DHANBHOOMI 2
by TIRUPATI DEVELOPERS · Hingna, Nagpur
Possession date of DHANBHOOMI 2: 30 September 2027, moved from 30 September 2023 (48 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P50500027114, and currently active.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about DHANBHOOMI 2?
How the possession date of DHANBHOOMI 2 has moved
30 September 2023
Completion date given when the project was registered
30 September 2024
Extended at the builder's request (MahaRERA application EXT50500017644)
Reason the builder gave MahaRERA: “Due to pandemic of Covid, we faced extreme labour shortages and disruption in work completion due to which we couldn’t complete the project on time”
30 September 2025
Extended at the builder's request (MahaRERA application EXT50500024817)
Reason the builder gave MahaRERA: “Technical glitches on MahaCriti, a new site launched by MahaRERA and labour shortage in areas, we were unable to complete the project in extended time”
30 September 2026
Extended at the builder's request (MahaRERA application EA23092502676)
Reason the builder gave MahaRERA: “Due to technical glitches on MahaCriti, a new site launched by MahaRERA and labour shortage in areas, we were unable to complete the project in extended time”
30 January 2027
Extended at the builder's request
30 September 2027
Extended at the builder's request (MahaRERA application EA11092622530)
Reason the builder gave MahaRERA:
“Due to delays in the availability and supply of construction materials and non-availability of suitable contractors for the remaining construction works, the project progress was affected, and the project could not be completed within the e…” Read the full reason
“Due to delays in the availability and supply of construction materials and non-availability of suitable contractors for the remaining construction works, the project progress was affected, and the project could not be completed within the extended time.”
Source: DHANBHOOMI 2’s extension records on MahaRERA (P50500027114), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on DHANBHOOMI 2
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the September 2027 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
Other wings and phases of this project
Each is registered on MahaRERA separately, with its own possession date. Check the one your flat is in.
- DHANBHOOMI 1P50500008320
- MahaRERA registration
- P50500027114
- Status
- Registered and active
- Builder
- TIRUPATI DEVELOPERS
- Location
- Hingna, Nagpur · 440023
- Project type
- Plotted
- Registered on
- 19 Nov 2020
- Completion date at registration
- September 2023
- Latest completion date
- September 2027
- Delay so far
- 48 months
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 81
DHANBHOOMI 2: buildings, flats and land, as filed on MahaRERA
- Land: 19,630 sq m (about 4.9 acres) · recreational space 3,677 sq m
The builder’s record and reviews
Tirupati Developers has 43 projects on MahaRERA since 2018, this one included. Of the 43 GharKundli has checked: 34 finished, 28 within the promised date and 6 needed more time (typically 37 months); 9 still being built, 2 past the promised date (typically 47 months late). 2 complaints on MahaRERA across 2 projects.
Read Google reviews of DHANBHOOMI 2 →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
DHANBHOOMI 2: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about DHANBHOOMI 2
What is the possession date of DHANBHOOMI 2?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for DHANBHOOMI 2 in Hingna, Nagpur is 30 September 2027 — 48 months later than 30 September 2023, the date given at registration.
Is the builder's possession date different from the MahaRERA date for DHANBHOOMI 2?
Builders and listing sites often quote an earlier "target" date for handover. The completion date DHANBHOOMI 2's builder has filed on MahaRERA, the official one, is 30 September 2027, already 48 months later than the 30 September 2023 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of DHANBHOOMI 2 extended?
According to GharKundli's check of MahaRERA records (updated October 2026), DHANBHOOMI 2's builder applied to MahaRERA to extend the completion date 5 times: to 30 September 2024, giving the reason "Due to pandemic of Covid, we faced extreme labour shortages and disruption in work completion due to which we couldn’t complete the project on time"; to 30 September 2025, giving the reason "Technical glitches on MahaCriti, a new site launched by MahaRERA and labour shortage in areas, we were unable to complete the project in extended time"; to 30 September 2026, giving the reason "Due to technical glitches on MahaCriti, a new site launched by MahaRERA and labour shortage in areas, we were unable to complete the project in extended time"; to 30 January 2027; to 30 September 2027, giving the reason "Due to delays in the availability and supply of construction materials and non-availability of suitable contractors for the remaining construction works, the project progress was affected, and the project could not be completed within the extended time.".
What is the RERA number of DHANBHOOMI 2?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of DHANBHOOMI 2 in Hingna, Nagpur is P50500027114.
Is DHANBHOOMI 2 registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), DHANBHOOMI 2 is registered as P50500027114 and its status is "Registered and active".
What is the construction status of DHANBHOOMI 2?
According to GharKundli's check of MahaRERA records (updated October 2026), DHANBHOOMI 2's status on MahaRERA is "Registered and active". GharKundli's full report compares construction progress with the deadline.
Does DHANBHOOMI 2 have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is DHANBHOOMI 2 safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), DHANBHOOMI 2 is registered on MahaRERA as P50500027114, its completion date has moved 48 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
Does DHANBHOOMI 2 have other wings or phases?
Yes. MahaRERA lists 1 other registration of the same project, each with its own possession date: DHANBHOOMI 1 (P50500008320). Check that your agreement names the registration of your own wing.
How can I get updates if DHANBHOOMI 2's possession date changes?
The latest dates are on DHANBHOOMI 2's MahaRERA page (P50500027114). GharKundli's Kundli Watch sends a free WhatsApp update on DHANBHOOMI 2 every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How big is the land of DHANBHOOMI 2?
According to GharKundli's check of MahaRERA records (updated October 2026), DHANBHOOMI 2 stands on 19,630 sq m of land (about 4.9 acres) and 3,677 sq m of recreational open space.
What is the track record of DHANBHOOMI 2's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Tirupati Developers has 43 projects on MahaRERA since 2018, this one included. Of the 43 GharKundli has checked: 34 finished, 28 within the promised date and 6 needed more time (typically 37 months); 9 still being built, 2 past the promised date (typically 47 months late). 2 complaints on MahaRERA across 2 projects. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of DHANBHOOMI 2?
Google Maps has reviews of DHANBHOOMI 2 written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is DHANBHOOMI 2?
DHANBHOOMI 2 by TIRUPATI DEVELOPERS is in Hingna, Nagpur (pincode 440023), Maharashtra, and is registered on MahaRERA as P50500027114, per GharKundli's check of MahaRERA records.
When was DHANBHOOMI 2 registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), DHANBHOOMI 2 was registered on MahaRERA on 19 November 2020. GharKundli did not find a title report on the land on file there.
Are there court cases on DHANBHOOMI 2?
No court cases are listed for DHANBHOOMI 2 on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder of DHANBHOOMI 2?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is TIRUPATI DEVELOPERS, which has 81 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of DHANBHOOMI 2
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2027 in Nagpur →
Other projects in Hingna
- M/S HINGNA PRIDE
- PLATINUM HOMES
- RAMNAGRI II
- GREENFIELD-5
- LAXMI RESIDENCY
- RAJOLI GREENS 2
- RAJOLI GREENS 1
- SWAMI NAGARI-3
Other projects by TIRUPATI DEVELOPERS
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.