Infina Gardens
by Infina Ashapura Homes LLP · Ghatkopar East, Mumbai
Possession date of Infina Gardens: 31 October 2026, moved from 30 November 2020 (71 months later). This is the latest completion date the builder has filed on MahaRERA, and it has already passed. How to check it yourself
Registered on MahaRERA under P51800007427. Status: Lapsed (registration period ended). 2 complaints are listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, November 2026.
The latest completion date on MahaRERA (October 2026) has passed.
What do you want to know about Infina Gardens?
How the possession date of Infina Gardens has moved
30 November 2020
Completion date given when the project was registered
30 November 2021
Extended at the builder's request (MahaRERA application EXT51800009150)
Reason the builder gave MahaRERA: “Construction work of the ongoing project was halted due to nationwide lockdown imposed during Covid 19 Pandemic.”
31 October 2026
Extended at the builder's request (MahaRERA application EA01082621989)
Reason the builder gave MahaRERA: “OC recived”
Source: Infina Gardens’s extension records on MahaRERA (P51800007427), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Infina Gardens
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 2 complaints, and how it ended
- Construction pace against the October 2026 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51800007427
- Status
- Lapsed (registration period ended)
- Builder
- Infina Ashapura Homes LLP
- Location
- Ghatkopar East, Mumbai · 400075
- Project type
- Residential / Group Housing
- Registered on
- 17 Aug 2017
- Completion date at registration
- November 2020
- Latest completion date
- October 2026
- Delay so far
- 71 months
- Homes
- 6
- Sold or booked
- 17%
- Towers
- 3
- Complaints on MahaRERA
- 2
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of Infina Gardens, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| A | 100% | 100% | 100% | 100% |
| B | 0% | 0% | 0% | 0% |
| C | 100% | 100% | 100% | 100% |
Commencement certificate (CC), as filed on MahaRERA
- A: covers PLINTH LEVEL
- B: covers PLINTH LEVEL
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Infina Gardens every month.
Infina Gardens: buildings, flats and land, as filed on MahaRERA
- Buildings: A (4 floors, 4 units) · B (4 floors, 2 units) · C (4 floors)
- Land: 3,097 sq m (about 0.8 acres) · sanctioned built-up 1,135 sq m
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of Infina Gardens →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Infina Gardens: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about Infina Gardens
What is the possession date of Infina Gardens?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for Infina Gardens in Ghatkopar East, Mumbai is 31 October 2026 — 71 months later than 30 November 2020, the date given at registration. That date has already passed.
Is the builder's possession date different from the MahaRERA date for Infina Gardens?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Infina Gardens's builder has filed on MahaRERA, the official one, is 31 October 2026, already 71 months later than the 30 November 2020 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Infina Gardens extended?
According to GharKundli's check of MahaRERA records (updated November 2026), Infina Gardens's builder applied to MahaRERA to extend the completion date 2 times: to 30 November 2021, giving the reason "Construction work of the ongoing project was halted due to nationwide lockdown imposed during Covid 19 Pandemic."; to 31 October 2026, giving the reason "OC recived".
What is the RERA number of Infina Gardens?
According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of Infina Gardens in Ghatkopar East, Mumbai is P51800007427.
Is Infina Gardens registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), Infina Gardens is registered as P51800007427 and its status is "Lapsed (registration period ended)".
What is the construction status of Infina Gardens?
According to GharKundli's check of MahaRERA records (updated November 2026), Infina Gardens's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work ranges from 0% to 100% across 3 towers. GharKundli's full report compares construction progress with the deadline.
Does Infina Gardens have complaints on MahaRERA?
2 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is Infina Gardens safe to buy?
According to GharKundli's check of MahaRERA records (updated November 2026), Infina Gardens is registered on MahaRERA as P51800007427, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 71 months since registration and 2 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if Infina Gardens's possession date changes?
The latest dates are on Infina Gardens's MahaRERA page (P51800007427). GharKundli's Kundli Watch sends a free WhatsApp update on Infina Gardens every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Infina Gardens have?
According to GharKundli's check of MahaRERA records (updated November 2026), Infina Gardens has 3 buildings filed: A with 4 floors and 4 units; B with 4 floors and 2 units; C with 4 floors.
How big is the land of Infina Gardens?
According to GharKundli's check of MahaRERA records (updated November 2026), Infina Gardens stands on 3,097 sq m of land (about 0.8 acres), with 1,135 sq m of sanctioned built-up area.
Where can I read reviews of Infina Gardens?
Google Maps has reviews of Infina Gardens written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 2 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is Infina Gardens?
Infina Gardens by Infina Ashapura Homes LLP is in Ghatkopar East, Mumbai (pincode 400075), Maharashtra, and is registered on MahaRERA as P51800007427, per GharKundli's check of MahaRERA records.
How many homes are in Infina Gardens?
According to GharKundli's check of MahaRERA records (updated November 2026), Infina Gardens has 6 homes in 3 towers registered on MahaRERA, and 17% of them are sold or booked.
When was Infina Gardens registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), Infina Gardens was registered on MahaRERA on 17 August 2017. GharKundli did not find a title report on the land on file there.
Are there court cases on Infina Gardens?
No court cases are listed for Infina Gardens on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).
Who is the builder of Infina Gardens?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is Infina Ashapura Homes LLP.
Check it yourself on MahaRERA
- How to check the possession date of Infina Gardens
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2026 in Mumbai Suburban →
Other projects in Ghatkopar East
- Jai Arihant
- Terraform Dwarka - Wing D
- Avis Residency
- Omkaar Pride
- Om Shreepal
- PALATINA
- Manhattan Residency (A4) - upto 14th Floor
- North Sea Heights (A1) - upto 14th floor
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.