SILVER CITY

by TIRUPATI DEVELOPERS · Kothewada, Nagpur

Possession date of SILVER CITY: 31 July 2027, moved from 30 September 2020 (78 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P50500018573, and currently active. Its completion date has moved from September 2020 to July 2027: 78 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects. 1 complaint is listed against it on MahaRERA.

Source: GharKundli’s check of MahaRERA records, October 2026.

What do you want to know about SILVER CITY?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of SILVER CITY has moved

  1. 30 September 2020

    Completion date given when the project was registered

  2. 30 September 2021

    Extended at the builder's request (MahaRERA application EXT50500008504)

    Reason the builder gave MahaRERA: “DUE TO PANDEMIC OF COVID 19 WE ARE UNABLE TO DO DEVELOPEMENT ACTIVITIES BEACUSE OF LACK OF MAN POWER AND FUND PROBLEM THATS WHY WE WANT TO EXTEND THE PROJECT DATE UPTO 18 NOV 2021”
  3. 31 March 2024

    Extended at the builder's request (MahaRERA application EXT50500011441)

    Reason the builder gave MahaRERA:
    “Due to the Corona pandemic the work on the site was stopped for about two years. Now we have completed about 80% of work on site. We estimate that we would be able to finish the remaining work by the end of March 2024. Hence we humbly reque…” Read the full reason“Due to the Corona pandemic the work on the site was stopped for about two years. Now we have completed about 80% of work on site. We estimate that we would be able to finish the remaining work by the end of March 2024. Hence we humbly request you to give us extension till end of March 2024 and oblige.”
  4. 31 March 2025

    Extended at the builder's request (MahaRERA application EXT50500024303)

    Reason the builder gave MahaRERA: “Due to Elections and labour shortage in areas, we were unable to complete the project in extended time.”
  5. 31 March 2026

    Extended at the builder's request (MahaRERA application EXT50500028278)

    Reason the builder gave MahaRERA: “Due labour Shortage in the area, we were unable to complete the project”
  6. 31 March 2027

    Extended at the builder's request (MahaRERA application EA27022620030)

    Reason the builder gave MahaRERA:
    “Due to technical issues encountered on MahaCriti, the newly launched platform by MahaRERA, and delays in receiving completion certificate for the development work carried out on the aforesaid project, from the Planning Authority we were una…” Read the full reason“Due to technical issues encountered on MahaCriti, the newly launched platform by MahaRERA, and delays in receiving completion certificate for the development work carried out on the aforesaid project, from the Planning Authority we were unable to complete the project in extended time.”
  7. 31 July 2027

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: SILVER CITY’s extension records on MahaRERA (P50500018573), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on SILVER CITY

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 1 complaint, and how it ended
  • Construction pace against the July 2027 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P50500018573
Status
Registered and active
Builder
TIRUPATI DEVELOPERS
Location
Kothewada, Nagpur · 441110
Project type
Plotted
Registered on
15 Nov 2018
Completion date at registration
September 2020
Latest completion date
July 2027
Delay so far
78 months
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Complaints on MahaRERA
1
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
81

SILVER CITY: buildings, flats and land, as filed on MahaRERA

  • Land: 34,564 sq m (about 8.5 acres) · recreational space 4,457 sq m

The builder’s record and reviews

Tirupati Developers has 43 projects on MahaRERA since 2018, this one included. Of the 43 GharKundli has checked: 34 finished, 28 within the promised date and 6 needed more time (typically 37 months); 9 still being built, 2 past the promised date (typically 47 months late). 2 complaints on MahaRERA across 2 projects.

Read Google reviews of SILVER CITY →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

SILVER CITY: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about SILVER CITY

What is the possession date of SILVER CITY?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for SILVER CITY in Kothewada, Nagpur is 31 July 2027 — 78 months later than 30 September 2020, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for SILVER CITY?

Builders and listing sites often quote an earlier "target" date for handover. The completion date SILVER CITY's builder has filed on MahaRERA, the official one, is 31 July 2027, already 78 months later than the 30 September 2020 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of SILVER CITY extended?

According to GharKundli's check of MahaRERA records (updated October 2026), SILVER CITY's builder applied to MahaRERA to extend the completion date 5 times: to 30 September 2021, giving the reason "DUE TO PANDEMIC OF COVID 19 WE ARE UNABLE TO DO DEVELOPEMENT ACTIVITIES BEACUSE OF LACK OF MAN POWER AND FUND PROBLEM THATS WHY WE WANT TO EXTEND THE PROJECT DATE UPTO 18 NOV 2021"; to 31 March 2024, giving the reason "Due to the Corona pandemic the work on the site was stopped for about two years. Now we have completed about 80% of work on site. We estimate that we would be able to finish the remaining work by the end of March 2024. Hence we humbly request you to give us extension till end of March 2024 and oblige."; to 31 March 2025, giving the reason "Due to Elections and labour shortage in areas, we were unable to complete the project in extended time."; to 31 March 2026, giving the reason "Due labour Shortage in the area, we were unable to complete the project"; to 31 March 2027, giving the reason "Due to technical issues encountered on MahaCriti, the newly launched platform by MahaRERA, and delays in receiving completion certificate for the development work carried out on the aforesaid project, from the Planning Authority we were unable to complete the project in extended time.". MahaRERA also added its automatic 4-month extension for all eligible projects.

What is the RERA number of SILVER CITY?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of SILVER CITY in Kothewada, Nagpur is P50500018573.

Is SILVER CITY registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), SILVER CITY is registered as P50500018573 and its status is "Registered and active".

What is the construction status of SILVER CITY?

According to GharKundli's check of MahaRERA records (updated October 2026), SILVER CITY's status on MahaRERA is "Registered and active". GharKundli's full report compares construction progress with the deadline.

Does SILVER CITY have complaints on MahaRERA?

1 complaint was listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Is SILVER CITY safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), SILVER CITY is registered on MahaRERA as P50500018573, its completion date has moved 78 months since registration and 1 complaint is listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if SILVER CITY's possession date changes?

The latest dates are on SILVER CITY's MahaRERA page (P50500018573). GharKundli's Kundli Watch sends a free WhatsApp update on SILVER CITY every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How big is the land of SILVER CITY?

According to GharKundli's check of MahaRERA records (updated October 2026), SILVER CITY stands on 34,564 sq m of land (about 8.5 acres) and 4,457 sq m of recreational open space.

What is the track record of SILVER CITY's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Tirupati Developers has 43 projects on MahaRERA since 2018, this one included. Of the 43 GharKundli has checked: 34 finished, 28 within the promised date and 6 needed more time (typically 37 months); 9 still being built, 2 past the promised date (typically 47 months late). 2 complaints on MahaRERA across 2 projects. GharKundli's full report covers the builder's record in detail.

Where can I read reviews of SILVER CITY?

Google Maps has reviews of SILVER CITY written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 1 complaint is listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is SILVER CITY?

SILVER CITY by TIRUPATI DEVELOPERS is in Kothewada, Nagpur (pincode 441110), Maharashtra, and is registered on MahaRERA as P50500018573, per GharKundli's check of MahaRERA records.

When was SILVER CITY registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), SILVER CITY was registered on MahaRERA on 15 November 2018. GharKundli did not find a title report on the land on file there.

Are there court cases on SILVER CITY?

No court cases are listed for SILVER CITY on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder of SILVER CITY?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is TIRUPATI DEVELOPERS, which has 81 other projects registered on MahaRERA.

All projects with possession due in 2027 in Nagpur →

Other projects in Hingna

All 169 projects in Hingna (441110) →

Other projects by TIRUPATI DEVELOPERS

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.