AADITYA PLAZA

by JET BUILD DEVELOPERS(MUMBAI) · Malad West, MumbaiAlso near Malad East, Borivali, Goregaon West

Possession date of AADITYA PLAZA: 30 April 2027, moved from 31 December 2018 (96 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P51800002793, and currently active. Its completion date has moved from December 2018 to April 2027: 96 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects. 1 complaint is listed against it on MahaRERA.

Source: GharKundli’s check of MahaRERA records, October 2026.

What do you want to know about AADITYA PLAZA?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of AADITYA PLAZA has moved

  1. 31 December 2018

    Completion date given when the project was registered

  2. 31 December 2020

    Extended at the builder's request (MahaRERA application EXT51800000579)

    Reason the builder gave MahaRERA:
    “The project under reference being Slum Redevelopment Project, two buildings i.e. Rehab Building and Sale Building are being constructed. As already mentioned above construction of Rehab building has been completed before implementation of R…” Read the full reason“The project under reference being Slum Redevelopment Project, two buildings i.e. Rehab Building and Sale Building are being constructed. As already mentioned above construction of Rehab building has been completed before implementation of RERA Act and existing members/tenants have been accommodated in the rehab building and Part Occupation Certificate in respect of the Sale building has also been obtained. However, 11 existing members/tenants were running commercial shops in their old unit. Hence, we have accommodated these 11 shop owners in our sale building by providing them permanent alt…”
  3. 31 December 2020

    Extended at the builder's request (MahaRERA application EXT51800003706)

    Reason the builder gave MahaRERA:
    “AS OUR PROJECT PART OCCUPATION CERTIFICATE 19TH nOV 2017 HAD BEEN RECEIVED FOR SALE BUILDING AND HOWEVER 11 EXISTING SLUM DWELLERS WERE RUNNING COMMERCIAL SHOPS IN THEIR OLD UNIT, THESES SLUM DWELLERS HAVE BEEN PROVIDED WITH THEIR ALTERNATE…” Read the full reason“AS OUR PROJECT PART OCCUPATION CERTIFICATE 19TH nOV 2017 HAD BEEN RECEIVED FOR SALE BUILDING AND HOWEVER 11 EXISTING SLUM DWELLERS WERE RUNNING COMMERCIAL SHOPS IN THEIR OLD UNIT, THESES SLUM DWELLERS HAVE BEEN PROVIDED WITH THEIR ALTERNATE ACCOMMODATION IN OUR SALE BUILDING. THESE SHOPS FOR EXISTING MEMBERS HAVE BEEN EARN MARKED IN OUR PART OCCUPATION CERTIFICATE OF SALE BUILDING AS WELL. SINCE 3 OF THE SLUM DWELLERS DID NOT PROVE THEIR ELIGIBILITY IN TIME, SRA WAS NOT GRANTING FSI IN RESPECT OF THESE SLUM DWELLERS AND RESULTING INTO DELAY IN OBTAINING REQUISITE PERMISSION FOR FURTHER CONS…”
  4. 30 June 2022

    Extended at the builder's request (MahaRERA application EXT51800009998)

    Reason the builder gave MahaRERA: “construction of building has been completed 99%. Now we are preparing to fulfill compliance to obtain Occupation Certificate.”
  5. 30 December 2023

    Extended at the builder's request (MahaRERA application EXT51800013339)

    Reason the builder gave MahaRERA:
    “We hereby inform you that the said project is completed in all aspect and part OC is also received for Basement, Ground Floor, First and Second Floor (Commercial) and 3rd,4thand 5th Podium Floor which is already uploaded on MAHARERA site.We…” Read the full reason“We hereby inform you that the said project is completed in all aspect and part OC is also received for Basement, Ground Floor, First and Second Floor (Commercial) and 3rd,4thand 5th Podium Floor which is already uploaded on MAHARERA site.We have applied for remaining OC and it is expected soon. Further consent from buyers is also taken. However due to non-receipt of full OC, we are seeking extension of said project for further One(1) Years i.e.upto 30.12.2023.”
  6. 31 December 2024

