SHRADDHA AUTUMN PARK

by ATHARVA DEVELOPERS · Ghatkopar East, MumbaiAlso near Kanjurmarg East, Bhandup West, Kanjur East

Possession date of SHRADDHA AUTUMN PARK: 30 April 2028, moved from 30 December 2021 (72 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P51800007651, and currently active. Its completion date has moved from December 2021 to April 2028: 72 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects. 1 complaint is listed against it on MahaRERA.

Source: GharKundli’s check of MahaRERA records, October 2026.

What do you want to know about SHRADDHA AUTUMN PARK?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of SHRADDHA AUTUMN PARK has moved

  1. 30 December 2021

    Completion date given when the project was registered

  2. 31 December 2027

    Extended at the builder's request (MahaRERA application EXT51800012104)

    Reason the builder gave MahaRERA:
    “We sincerely apologize for the delay in the project's completion and the submission of this request. The delay has been caused by challenges related to procurement, unforeseen site conditions, coordination issues, and temporary financial co…” Read the full reason“We sincerely apologize for the delay in the project's completion and the submission of this request. The delay has been caused by challenges related to procurement, unforeseen site conditions, coordination issues, and temporary financial constraints. Despite these obstacles, we are making every effort to resolve these matters and finalize the remaining work. We are closely monitoring the progress and taking all necessary measures to ensure the timely completion of the project. As of now, building 1 and building 2 have been successfully completed, and we have obtained the Partial Occupancy C…”
  3. 30 April 2028

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: SHRADDHA AUTUMN PARK’s extension records on MahaRERA (P51800007651), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on SHRADDHA AUTUMN PARK

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 1 complaint and 2 court cases, and how it ended
  • Construction pace against the April 2028 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51800007651
Status
Registered and active
Builder
ATHARVA DEVELOPERS
Location
Ghatkopar East, Mumbai · 400042
Project type
Residential / Group Housing
Registered on
17 Aug 2017
Completion date at registration
December 2021
Latest completion date
April 2028
Delay so far
72 months
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
197
Towers
5
Complaints on MahaRERA
1
Court cases listed
2
Appeals at the tribunal
1
Title report on file
Not found
Builder's other MahaRERA projects
20

Construction progress of SHRADDHA AUTUMN PARK, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
BUILDING NO 1100%100%100%100%
BUILDING NO 2 WING A100%100%100%100%
BUILDING NO 2 WING B REHAB100%100%100%100%
BUILDING NO 3 WING A100%100%100%50%
BUILDING NO 3 WING B0%50%25%0%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on SHRADDHA AUTUMN PARK every month.

SHRADDHA AUTUMN PARK: buildings, flats and land, as filed on MahaRERA

  • Buildings: BUILDING NO 1 (25 floors) · BUILDING NO 2 WING A (25 floors) · BUILDING NO 2 WING B REHAB (25 floors) · BUILDING NO 3 WING A (24 floors) · BUILDING NO 3 WING B (25 floors)
  • Land: 3,850 sq m (about 1.0 acres) · sanctioned built-up 5,739 sq m · recreational space 1,008 sq m
  • Map: the location the builder filed on MahaRERA

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of SHRADDHA AUTUMN PARK →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

SHRADDHA AUTUMN PARK: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about SHRADDHA AUTUMN PARK

What is the possession date of SHRADDHA AUTUMN PARK?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for SHRADDHA AUTUMN PARK in Ghatkopar East, Mumbai is 30 April 2028 — 72 months later than 30 December 2021, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for SHRADDHA AUTUMN PARK?

Builders and listing sites often quote an earlier "target" date for handover. The completion date SHRADDHA AUTUMN PARK's builder has filed on MahaRERA, the official one, is 30 April 2028, already 72 months later than the 30 December 2021 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of SHRADDHA AUTUMN PARK extended?

