by GREEN CITY BUILDERS · Main Road, NagpurAlso near Katolroad

Possession date of AMANS MANNAT: 31 July 2027, moved from 20 April 2021 (71 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P50500008476, and currently active. Its completion date has moved from April 2021 to July 2027: 71 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects. 1 complaint is listed against it on MahaRERA.

Source: GharKundli’s check of MahaRERA records, October 2026.

What do you want to know about AMANS MANNAT?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of AMANS MANNAT has moved

  1. 20 April 2021

    Completion date given when the project was registered

  2. 20 April 2022

    Extended at the builder's request (MahaRERA application EXT50500009544)

    Reason the builder gave MahaRERA: “THE REASON FOR DELAY ABOVE SAID SCHEME BECAUSE OF COVID-19 AND DUE NON AVAILABILITY OF LABOURS FOR CONSTRUCTION WORK .”
  3. 31 March 2024

    Extended at the builder's request (MahaRERA application EXT50500012777)

    Reason the builder gave MahaRERA: “Construction Work not yet completed.”
  4. 31 March 2025

    Extended at the builder's request (MahaRERA application EXT50500019642)

    Reason the builder gave MahaRERA: “Covid”
  5. 31 March 2027

    Extended at the builder's request (MahaRERA application EXT50500028343)

    Reason the builder gave MahaRERA:
    “Due to unforeseen circumstances, the project has experienced unavoidable delays. Despite our best efforts to adhere to the original schedule, factors have significantly impacted our progress. We assure you that we are committed to completin…” Read the full reason“Due to unforeseen circumstances, the project has experienced unavoidable delays. Despite our best efforts to adhere to the original schedule, factors have significantly impacted our progress. We assure you that we are committed to completing the project at the earliest and are taking all necessary measures to expedite construction while maintaining the highest quality and compliance standards. In light of the above, we kindly request MahaRERA to consider our application and grant an extension for the completion deadline.We sincerely appreciate your understanding and cooperation. Kindly let…”
  6. 31 July 2027

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: AMANS MANNAT’s extension records on MahaRERA (P50500008476), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on AMANS MANNAT

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 1 complaint, and how it ended
  • Construction pace against the July 2027 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay

Other wings and phases of this project

Each is registered on MahaRERA separately, with its own possession date. Check the one your flat is in.

MahaRERA registration
P50500008476
Status
Registered and active
Builder
GREEN CITY BUILDERS
Location
Main Road, Nagpur · 440013
Project type
Residential / Group Housing
Registered on
19 Aug 2017
Completion date at registration
April 2021
Latest completion date
July 2027
Delay so far
71 months
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
78
Sold or booked
63%
Towers
1
Complaints on MahaRERA
1
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
3

Construction progress of AMANS MANNAT, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
AMANS MANNAT100%100%85%45%

Commencement certificate (CC), as filed on MahaRERA

  • AMANS MANNAT: covers 13 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on AMANS MANNAT every month.

AMANS MANNAT: buildings, flats and land, as filed on MahaRERA

  • Buildings: AMANS MANNAT (15 floors, 78 units)
  • Land: 4,664 sq m (about 1.2 acres) · sanctioned built-up 5,830 sq m · recreational space 3,353 sq m
  • Boundaries filed include: AYYAPA TEMPLE AND RING ROAD, ROAD AND LAND MAHESH SADHWANI
  • Map: the location the builder filed on MahaRERA

The builder’s record and reviews

Green City Builders has 4 projects on MahaRERA since 2017, this one included. Of the 2 GharKundli has checked: 2 still being built, 2 past the promised date (typically 33 months late). 1 complaint on MahaRERA across 1 project.

Read Google reviews of AMANS MANNAT →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

AMANS MANNAT: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about AMANS MANNAT

What is the possession date of AMANS MANNAT?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for AMANS MANNAT in Main Road, Nagpur is 31 July 2027 — 71 months later than 20 April 2021, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for AMANS MANNAT?

Builders and listing sites often quote an earlier "target" date for handover. The completion date AMANS MANNAT's builder has filed on MahaRERA, the official one, is 31 July 2027, already 71 months later than the 20 April 2021 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of AMANS MANNAT extended?