    Extended at the builder's request (MahaRERA application EXT51800018596)

    Reason the builder gave MahaRERA: “We have already fulfilled the compliances of Occupancy Certificate (OC) and awaiting for the same to be issued from SRA. Same is under review and process as per the fresh guide lines hence expected to receive the full occupancy certificate.”
  7. 31 December 2026

    Extended at the builder's request (MahaRERA application EXT51800025981)

    Reason the builder gave MahaRERA:
    “I, Mr. Rakeshkumar Rameshchandra Shah, hereby declare the following with respect to the project “Aaditya Plaza” bearing registration number P51800002793 registered under MahaRERA, The Project is already complete and we have fulfilled the co…” Read the full reason“I, Mr. Rakeshkumar Rameshchandra Shah, hereby declare the following with respect to the project “Aaditya Plaza” bearing registration number P51800002793 registered under MahaRERA, The Project is already complete and we have fulfilled the compliances of Occupancy Certificate and applied for the same, Now we are waiting for the certifiate to be issued from the SRA department Same is under review and process as per the fresh guidelines. We are applying Extension under section 7(3), request you to please consider and grant us extension for the smooth process.”
  8. 30 April 2027

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: AADITYA PLAZA’s extension records on MahaRERA (P51800002793), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on AADITYA PLAZA

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 1 complaint, and how it ended
  • Construction pace against the April 2027 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51800002793
Status
Registered and active
Builder
JET BUILD DEVELOPERS(MUMBAI)
Location
Malad West, Mumbai · 400064
Project type
Others
Registered on
4 Aug 2017
Completion date at registration
December 2018
Latest completion date
April 2027
Delay so far
96 months
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Towers
1
Complaints on MahaRERA
1
Court cases listed
0
Appeals at the tribunal
2
Title report on file
Not found

Construction progress of AADITYA PLAZA, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
AADITYA PLAZA100%100%100%95%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on AADITYA PLAZA every month.

AADITYA PLAZA: buildings, flats and land, as filed on MahaRERA

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of AADITYA PLAZA →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

AADITYA PLAZA: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about AADITYA PLAZA

What is the possession date of AADITYA PLAZA?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for AADITYA PLAZA in Malad West, Mumbai is 30 April 2027 — 96 months later than 31 December 2018, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for AADITYA PLAZA?

Builders and listing sites often quote an earlier "target" date for handover. The completion date AADITYA PLAZA's builder has filed on MahaRERA, the official one, is 30 April 2027, already 96 months later than the 31 December 2018 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of AADITYA PLAZA extended?

