Kedar Mauli Apartments
by M/S. KEDAR DEVELOPERS · Laxmi Nagar, Nagpur, Nagpur 440022Also near Bajaj Nagar, Laxminagar, NeeriRegistered on MahaRERA as “MAULI APARTMENTS”
What’s in the report? →Possession date of Kedar Mauli Apartments (MahaRERA P50500031997): 31 December 2026, moved from 31 December 2024 (24 months later). It has 17 homes, 59% sold or booked. No complaints on MahaRERA. How to check it yourself
Registered on MahaRERA under P50500031997, and currently active.
Source: MahaRERA website — records for P50500031997, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.
What do you want to know about Kedar Mauli Apartments?
Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.
How the possession date of Kedar Mauli Apartments has moved
31 December 2024
Completion date given when the project was registered
31 December 2026
Extended at the builder's request (MahaRERA application EA30092639008)
Reason the builder gave MahaRERA: “OC Is already received and we have uploaded on portal due to correction in Map, so we have to apply for correction thats why we want extention of project.”
Source: Kedar Mauli Apartments’s extension records on MahaRERA (P50500031997), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Kedar Mauli Apartments
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the December 2026 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P50500031997
- Status
- Registered and active
- Builder
- M/S. KEDAR DEVELOPERS
- Location
- Laxmi Nagar, Nagpur, Nagpur · 440022
- Project type
- Residential / Group Housing
- Registered on
- 3 Dec 2021
- Completion date at registration
- December 2024
- Latest completion date
- December 2026
- Delay so far
- 24 months
- Homes
- 17
- Sold or booked
- 59%
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of Kedar Mauli Apartments, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| MAULI APARTMENTS | 100% | 100% | 100% | 100% |
Commencement certificate (CC), as filed on MahaRERA
- MAULI APARTMENTS: covers 8 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Kedar Mauli Apartments every 1–2 months.
Kedar Mauli Apartments: buildings, flats and land, as filed on MahaRERA
- Buildings: MAULI APARTMENTS (8 floors, 17 units)
- Land: 710 sq m (about 0.2 acres) · sanctioned built-up 2,141 sq m
- Land, as filed: CTS NO 361 PLOT NO 1 IN BLOCK Q
- Map: the location the builder filed on MahaRERA · Get directions
The builder’s record and reviews
Kedar Developers has 2 projects on MahaRERA since 2021, this one included. Of the 2 GharKundli has checked: 2 still being built, 1 past the promised date (typically 22 months late). No complaints on MahaRERA.
Read Google reviews of Kedar Mauli Apartments →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Kedar Mauli Apartments: buyers & owners
Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.
Common questions about Kedar Mauli Apartments
What is the possession date of Kedar Mauli Apartments?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for Kedar Mauli Apartments in Laxmi Nagar, Nagpur, Nagpur is 31 December 2026 — 24 months later than 31 December 2024, the date given at registration.
The date has already moved 24 months. Will it move again? Check the real pace of construction →
Is the builder's possession date different from the MahaRERA date for Kedar Mauli Apartments?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Kedar Mauli Apartments's builder has filed on MahaRERA, the official one, is 31 December 2026, already 24 months later than the 31 December 2024 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Kedar Mauli Apartments extended?
According to GharKundli's check of MahaRERA records (updated November 2026), Kedar Mauli Apartments's builder applied to MahaRERA to extend the completion date once: to 31 December 2026, giving the reason "OC Is already received and we have uploaded on portal due to correction in Map, so we have to apply for correction thats why we want extention of project.".
What is the RERA number of Kedar Mauli Apartments?
According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of Kedar Mauli Apartments in Laxmi Nagar, Nagpur, Nagpur is P50500031997.
Is Kedar Mauli Apartments registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), Kedar Mauli Apartments is registered as P50500031997 and its status is "Registered and active".
What is the current construction status of Kedar Mauli Apartments? How much work is done?
According to GharKundli's check of MahaRERA records (updated November 2026), Kedar Mauli Apartments's status on MahaRERA is "Registered and active". As filed by the builder, slab work on MAULI APARTMENTS is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.
