by MALHAR MAHENDRA TAYWADE · Ranapratap Nagar, NagpurAlso near Laxmi Nagar, Mouje Ajni, Neeri

Possession date of MAHENDRA REGALIA: 30 March 2027, moved from 30 November 2025 (12 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P50500055276, and currently active. Its completion date has moved from November 2025 to March 2027: 12 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.

Source: GharKundli’s check of MahaRERA records, October 2026.

What do you want to know about MAHENDRA REGALIA?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of MAHENDRA REGALIA has moved

  1. 30 November 2025

    Completion date given when the project was registered

  2. 30 November 2026

    Extended at the builder's request (MahaRERA application EA24112518418)

    Reason the builder gave MahaRERA: “Due to labour shortage in areas, we were unable to complete the project in extended time”
  3. 30 March 2027

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: MAHENDRA REGALIA’s extension records on MahaRERA (P50500055276), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on MAHENDRA REGALIA

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the March 2027 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P50500055276
Status
Registered and active
Builder
MALHAR MAHENDRA TAYWADE
Location
Ranapratap Nagar, Nagpur · 440022
Project type
Residential / Group Housing
Registered on
14 Mar 2024
Completion date at registration
November 2025
Latest completion date
March 2027
Delay so far
12 months
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
18
Sold or booked
90%
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found

Construction progress of MAHENDRA REGALIA, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
MAHENDRA REGALIA100%100%100%70%

Commencement certificate (CC), as filed on MahaRERA

  • MAHENDRA REGALIA: covers 10 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on MAHENDRA REGALIA every month.

MAHENDRA REGALIA: buildings, flats and land, as filed on MahaRERA

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of MAHENDRA REGALIA →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

MAHENDRA REGALIA: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about MAHENDRA REGALIA

What is the possession date of MAHENDRA REGALIA?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for MAHENDRA REGALIA in Ranapratap Nagar, Nagpur is 30 March 2027 — 12 months later than 30 November 2025, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for MAHENDRA REGALIA?

Builders and listing sites often quote an earlier "target" date for handover. The completion date MAHENDRA REGALIA's builder has filed on MahaRERA, the official one, is 30 March 2027, already 12 months later than the 30 November 2025 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of MAHENDRA REGALIA extended?

According to GharKundli's check of MahaRERA records (updated October 2026), MAHENDRA REGALIA's builder applied to MahaRERA to extend the completion date once: to 30 November 2026, giving the reason "Due to labour shortage in areas, we were unable to complete the project in extended time". MahaRERA also added its automatic 4-month extension for all eligible projects.

What is the RERA number of MAHENDRA REGALIA?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of MAHENDRA REGALIA in Ranapratap Nagar, Nagpur is P50500055276.

Is MAHENDRA REGALIA registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), MAHENDRA REGALIA is registered as P50500055276 and its status is "Registered and active".

What is the construction status of MAHENDRA REGALIA?

According to GharKundli's check of MahaRERA records (updated October 2026), MAHENDRA REGALIA's status on MahaRERA is "Registered and active". As filed by the builder, slab work on MAHENDRA REGALIA is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.

Does MAHENDRA REGALIA have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is MAHENDRA REGALIA safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), MAHENDRA REGALIA is registered on MahaRERA as P50500055276, its completion date has moved 12 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if MAHENDRA REGALIA's possession date changes?

The latest dates are on MAHENDRA REGALIA's MahaRERA page (P50500055276). GharKundli's Kundli Watch sends a free WhatsApp update on MAHENDRA REGALIA every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does MAHENDRA REGALIA have?

According to GharKundli's check of MahaRERA records (updated October 2026), MAHENDRA REGALIA has one building filed: MAHENDRA REGALIA with 10 floors and 18 units.

How much parking does MAHENDRA REGALIA have?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 17 covered car parking spaces for MAHENDRA REGALIA.

How big is the land of MAHENDRA REGALIA?

According to GharKundli's check of MahaRERA records (updated October 2026), MAHENDRA REGALIA stands on 743 sq m of land (about 0.2 acres), with 2,663 sq m of sanctioned built-up area.

Where can I read reviews of MAHENDRA REGALIA?

Google Maps has reviews of MAHENDRA REGALIA written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is MAHENDRA REGALIA?

MAHENDRA REGALIA by MALHAR MAHENDRA TAYWADE is in Ranapratap Nagar, Nagpur (pincode 440022), near Laxmi Nagar, Mouje Ajni, Neeri, Maharashtra, and is registered on MahaRERA as P50500055276, per GharKundli's check of MahaRERA records.

How many homes are in MAHENDRA REGALIA?

According to GharKundli's check of MahaRERA records (updated October 2026), MAHENDRA REGALIA has 18 homes in 1 tower registered on MahaRERA, and 90% of them are sold or booked.

When was MAHENDRA REGALIA registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), MAHENDRA REGALIA was registered on MahaRERA on 14 March 2024. GharKundli did not find a title report on the land on file there.

Are there court cases on MAHENDRA REGALIA?

No court cases are listed for MAHENDRA REGALIA on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder of MAHENDRA REGALIA?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is MALHAR MAHENDRA TAYWADE.

All projects with possession due in 2027 in Nagpur →

Other projects in pincode 440022