According to GharKundli's check of MahaRERA records (updated October 2026), AADITYA PLAZA's builder applied to MahaRERA to extend the completion date 6 times: to 31 December 2020, giving the reason "The project under reference being Slum Redevelopment Project, two buildings i.e. Rehab Building and Sale Building are being constructed. As already mentioned above construction of Rehab building has been completed before implementation of RERA Act and existing members/tenants have been accommodated in the rehab building and Part Occupation Certificate in respect of the Sale building has also been obtained. However, 11 existing members/tenants were running commercial shops in their old unit. Hence, we have accommodated these 11 shop owners in our sale building by providing them permanent alt…"; to 31 December 2020, giving the reason "AS OUR PROJECT PART OCCUPATION CERTIFICATE 19TH nOV 2017 HAD BEEN RECEIVED FOR SALE BUILDING AND HOWEVER 11 EXISTING SLUM DWELLERS WERE RUNNING COMMERCIAL SHOPS IN THEIR OLD UNIT, THESES SLUM DWELLERS HAVE BEEN PROVIDED WITH THEIR ALTERNATE ACCOMMODATION IN OUR SALE BUILDING. THESE SHOPS FOR EXISTING MEMBERS HAVE BEEN EARN MARKED IN OUR PART OCCUPATION CERTIFICATE OF SALE BUILDING AS WELL. SINCE 3 OF THE SLUM DWELLERS DID NOT PROVE THEIR ELIGIBILITY IN TIME, SRA WAS NOT GRANTING FSI IN RESPECT OF THESE SLUM DWELLERS AND RESULTING INTO DELAY IN OBTAINING REQUISITE PERMISSION FOR FURTHER CONS…"; to 30 June 2022, giving the reason "construction of building has been completed 99%. Now we are preparing to fulfill compliance to obtain Occupation Certificate."; to 30 December 2023, giving the reason "We hereby inform you that the said project is completed in all aspect and part OC is also received for Basement, Ground Floor, First and Second Floor (Commercial) and 3rd,4thand 5th Podium Floor which is already uploaded on MAHARERA site.We have applied for remaining OC and it is expected soon. Further consent from buyers is also taken. However due to non-receipt of full OC, we are seeking extension of said project for further One(1) Years i.e.upto 30.12.2023."; to 31 December 2024, giving the reason "We have already fulfilled the compliances of Occupancy Certificate (OC) and awaiting for the same to be issued from SRA. Same is under review and process as per the fresh guide lines hence expected to receive the full occupancy certificate."; to 31 December 2026, giving the reason "I, Mr. Rakeshkumar Rameshchandra Shah, hereby declare the following with respect to the project “Aaditya Plaza” bearing registration number P51800002793 registered under MahaRERA, The Project is already complete and we have fulfilled the compliances of Occupancy Certificate and applied for the same, Now we are waiting for the certifiate to be issued from the SRA department Same is under review and process as per the fresh guidelines. We are applying Extension under section 7(3), request you to please consider and grant us extension for the smooth process.". MahaRERA also added its automatic 4-month extension for all eligible projects.

What is the RERA number of AADITYA PLAZA?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of AADITYA PLAZA in Malad West, Mumbai is P51800002793.

Is AADITYA PLAZA registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), AADITYA PLAZA is registered as P51800002793 and its status is "Registered and active".

What is the construction status of AADITYA PLAZA?

According to GharKundli's check of MahaRERA records (updated October 2026), AADITYA PLAZA's status on MahaRERA is "Registered and active". As filed by the builder, slab work on AADITYA PLAZA is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.

Does AADITYA PLAZA have complaints on MahaRERA?

1 complaint was listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Is AADITYA PLAZA safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), AADITYA PLAZA is registered on MahaRERA as P51800002793, its completion date has moved 96 months since registration and 1 complaint is listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if AADITYA PLAZA's possession date changes?

The latest dates are on AADITYA PLAZA's MahaRERA page (P51800002793). GharKundli's Kundli Watch sends a free WhatsApp update on AADITYA PLAZA every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does AADITYA PLAZA have?

According to GharKundli's check of MahaRERA records (updated October 2026), AADITYA PLAZA has one building filed: AADITYA PLAZA with 26 floors.

How big is the land of AADITYA PLAZA?

According to GharKundli's check of MahaRERA records (updated October 2026), AADITYA PLAZA stands on 1,729 sq m of land (about 0.4 acres), with 4,738 sq m of sanctioned built-up area.

Where can I read reviews of AADITYA PLAZA?

Google Maps has reviews of AADITYA PLAZA written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 1 complaint is listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is AADITYA PLAZA?

AADITYA PLAZA by JET BUILD DEVELOPERS(MUMBAI) is in Malad West, Mumbai (pincode 400064), near Malad East, Borivali, Goregaon West, Maharashtra, and is registered on MahaRERA as P51800002793, per GharKundli's check of MahaRERA records.

When was AADITYA PLAZA registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), AADITYA PLAZA was registered on MahaRERA on 4 August 2017. GharKundli did not find a title report on the land on file there.

Are there court cases on AADITYA PLAZA?

No court cases are listed for AADITYA PLAZA on MahaRERA, and 2 appeals at the tribunal, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.

Who is the builder of AADITYA PLAZA?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is JET BUILD DEVELOPERS(MUMBAI).

All projects with possession due in 2027 in Mumbai Suburban →

Other projects in pincode 400064

All 301 projects in Malad West (400064) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.