Does Kedar Mauli Apartments have complaints on MahaRERA?
No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.
Is Kedar Mauli Apartments safe to buy?
According to GharKundli's check of MahaRERA records (updated November 2026), Kedar Mauli Apartments is registered on MahaRERA as P50500031997, its completion date has moved 24 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How much GST is payable on a flat in Kedar Mauli Apartments?
Kedar Mauli Apartments is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 90 sq m (about 969 sq ft) outside the Mumbai region, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.
What is the stamp duty and registration cost for a flat in Kedar Mauli Apartments?
For a flat in Kedar Mauli Apartments (Nagpur), stamp duty is 7% of the agreement value, or of the ready reckoner value if that's higher, including 1% Transport Surcharge + 1% LBT. A woman buying in her own name pays 6%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹7 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator
Has Kedar Mauli Apartments received its OC? Is it ready to move in?
Not yet. According to GharKundli's check of MahaRERA records (updated November 2026), Kedar Mauli Apartments is still under construction, with 31 December 2026 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.
Has Kedar Mauli Apartments uploaded its title report on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), no title report for Kedar Mauli Apartments was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.
No title report is on MahaRERA for this project. See which documents are missing →
How can I get updates if Kedar Mauli Apartments's possession date changes?
The latest dates are on Kedar Mauli Apartments's MahaRERA page (P50500031997). GharKundli's Kundli Watch sends a free WhatsApp update on Kedar Mauli Apartments every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Kedar Mauli Apartments have?
According to GharKundli's check of MahaRERA records (updated November 2026), Kedar Mauli Apartments has one building filed: MAULI APARTMENTS with 8 floors and 17 units.
How big is the land of Kedar Mauli Apartments?
According to GharKundli's check of MahaRERA records (updated November 2026), Kedar Mauli Apartments stands on 710 sq m of land (about 0.2 acres), with 2,141 sq m of sanctioned built-up area.
What is the track record of Kedar Mauli Apartments's builder?
According to GharKundli's check of MahaRERA records (updated November 2026), Kedar Developers has 2 projects on MahaRERA since 2021, this one included. Of the 2 GharKundli has checked: 2 still being built, 1 past the promised date (typically 22 months late). No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.
What are the reviews of Kedar Mauli Apartments?
Google Maps has reviews of Kedar Mauli Apartments written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
What is the address and pincode of Kedar Mauli Apartments?
Kedar Mauli Apartments by M/S. KEDAR DEVELOPERS is in Laxmi Nagar, Nagpur, Nagpur, pincode 440022 (near Bajaj Nagar, Laxminagar, Neeri), Maharashtra, and is registered on MahaRERA as P50500031997, per GharKundli's check of MahaRERA records. Its land is filed as CTS NO 361 PLOT NO 1 IN BLOCK Q. GharKundli lists all 81 MahaRERA projects in Ranapratap Nagar (440022).
How many flats are in Kedar Mauli Apartments, and how many are sold?
According to GharKundli's check of MahaRERA records (updated November 2026), Kedar Mauli Apartments has 17 homes in 1 tower registered on MahaRERA, and 59% of them are sold or booked.
When was Kedar Mauli Apartments registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), Kedar Mauli Apartments was registered on MahaRERA on 3 December 2021. GharKundli did not find a title report on the land on file there.
Does Kedar Mauli Apartments have any legal issues or court cases?
No court cases are listed for Kedar Mauli Apartments on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).
Who is the builder / developer of Kedar Mauli Apartments?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is M/S. KEDAR DEVELOPERS.
Check it yourself on MahaRERA
- How to check the possession date of Kedar Mauli Apartments
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2026 in Nagpur →
Other projects in Ranapratap Nagar (440022)
- Usha Deepak Thool
- Mahendra Regalia
- Nishigandha
- Construction of 40 Flats under EWS on kh no 13/3 part at mouza bhamti dist nagpur.
- S-13-dev Heights
- Shree Apartments
- Mithila Apartment
- Chanakya Apartment
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.