THE URBAN VILLAGE
by SHRI HOUSING AND INFRASTRUCTURE · Industrial Area Butibori, Nagpur
Possession date of THE URBAN VILLAGE: 30 April 2027. This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P50500034930, and currently active. Its completion date is now April 2027, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time.
Source: GharKundli’s check of MahaRERA records, November 2026.
What do you want to know about THE URBAN VILLAGE?
How the possession date of THE URBAN VILLAGE has moved
31 December 2026
Completion date given when the project was registered
30 April 2027
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: THE URBAN VILLAGE’s extension records on MahaRERA (P50500034930), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on THE URBAN VILLAGE
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the April 2027 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P50500034930
- Status
- Registered and active
- Builder
- SHRI HOUSING AND INFRASTRUCTURE
- Location
- Industrial Area Butibori, Nagpur · 441122
- Project type
- Residential / Group Housing
- Registered on
- 28 Apr 2022
- Completion date at registration
- December 2026
- Latest completion date
- April 2027
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 72
- Sold or booked
- 35%
- Towers
- 14
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of THE URBAN VILLAGE, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| Building No 1 | 0% | 0% | 0% | 0% |
| Building No 2 | 0% | 0% | 0% | 0% |
| Building No 3 | 0% | 0% | 0% | 0% |
| Building No 4 | 0% | 0% | 0% | 0% |
| Building No 5 | 100% | 0% | 0% | 0% |
| Building No 6 | 100% | 30% | 0% | 0% |
| Building No 7 | 100% | 20% | 0% | 0% |
| Building No 8 | 100% | 90% | 40% | 0% |
| Building No 9 | 0% | 0% | 0% | 0% |
| Building No 10 | 0% | 0% | 0% | 0% |
| Building No 11 | 0% | 0% | 0% | 0% |
| Building No 12 | 0% | 0% | 0% | 0% |
| Building No 13 | 0% | 0% | 0% | 0% |
| Building No 14 | 0% | 0% | 0% | 0% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on THE URBAN VILLAGE every month.
THE URBAN VILLAGE: buildings, flats and land, as filed on MahaRERA
- Buildings: Building No 1 (5 floors) · Building No 2 (5 floors) · Building No 3 (5 floors) · Building No 4 (5 floors) · Building No 5 (5 floors) · Building No 6 (5 floors) · Building No 7 (5 floors) · Building No 8 (5 floors) · and 6 more
- Land: 20,025 sq m (about 4.9 acres) · sanctioned built-up 20,025 sq m
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of THE URBAN VILLAGE →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
THE URBAN VILLAGE: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about THE URBAN VILLAGE
What is the possession date of THE URBAN VILLAGE?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for THE URBAN VILLAGE in Industrial Area Butibori, Nagpur is 30 April 2027, including MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for THE URBAN VILLAGE?
Builders and listing sites often quote an earlier "target" date for handover. The completion date THE URBAN VILLAGE's builder has filed on MahaRERA, the official one, is 30 April 2027, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
What is the RERA number of THE URBAN VILLAGE?
According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of THE URBAN VILLAGE in Industrial Area Butibori, Nagpur is P50500034930.
Is THE URBAN VILLAGE registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), THE URBAN VILLAGE is registered as P50500034930 and its status is "Registered and active".
What is the construction status of THE URBAN VILLAGE?
According to GharKundli's check of MahaRERA records (updated November 2026), THE URBAN VILLAGE's status on MahaRERA is "Registered and active". As filed by the builder, slab work ranges from 0% to 90% across 14 towers. GharKundli's full report compares construction progress with the deadline.
Does THE URBAN VILLAGE have complaints on MahaRERA?
No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.
Is THE URBAN VILLAGE safe to buy?
According to GharKundli's check of MahaRERA records (updated November 2026), THE URBAN VILLAGE is registered on MahaRERA as P50500034930, its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if THE URBAN VILLAGE's possession date changes?
The latest dates are on THE URBAN VILLAGE's MahaRERA page (P50500034930). GharKundli's Kundli Watch sends a free WhatsApp update on THE URBAN VILLAGE every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does THE URBAN VILLAGE have?
According to GharKundli's check of MahaRERA records (updated November 2026), THE URBAN VILLAGE has 14 buildings filed: Building No 1 with 5 floors; Building No 2 with 5 floors; Building No 3 with 5 floors; Building No 4 with 5 floors; Building No 5 with 5 floors; Building No 6 with 5 floors; and 8 more.
How big is the land of THE URBAN VILLAGE?
According to GharKundli's check of MahaRERA records (updated November 2026), THE URBAN VILLAGE stands on 20,025 sq m of land (about 4.9 acres), with 20,025 sq m of sanctioned built-up area.
Where can I read reviews of THE URBAN VILLAGE?
Google Maps has reviews of THE URBAN VILLAGE written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is THE URBAN VILLAGE?
THE URBAN VILLAGE by SHRI HOUSING AND INFRASTRUCTURE is in Industrial Area Butibori, Nagpur (pincode 441122), Maharashtra, and is registered on MahaRERA as P50500034930, per GharKundli's check of MahaRERA records.
How many homes are in THE URBAN VILLAGE?
According to GharKundli's check of MahaRERA records (updated November 2026), THE URBAN VILLAGE has 72 homes in 14 towers registered on MahaRERA, and 35% of them are sold or booked.
When was THE URBAN VILLAGE registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), THE URBAN VILLAGE was registered on MahaRERA on 28 April 2022. GharKundli did not find a title report on the land on file there.
Are there court cases on THE URBAN VILLAGE?
No court cases are listed for THE URBAN VILLAGE on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).
Who is the builder of THE URBAN VILLAGE?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is SHRI HOUSING AND INFRASTRUCTURE.
Check it yourself on MahaRERA
- How to check the possession date of THE URBAN VILLAGE
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2027 in Nagpur →
Other projects in pincode 441122
- Final Demarcated Residential Layout on Kh. No. 106, Mouza Kothewada, Tal hingna Nagput
- DIVYANJALI APARTMENTS
- MAULI INFINITY SQUARE 39
- SAMRUDDHI ESTATE-III
- MORESHWAR PARK-15
- ANANDAM 14
- ASHOKA NAGARI-2
- GULMOHAR GREENS - III
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.