GALAXY PRAYAG

by SHASHANK PANDE · Ranapratap Nagar, NagpurAlso near Parsodi, A.D. Project, Khamla

Possession: GALAXY PRAYAG is marked completed on MahaRERA. How to check it yourself

Registered on MahaRERA under P50500010247. Status: Completed.

Source: GharKundli’s check of MahaRERA records, November 2026.

What do you want to know about GALAXY PRAYAG?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of GALAXY PRAYAG has moved

  1. 31 March 2019

    Completion date given when the project was registered

  2. 30 September 2021

    Extended at the builder's request (MahaRERA application EXT50500005030)

    Reason the builder gave MahaRERA: “HIGH COURT HAD PUT STAY ORDER ON PROJECT NOW ALL LEGAL DISPUTE WERE RESOLVED & I HAVE OBTAINED ALL NECESSARY PERMISSION FROM RESPECTIVE AUTHORITY. PLEASE ALLOW ME EXTENDED TIME PERIOD FOR PROJECT COMPLETION.”
  3. 30 September 2021

    Extended at the builder's request (MahaRERA application EXT50500005981)

    Reason the builder gave MahaRERA:
    “HIGH COURT HAS PUT STAY PERIOD ON THE PROJECT DUE TO SOME LITIGATION MATTER THUS PROMOTER CAN NOT COMPLETE PROJECT WITHIN THE DUE PERIOD SPECIFIED AT THE TIME OF REGISTRATION . NOW LITIGATION HAS ENDED IN MY FAVOUR & I HAVE RESTARTED THE PR…” Read the full reason“HIGH COURT HAS PUT STAY PERIOD ON THE PROJECT DUE TO SOME LITIGATION MATTER THUS PROMOTER CAN NOT COMPLETE PROJECT WITHIN THE DUE PERIOD SPECIFIED AT THE TIME OF REGISTRATION . NOW LITIGATION HAS ENDED IN MY FAVOUR & I HAVE RESTARTED THE PROJECT. I REQUEST YOU TO EXTEND TIME PERIOD FOR COMPLETION OF MY PROJECT “GALAXY PRAYAG” BY 18 MONTHS.”
  4. 30 November 2022

    Extended at the builder's request (MahaRERA application EXT50500012652)

    Reason the builder gave MahaRERA: “application for completion submitted awaited from competent authority”
  5. 31 March 2023

    Extended at the builder's request (MahaRERA application EXT50500012986)

    Reason the builder gave MahaRERA:
    “The building is complete and architect certificate is also issued. The application to Nagpur Municipal corporation is also fined for issue of completion certificate. The application for Airport NOC is also made. The approvals are pending fr…” Read the full reason“The building is complete and architect certificate is also issued. The application to Nagpur Municipal corporation is also fined for issue of completion certificate. The application for Airport NOC is also made. The approvals are pending from the authority”

Source: GALAXY PRAYAG’s extension records on MahaRERA (P50500010247), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on GALAXY PRAYAG

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the March 2023 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P50500010247
Status
Completed
Builder
SHASHANK PANDE
Location
Ranapratap Nagar, Nagpur · 440022
Project type
Residential / Group Housing
Registered on
24 Aug 2017
Completion date at registration
March 2019
Latest completion date
March 2023
Delay so far
48 months
Homes
48
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
1

Construction progress of GALAXY PRAYAG, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
GALAXY PRAYAG100%100%100%90%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on GALAXY PRAYAG every month.

GALAXY PRAYAG: buildings, flats and land, as filed on MahaRERA

The builder’s record and reviews

Shashank Pande has 2 projects on MahaRERA since 2017, this one included. Of the 2 GharKundli has checked: 1 finished, 0 within the promised date and 1 needed more time (typically 46 months); 1 still being built, 1 past the promised date (typically 9 months late). No complaints on MahaRERA.

Read Google reviews of GALAXY PRAYAG →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

GALAXY PRAYAG: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about GALAXY PRAYAG

What is the possession date of GALAXY PRAYAG?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for GALAXY PRAYAG in Ranapratap Nagar, Nagpur is 31 March 2023 — 48 months later than 31 March 2019, the date given at registration.

Is the builder's possession date different from the MahaRERA date for GALAXY PRAYAG?

Builders and listing sites often quote an earlier "target" date for handover. The completion date GALAXY PRAYAG's builder has filed on MahaRERA, the official one, is 31 March 2023, already 48 months later than the 31 March 2019 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of GALAXY PRAYAG extended?

