by PANCH TATVA REALTY · Chembur, MumbaiAlso near Borla- M/W Ward, Fci, T F Deonar

Possession date of TRIDHAATU PRARAMBH: 31 March 2024, moved from 30 June 2021 (33 months later). This is the latest completion date the builder has filed on MahaRERA, and it has already passed. How to check it yourself

Registered on MahaRERA under P51800012185. Status: Lapsed (registration period ended). MahaRERA has issued a regulatory order on this project. 15 complaints are listed against it on MahaRERA.

Source: GharKundli’s check of MahaRERA records, November 2026.

The latest completion date on MahaRERA (March 2024) has passed.

What do you want to know about TRIDHAATU PRARAMBH?

Ask us on WhatsAppNo login needed. A real person replies.

GharKundli’s full report on TRIDHAATU PRARAMBH

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 15 complaints and 1 court case, and how it ended
  • Construction pace against the March 2024 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51800012185
Status
Lapsed (registration period ended)
Builder
PANCH TATVA REALTY
Location
Chembur, Mumbai · 400071
Project type
Residential / Group Housing
Registered on
1 Sep 2017
Completion date at registration
June 2021
Latest completion date
March 2024
Delay so far
33 months
Homes
82
Sold or booked
80%
Towers
1
Complaints on MahaRERA
15
Court cases listed
1
Appeals at the tribunal
3
MahaRERA regulatory orders
1
Title report on file
Not found

Construction progress of TRIDHAATU PRARAMBH, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
TRIDHAATU PRARAMBH100%100%80%90%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on TRIDHAATU PRARAMBH every month.

TRIDHAATU PRARAMBH: buildings, flats and land, as filed on MahaRERA

  • Buildings: TRIDHAATU PRARAMBH (23 floors)
  • Land: 1,817 sq m (about 0.4 acres) · sanctioned built-up 3,474 sq m
  • Boundaries filed include: Sub-Division Road, Gaothan Road
  • Map: the location the builder filed on MahaRERA

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of TRIDHAATU PRARAMBH →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

TRIDHAATU PRARAMBH: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about TRIDHAATU PRARAMBH

What is the possession date of TRIDHAATU PRARAMBH?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for TRIDHAATU PRARAMBH in Chembur, Mumbai is 31 March 2024 — 33 months later than 30 June 2021, the date given at registration. That date has already passed.

Is the builder's possession date different from the MahaRERA date for TRIDHAATU PRARAMBH?

Builders and listing sites often quote an earlier "target" date for handover. The completion date TRIDHAATU PRARAMBH's builder has filed on MahaRERA, the official one, is 31 March 2024, already 33 months later than the 30 June 2021 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

What is the RERA number of TRIDHAATU PRARAMBH?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of TRIDHAATU PRARAMBH in Chembur, Mumbai is P51800012185.

Is TRIDHAATU PRARAMBH registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), TRIDHAATU PRARAMBH is registered as P51800012185 and its status is "Lapsed (registration period ended)".

What is the construction status of TRIDHAATU PRARAMBH?

According to GharKundli's check of MahaRERA records (updated November 2026), TRIDHAATU PRARAMBH's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work on TRIDHAATU PRARAMBH is 100% done and internal work 80%. GharKundli's full report compares construction progress with the deadline.

Does TRIDHAATU PRARAMBH have complaints on MahaRERA?

15 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Is TRIDHAATU PRARAMBH safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), TRIDHAATU PRARAMBH is registered on MahaRERA as P51800012185, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 33 months since registration and 15 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if TRIDHAATU PRARAMBH's possession date changes?

The latest dates are on TRIDHAATU PRARAMBH's MahaRERA page (P51800012185). GharKundli's Kundli Watch sends a free WhatsApp update on TRIDHAATU PRARAMBH every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does TRIDHAATU PRARAMBH have?

According to GharKundli's check of MahaRERA records (updated November 2026), TRIDHAATU PRARAMBH has one building filed: TRIDHAATU PRARAMBH with 23 floors.

How big is the land of TRIDHAATU PRARAMBH?

According to GharKundli's check of MahaRERA records (updated November 2026), TRIDHAATU PRARAMBH stands on 1,817 sq m of land (about 0.4 acres), with 3,474 sq m of sanctioned built-up area.

Where can I read reviews of TRIDHAATU PRARAMBH?

Google Maps has reviews of TRIDHAATU PRARAMBH written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 15 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is TRIDHAATU PRARAMBH?

TRIDHAATU PRARAMBH by PANCH TATVA REALTY is in Chembur, Mumbai (pincode 400071), near Borla- M/W Ward, Fci, T F Deonar, Maharashtra, and is registered on MahaRERA as P51800012185, per GharKundli's check of MahaRERA records. Its boundaries filed there include Sub-Division Road, Gaothan Road.

How many homes are in TRIDHAATU PRARAMBH?

According to GharKundli's check of MahaRERA records (updated November 2026), TRIDHAATU PRARAMBH has 82 homes in 1 tower registered on MahaRERA, and 80% of them are sold or booked.

When was TRIDHAATU PRARAMBH registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), TRIDHAATU PRARAMBH was registered on MahaRERA on 1 September 2017. GharKundli did not find a title report on the land on file there.

Are there court cases on TRIDHAATU PRARAMBH?

1 court case is listed for TRIDHAATU PRARAMBH on MahaRERA, and 3 appeals at the tribunal, per GharKundli's check of MahaRERA records (updated November 2026). GharKundli's full report explains each case and how it ended.

Who is the builder of TRIDHAATU PRARAMBH?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is PANCH TATVA REALTY.

Other projects in pincode 400071