ARPAN CHS LTD

by PARSHVANATH SUPERSTRUCTURES PRIVATE LIMITED · Kandivali W, MumbaiAlso near Bandra, Iraniwadi, Malad West

Possession date of ARPAN CHS LTD: 30 June 2024, moved from 31 December 2019 (54 months later). This is the latest completion date the builder has filed on MahaRERA, and it has already passed. How to check it yourself

Registered on MahaRERA under P51800006250. Status: Lapsed (registration period ended). 2 complaints are listed against it on MahaRERA.

Source: GharKundli’s check of MahaRERA records, November 2026.

The latest completion date on MahaRERA (June 2024) has passed.

What do you want to know about ARPAN CHS LTD?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of ARPAN CHS LTD has moved

  1. 31 December 2019

    Completion date given when the project was registered

  2. 31 December 2021

    Extended at the builder's request (MahaRERA application EXT51800006004)

    Reason the builder gave MahaRERA: “CHANGE IN DCR REQUIRED REVISED CONCESSIONS WHICH GOT DELAYED . MARKET CONDITION.”
  3. 30 June 2024

    Extended at the builder's request (MahaRERA application EXT51800015069)

    Reason the builder gave MahaRERA: “DUE TO COVID PENDAMIC AND DUE TO CHANGES IN BMC POLICY AND UNFORSEEN CIRCUMSTANCES IN PROMOTERS FAMILY”

Source: ARPAN CHS LTD’s extension records on MahaRERA (P51800006250), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on ARPAN CHS LTD

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 2 complaints, and how it ended
  • Construction pace against the June 2024 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51800006250
Status
Lapsed (registration period ended)
Builder
PARSHVANATH SUPERSTRUCTURES PRIVATE LIMITED
Location
Kandivali W, Mumbai · 400067
Project type
Residential / Group Housing
Registered on
14 Aug 2017
Completion date at registration
December 2019
Latest completion date
June 2024
Delay so far
54 months
Homes
26
Towers
1
Complaints on MahaRERA
2
Court cases listed
0
Title report on file
Not found

Construction progress of ARPAN CHS LTD, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
ARPAN CHS LTD100%11%80%50%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on ARPAN CHS LTD every month.

ARPAN CHS LTD: buildings, flats and land, as filed on MahaRERA

The builder’s record and reviews

Parshvanath Superstructures (a group of 2 linked companies) has 2 projects on MahaRERA since 2017, this one included. Of the 2 GharKundli has checked: 2 lapsed. 4 complaints on MahaRERA across 2 projects.

Read Google reviews of ARPAN CHS LTD →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

ARPAN CHS LTD: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about ARPAN CHS LTD

What is the possession date of ARPAN CHS LTD?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for ARPAN CHS LTD in Kandivali W, Mumbai is 30 June 2024 — 54 months later than 31 December 2019, the date given at registration. That date has already passed.

Is the builder's possession date different from the MahaRERA date for ARPAN CHS LTD?

Builders and listing sites often quote an earlier "target" date for handover. The completion date ARPAN CHS LTD's builder has filed on MahaRERA, the official one, is 30 June 2024, already 54 months later than the 31 December 2019 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of ARPAN CHS LTD extended?

According to GharKundli's check of MahaRERA records (updated November 2026), ARPAN CHS LTD's builder applied to MahaRERA to extend the completion date 2 times: to 31 December 2021, giving the reason "CHANGE IN DCR REQUIRED REVISED CONCESSIONS WHICH GOT DELAYED . MARKET CONDITION."; to 30 June 2024, giving the reason "DUE TO COVID PENDAMIC AND DUE TO CHANGES IN BMC POLICY AND UNFORSEEN CIRCUMSTANCES IN PROMOTERS FAMILY".

What is the RERA number of ARPAN CHS LTD?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of ARPAN CHS LTD in Kandivali W, Mumbai is P51800006250.

Is ARPAN CHS LTD registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), ARPAN CHS LTD is registered as P51800006250 and its status is "Lapsed (registration period ended)".

What is the construction status of ARPAN CHS LTD?

According to GharKundli's check of MahaRERA records (updated November 2026), ARPAN CHS LTD's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work on ARPAN CHS LTD is 11% done and internal work 80%. GharKundli's full report compares construction progress with the deadline.

Does ARPAN CHS LTD have complaints on MahaRERA?

2 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Is ARPAN CHS LTD safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), ARPAN CHS LTD is registered on MahaRERA as P51800006250, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 54 months since registration and 2 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if ARPAN CHS LTD's possession date changes?

The latest dates are on ARPAN CHS LTD's MahaRERA page (P51800006250). GharKundli's Kundli Watch sends a free WhatsApp update on ARPAN CHS LTD every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does ARPAN CHS LTD have?

According to GharKundli's check of MahaRERA records (updated November 2026), ARPAN CHS LTD has one building filed: ARPAN CHS LTD with 16 floors.

How big is the land of ARPAN CHS LTD?

According to GharKundli's check of MahaRERA records (updated November 2026), ARPAN CHS LTD stands on 397 sq m of land (about 0.1 acres), with 1,073 sq m of sanctioned built-up area.

What is the track record of ARPAN CHS LTD's builder?

According to GharKundli's check of MahaRERA records (updated November 2026), Parshvanath Superstructures (a group of 2 linked companies) has 2 projects on MahaRERA since 2017, this one included. Of the 2 GharKundli has checked: 2 lapsed. 4 complaints on MahaRERA across 2 projects. GharKundli's full report covers the builder's record in detail.

Where can I read reviews of ARPAN CHS LTD?

Google Maps has reviews of ARPAN CHS LTD written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 2 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is ARPAN CHS LTD?

ARPAN CHS LTD by PARSHVANATH SUPERSTRUCTURES PRIVATE LIMITED is in Kandivali W, Mumbai (pincode 400067), near Bandra, Iraniwadi, Malad West, Maharashtra, and is registered on MahaRERA as P51800006250, per GharKundli's check of MahaRERA records. Its boundaries filed there include 7-62 meters vide TPS road.

How many homes are in ARPAN CHS LTD?

According to GharKundli's check of MahaRERA records (updated November 2026), ARPAN CHS LTD has 26 homes in 1 tower registered on MahaRERA.

When was ARPAN CHS LTD registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), ARPAN CHS LTD was registered on MahaRERA on 14 August 2017. GharKundli did not find a title report on the land on file there.

Are there court cases on ARPAN CHS LTD?

No court cases are listed for ARPAN CHS LTD on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).

Who is the builder of ARPAN CHS LTD?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is PARSHVANATH SUPERSTRUCTURES PRIVATE LIMITED.