According to GharKundli's check of MahaRERA records (updated November 2026), GALAXY PRAYAG's builder applied to MahaRERA to extend the completion date 4 times: to 30 September 2021, giving the reason "HIGH COURT HAD PUT STAY ORDER ON PROJECT NOW ALL LEGAL DISPUTE WERE RESOLVED & I HAVE OBTAINED ALL NECESSARY PERMISSION FROM RESPECTIVE AUTHORITY. PLEASE ALLOW ME EXTENDED TIME PERIOD FOR PROJECT COMPLETION."; to 30 September 2021, giving the reason "HIGH COURT HAS PUT STAY PERIOD ON THE PROJECT DUE TO SOME LITIGATION MATTER THUS PROMOTER CAN NOT COMPLETE PROJECT WITHIN THE DUE PERIOD SPECIFIED AT THE TIME OF REGISTRATION . NOW LITIGATION HAS ENDED IN MY FAVOUR & I HAVE RESTARTED THE PROJECT. I REQUEST YOU TO EXTEND TIME PERIOD FOR COMPLETION OF MY PROJECT “GALAXY PRAYAG” BY 18 MONTHS."; to 30 November 2022, giving the reason "application for completion submitted awaited from competent authority"; to 31 March 2023, giving the reason "The building is complete and architect certificate is also issued. The application to Nagpur Municipal corporation is also fined for issue of completion certificate. The application for Airport NOC is also made. The approvals are pending from the authority".

What is the RERA number of GALAXY PRAYAG?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of GALAXY PRAYAG in Ranapratap Nagar, Nagpur is P50500010247.

Is GALAXY PRAYAG registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), GALAXY PRAYAG is registered as P50500010247 and its status is "Completed".

What is the construction status of GALAXY PRAYAG?

According to GharKundli's check of MahaRERA records (updated November 2026), GALAXY PRAYAG's status on MahaRERA is "Completed". As filed by the builder, slab work on GALAXY PRAYAG is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.

Does GALAXY PRAYAG have complaints on MahaRERA?

No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.

Is GALAXY PRAYAG safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), GALAXY PRAYAG is registered on MahaRERA as P50500010247, its MahaRERA status is "Completed", its completion date has moved 48 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if GALAXY PRAYAG's possession date changes?

The latest dates are on GALAXY PRAYAG's MahaRERA page (P50500010247). GharKundli's Kundli Watch sends a free WhatsApp update on GALAXY PRAYAG every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does GALAXY PRAYAG have?

According to GharKundli's check of MahaRERA records (updated November 2026), GALAXY PRAYAG has one building filed: GALAXY PRAYAG with 15 floors.

How big is the land of GALAXY PRAYAG?

According to GharKundli's check of MahaRERA records (updated November 2026), GALAXY PRAYAG stands on 1,500 sq m of land (about 0.4 acres), with 3,212 sq m of sanctioned built-up area.

What is the track record of GALAXY PRAYAG's builder?

According to GharKundli's check of MahaRERA records (updated November 2026), Shashank Pande has 2 projects on MahaRERA since 2017, this one included. Of the 2 GharKundli has checked: 1 finished, 0 within the promised date and 1 needed more time (typically 46 months); 1 still being built, 1 past the promised date (typically 9 months late). No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.

Where can I read reviews of GALAXY PRAYAG?

Google Maps has reviews of GALAXY PRAYAG written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is GALAXY PRAYAG?

GALAXY PRAYAG by SHASHANK PANDE is in Ranapratap Nagar, Nagpur (pincode 440022), near Parsodi, A.D. Project, Khamla, Maharashtra, and is registered on MahaRERA as P50500010247, per GharKundli's check of MahaRERA records.

How many homes are in GALAXY PRAYAG?

According to GharKundli's check of MahaRERA records (updated November 2026), GALAXY PRAYAG has 48 homes in 1 tower registered on MahaRERA.

When was GALAXY PRAYAG registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), GALAXY PRAYAG was registered on MahaRERA on 24 August 2017. GharKundli did not find a title report on the land on file there.

Are there court cases on GALAXY PRAYAG?

No court cases are listed for GALAXY PRAYAG on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).

Who is the builder of GALAXY PRAYAG?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is SHASHANK PANDE, which has 1 other project registered on MahaRERA.

Other projects in pincode 440022

All 52 projects in Ranapratap Nagar (440022) →

Other projects by SHASHANK PANDE

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.