According to GharKundli's check of MahaRERA records (updated October 2026), SHRADDHA AUTUMN PARK's builder applied to MahaRERA to extend the completion date once: to 31 December 2027, giving the reason "We sincerely apologize for the delay in the project's completion and the submission of this request. The delay has been caused by challenges related to procurement, unforeseen site conditions, coordination issues, and temporary financial constraints. Despite these obstacles, we are making every effort to resolve these matters and finalize the remaining work. We are closely monitoring the progress and taking all necessary measures to ensure the timely completion of the project. As of now, building 1 and building 2 have been successfully completed, and we have obtained the Partial Occupancy C…". MahaRERA also added its automatic 4-month extension for all eligible projects.

What is the RERA number of SHRADDHA AUTUMN PARK?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of SHRADDHA AUTUMN PARK in Ghatkopar East, Mumbai is P51800007651.

Is SHRADDHA AUTUMN PARK registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), SHRADDHA AUTUMN PARK is registered as P51800007651 and its status is "Registered and active".

What is the construction status of SHRADDHA AUTUMN PARK?

According to GharKundli's check of MahaRERA records (updated October 2026), SHRADDHA AUTUMN PARK's status on MahaRERA is "Registered and active". As filed by the builder, slab work ranges from 50% to 100% across 5 towers. GharKundli's full report compares construction progress with the deadline.

Does SHRADDHA AUTUMN PARK have complaints on MahaRERA?

1 complaint was listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Is SHRADDHA AUTUMN PARK safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), SHRADDHA AUTUMN PARK is registered on MahaRERA as P51800007651, its completion date has moved 72 months since registration and 1 complaint is listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if SHRADDHA AUTUMN PARK's possession date changes?

The latest dates are on SHRADDHA AUTUMN PARK's MahaRERA page (P51800007651). GharKundli's Kundli Watch sends a free WhatsApp update on SHRADDHA AUTUMN PARK every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does SHRADDHA AUTUMN PARK have?

According to GharKundli's check of MahaRERA records (updated October 2026), SHRADDHA AUTUMN PARK has 5 buildings filed: BUILDING NO 1 with 25 floors; BUILDING NO 2 WING A with 25 floors; BUILDING NO 2 WING B REHAB with 25 floors; BUILDING NO 3 WING A with 24 floors; BUILDING NO 3 WING B with 25 floors.

How big is the land of SHRADDHA AUTUMN PARK?

According to GharKundli's check of MahaRERA records (updated October 2026), SHRADDHA AUTUMN PARK stands on 3,850 sq m of land (about 1.0 acres), with 5,739 sq m of sanctioned built-up area and 1,008 sq m of recreational open space.

Where can I read reviews of SHRADDHA AUTUMN PARK?

Google Maps has reviews of SHRADDHA AUTUMN PARK written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 1 complaint is listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is SHRADDHA AUTUMN PARK?

SHRADDHA AUTUMN PARK by ATHARVA DEVELOPERS is in Ghatkopar East, Mumbai (pincode 400042), near Kanjurmarg East, Bhandup West, Kanjur East, Maharashtra, and is registered on MahaRERA as P51800007651, per GharKundli's check of MahaRERA records.

How many homes are in SHRADDHA AUTUMN PARK?

According to GharKundli's check of MahaRERA records (updated October 2026), SHRADDHA AUTUMN PARK has 197 homes in 5 towers registered on MahaRERA.

When was SHRADDHA AUTUMN PARK registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), SHRADDHA AUTUMN PARK was registered on MahaRERA on 17 August 2017. GharKundli did not find a title report on the land on file there.

Are there court cases on SHRADDHA AUTUMN PARK?

2 court cases are listed for SHRADDHA AUTUMN PARK on MahaRERA, and 1 appeal at the tribunal, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.

Who is the builder of SHRADDHA AUTUMN PARK?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is ATHARVA DEVELOPERS, which has 20 other projects registered on MahaRERA.

All projects with possession due in 2028 in Mumbai Suburban →

Other projects in Kurla

All 74 projects in Kanjurmarg East (400042) →

Other projects by ATHARVA DEVELOPERS

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.