MB Town 4 Phase 1

by MAHARANA AND BOSE ASSOCIATES · Near Zingabai Takli, NagpurAlso near Godhani

Possession date of MB Town 4 Phase 1: 30 April 2030, moved from 31 December 2026 (36 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P50500032132, and currently active. Its completion date has moved from December 2026 to April 2030: 36 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects. 1 complaint is listed against it on MahaRERA.

Source: GharKundli’s check of MahaRERA records, October 2026.

What do you want to know about MB Town 4 Phase 1?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of MB Town 4 Phase 1 has moved

  1. 31 December 2026

    Completion date given when the project was registered

  2. 31 December 2029

    Extended at the builder's request (MahaRERA application EA01092622434)

    Reason the builder gave MahaRERA:
    “I, Shri Maharana and Bose Associates, promoter / authorized person of the said project, am writing to formally request an extension for the completion date of our residential development project known as MB TOWN 4 PHASE 1, located at Plot N…” Read the full reason“I, Shri Maharana and Bose Associates, promoter / authorized person of the said project, am writing to formally request an extension for the completion date of our residential development project known as MB TOWN 4 PHASE 1, located at Plot No. 18 and 19, CTS No. 37, Kh. No. 35/5, Mouza – Nagpur, Taluka – Nagpur (Urban), District – Nagpur, total plotable area 2920.82 Sq. Mtrs. I, Shri Maharana and Bose Associates, being the Authorized Signatory/Promoter of the project " MB TOWN 4 PHASE 1", bearing MahaRERA Registration No. P50500015969. We would like to bring to your notice the current ground…”
  3. 30 April 2030

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: MB Town 4 Phase 1’s extension records on MahaRERA (P50500032132), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on MB Town 4 Phase 1

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 1 complaint, and how it ended
  • Construction pace against the April 2030 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P50500032132
Status
Registered and active
Builder
MAHARANA AND BOSE ASSOCIATES
Location
Near Zingabai Takli, Nagpur · 440030
Project type
Others
Registered on
14 Dec 2021
Completion date at registration
December 2026
Latest completion date
April 2030
Delay so far
36 months
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
112
Sold or booked
0%
Towers
2
Complaints on MahaRERA
1
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
1

Construction progress of MB Town 4 Phase 1, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
KAILASH TOWERS - A95%80%20%0%
HIM-SHIKHAR TOWERS95%80%20%0%

Commencement certificate (CC), as filed on MahaRERA

  • KAILASH TOWERS - A: covers 7 floors
  • HIM-SHIKHAR TOWERS: covers 7 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on MB Town 4 Phase 1 every month.

MB Town 4 Phase 1: buildings, flats and land, as filed on MahaRERA

The builder’s record and reviews

Maharana AND Bose Associates has 2 projects on MahaRERA since 2021, this one included. Of the 2 GharKundli has checked: 2 still being built, none past the promised date yet. 1 complaint on MahaRERA across 1 project.

Read Google reviews of MB Town 4 Phase 1 →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

MB Town 4 Phase 1: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about MB Town 4 Phase 1

What is the possession date of MB Town 4 Phase 1?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for MB Town 4 Phase 1 in Near Zingabai Takli, Nagpur is 30 April 2030 — 36 months later than 31 December 2026, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for MB Town 4 Phase 1?

Builders and listing sites often quote an earlier "target" date for handover. The completion date MB Town 4 Phase 1's builder has filed on MahaRERA, the official one, is 30 April 2030, already 36 months later than the 31 December 2026 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of MB Town 4 Phase 1 extended?

According to GharKundli's check of MahaRERA records (updated October 2026), MB Town 4 Phase 1's builder applied to MahaRERA to extend the completion date once: to 31 December 2029, giving the reason "I, Shri Maharana and Bose Associates, promoter / authorized person of the said project, am writing to formally request an extension for the completion date of our residential development project known as MB TOWN 4 PHASE 1, located at Plot No. 18 and 19, CTS No. 37, Kh. No. 35/5, Mouza – Nagpur, Taluka – Nagpur (Urban), District – Nagpur, total plotable area 2920.82 Sq. Mtrs. I, Shri Maharana and Bose Associates, being the Authorized Signatory/Promoter of the project " MB TOWN 4 PHASE 1", bearing MahaRERA Registration No. P50500015969. We would like to bring to your notice the current ground…". MahaRERA also added its automatic 4-month extension for all eligible projects.

What is the RERA number of MB Town 4 Phase 1?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of MB Town 4 Phase 1 in Near Zingabai Takli, Nagpur is P50500032132.

Is MB Town 4 Phase 1 registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), MB Town 4 Phase 1 is registered as P50500032132 and its status is "Registered and active".

What is the construction status of MB Town 4 Phase 1?

According to GharKundli's check of MahaRERA records (updated October 2026), MB Town 4 Phase 1's status on MahaRERA is "Registered and active". As filed by the builder, slab work is 80% done across 2 towers. GharKundli's full report compares construction progress with the deadline.

Does MB Town 4 Phase 1 have complaints on MahaRERA?

1 complaint was listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Is MB Town 4 Phase 1 safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), MB Town 4 Phase 1 is registered on MahaRERA as P50500032132, its completion date has moved 36 months since registration and 1 complaint is listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if MB Town 4 Phase 1's possession date changes?

The latest dates are on MB Town 4 Phase 1's MahaRERA page (P50500032132). GharKundli's Kundli Watch sends a free WhatsApp update on MB Town 4 Phase 1 every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does MB Town 4 Phase 1 have?

According to GharKundli's check of MahaRERA records (updated October 2026), MB Town 4 Phase 1 has 2 buildings filed: KAILASH TOWERS - A with 9 floors and 56 units; HIM-SHIKHAR TOWERS with 9 floors and 56 units.

How big is the land of MB Town 4 Phase 1?

According to GharKundli's check of MahaRERA records (updated October 2026), MB Town 4 Phase 1 stands on 2,921 sq m of land (about 0.7 acres), with 8,022 sq m of sanctioned built-up area.

What is the track record of MB Town 4 Phase 1's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Maharana AND Bose Associates has 2 projects on MahaRERA since 2021, this one included. Of the 2 GharKundli has checked: 2 still being built, none past the promised date yet. 1 complaint on MahaRERA across 1 project. GharKundli's full report covers the builder's record in detail.

Where can I read reviews of MB Town 4 Phase 1?

Google Maps has reviews of MB Town 4 Phase 1 written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 1 complaint is listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is MB Town 4 Phase 1?

MB Town 4 Phase 1 by MAHARANA AND BOSE ASSOCIATES is in Near Zingabai Takli, Nagpur (pincode 440030), near Godhani, Maharashtra, and is registered on MahaRERA as P50500032132, per GharKundli's check of MahaRERA records.

How many homes are in MB Town 4 Phase 1?

According to GharKundli's check of MahaRERA records (updated October 2026), MB Town 4 Phase 1 has 112 homes in 2 towers registered on MahaRERA, and 0% of them are sold or booked.

When was MB Town 4 Phase 1 registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), MB Town 4 Phase 1 was registered on MahaRERA on 14 December 2021. GharKundli did not find a title report on the land on file there.

Are there court cases on MB Town 4 Phase 1?

No court cases are listed for MB Town 4 Phase 1 on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder of MB Town 4 Phase 1?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is MAHARANA AND BOSE ASSOCIATES, which has 1 other project registered on MahaRERA.

All projects with possession due in 2030 in Nagpur →

Other projects in Nagpur (Urban)

All 31 projects in Zingabai Takli (440030) →

Other projects by MAHARANA AND BOSE ASSOCIATES

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.