According to GharKundli's check of MahaRERA records (updated October 2026), AMANS MANNAT's builder applied to MahaRERA to extend the completion date 4 times: to 20 April 2022, giving the reason "THE REASON FOR DELAY ABOVE SAID SCHEME BECAUSE OF COVID-19 AND DUE NON AVAILABILITY OF LABOURS FOR CONSTRUCTION WORK ."; to 31 March 2024, giving the reason "Construction Work not yet completed."; to 31 March 2025, giving the reason "Covid"; to 31 March 2027, giving the reason "Due to unforeseen circumstances, the project has experienced unavoidable delays. Despite our best efforts to adhere to the original schedule, factors have significantly impacted our progress. We assure you that we are committed to completing the project at the earliest and are taking all necessary measures to expedite construction while maintaining the highest quality and compliance standards. In light of the above, we kindly request MahaRERA to consider our application and grant an extension for the completion deadline.We sincerely appreciate your understanding and cooperation. Kindly let…". MahaRERA also added its automatic 4-month extension for all eligible projects.

What is the RERA number of AMANS MANNAT?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of AMANS MANNAT in Main Road, Nagpur is P50500008476.

Is AMANS MANNAT registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), AMANS MANNAT is registered as P50500008476 and its status is "Registered and active".

What is the construction status of AMANS MANNAT?

According to GharKundli's check of MahaRERA records (updated October 2026), AMANS MANNAT's status on MahaRERA is "Registered and active". As filed by the builder, slab work on AMANS MANNAT is 100% done and internal work 85%. GharKundli's full report compares construction progress with the deadline.

Does AMANS MANNAT have complaints on MahaRERA?

1 complaint was listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Is AMANS MANNAT safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), AMANS MANNAT is registered on MahaRERA as P50500008476, its completion date has moved 71 months since registration and 1 complaint is listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

Does AMANS MANNAT have other wings or phases?

Yes. MahaRERA lists 1 other registration of the same project, each with its own possession date: AMANS MANNAT-BLOCK C-1 (P50500048603, possession 31 Jul 2027). Check that your agreement names the registration of your own wing.

How can I get updates if AMANS MANNAT's possession date changes?

The latest dates are on AMANS MANNAT's MahaRERA page (P50500008476). GharKundli's Kundli Watch sends a free WhatsApp update on AMANS MANNAT every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does AMANS MANNAT have?

According to GharKundli's check of MahaRERA records (updated October 2026), AMANS MANNAT has one building filed: AMANS MANNAT with 15 floors and 78 units.

How big is the land of AMANS MANNAT?

According to GharKundli's check of MahaRERA records (updated October 2026), AMANS MANNAT stands on 4,664 sq m of land (about 1.2 acres), with 5,830 sq m of sanctioned built-up area and 3,353 sq m of recreational open space.

What is the track record of AMANS MANNAT's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Green City Builders has 4 projects on MahaRERA since 2017, this one included. Of the 2 GharKundli has checked: 2 still being built, 2 past the promised date (typically 33 months late). 1 complaint on MahaRERA across 1 project. GharKundli's full report covers the builder's record in detail.

Where can I read reviews of AMANS MANNAT?

Google Maps has reviews of AMANS MANNAT written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 1 complaint is listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is AMANS MANNAT?

AMANS MANNAT by GREEN CITY BUILDERS is in Main Road, Nagpur (pincode 440013), near Katolroad, Maharashtra, and is registered on MahaRERA as P50500008476, per GharKundli's check of MahaRERA records. Its boundaries filed there include AYYAPA TEMPLE AND RING ROAD, ROAD AND LAND MAHESH SADHWANI.

How many homes are in AMANS MANNAT?

According to GharKundli's check of MahaRERA records (updated October 2026), AMANS MANNAT has 78 homes in 1 tower registered on MahaRERA, and 63% of them are sold or booked.

When was AMANS MANNAT registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), AMANS MANNAT was registered on MahaRERA on 19 August 2017. GharKundli did not find a title report on the land on file there.

Are there court cases on AMANS MANNAT?

No court cases are listed for AMANS MANNAT on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder of AMANS MANNAT?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is GREEN CITY BUILDERS, which has 3 other projects registered on MahaRERA.

All projects with possession due in 2027 in Nagpur →

Other projects in Nagpur (Urban)

All 54 projects in Katolroad (440013) →

Other projects by GREEN CITY BUILDERS

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.