects in Dahisar East (400068).

How many flats are in Grace Meadows?

According to GharKundli's check of MahaRERA records (updated October 2026), Grace Meadows has 117 homes in 1 tower registered on MahaRERA.

When was Grace Meadows registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Grace Meadows was registered on MahaRERA on 17 August 2017. GharKundli did not find a title report on the land on file there.

Does Grace Meadows have any legal issues or court cases?

2 court cases are listed for Grace Meadows on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.

A court case can stall a project or tie up the land. See what each case is about →

Who is the builder / developer of Grace Meadows?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Grace Suburban Development Venture.

All projects with possession due in 2027 in Mumbai Suburban →

Other projects in Dahisar East (400068)

All 180 projects in Dahisar East (400068) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.