Skip to content
GharKundli

Maya Atharva

by MAYA DEVELOPERS · Chembur, Mumbai 400071Also near Bhandup West, Tilak Nagar, PanvelRegistered on MahaRERA as “ATHARVA”

What’s in the report? →

Possession date of Maya Atharva (MahaRERA P51800005146): 31 July 2027, moved from 30 September 2020 (78 months later). It has 40 homes (2 BHK, 623–693 sq ft carpet), 79% sold or booked. No complaints on MahaRERA. How to check it yourself

Registered on MahaRERA under P51800005146, and currently active. Its completion date has moved from September 2020 to July 2027: 78 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.

Source: MahaRERA website — records for P51800005146, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

What do you want to know about Maya Atharva?

Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

How the possession date of Maya Atharva has moved

  1. 30 September 2020

    Completion date given when the project was registered

  2. 30 September 2021

    Extended at the builder's request (MahaRERA application EXT51800006350)

    Reason the builder gave MahaRERA: “Change in policy by MHADA and COVID-19 Pandemic, We need an extension upto 31st December 2021”
  3. 31 December 2023

    Extended at the builder's request (MahaRERA application EXT51800011677)

    Reason the builder gave MahaRERA: “Due to COVID-19 pandemic, the regular flow of work is hampered on account of unavailability of labor on regular basis”
  4. 31 December 2025

    Extended at the builder's request (MahaRERA application EXT51800023037)

    Reason the builder gave MahaRERA: “We are in the process of obtaining a revised commencement certificate in accordance with the provisions of the RERA act and Rules & project is yet to complete.”
  5. 31 March 2027

    Extended at the builder's request (MahaRERA application EA29012619630)

    Reason the builder gave MahaRERA:
    “1) As the entire country including Mumbai Suburban were under a total lock-down; and the Government of India as well as the Government of Maharashtra had announced a slew of measures including “work from home” and “social distancing” to cur…” Read the full reason“1) As the entire country including Mumbai Suburban were under a total lock-down; and the Government of India as well as the Government of Maharashtra had announced a slew of measures including “work from home” and “social distancing” to curb the spread of the COVID-19. 2) Inspite of best efforts, the said project was adversely affected due to unprecedented COVID-19 Pandemic which lasted for more than 2 years and are still facing aftermath of COVID Pandemic. 3) Initially, the project was sanctioned for Ground + Stilt + 7 Floors. Subsequently, the competent authority approved an amended plan…”
  6. 31 July 2027

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: Maya Atharva’s extension records on MahaRERA (P51800005146), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Maya Atharva

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the July 2027 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51800005146
Status
Registered and active
Builder
MAYA DEVELOPERS
Location
Chembur, Mumbai · 400071
Project type
Others
Registered on
9 Aug 2017
Completion date at registration
September 2020
Latest completion date
July 2027
Delay so far
78 months
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
40
Sold or booked
79%
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
1

Construction progress of Maya Atharva, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
ATHARVA100%85%70%70%

Commencement certificate (CC), as filed on MahaRERA

  • ATHARVA: covers 11 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Maya Atharva every 1–2 months.

Maya Atharva: buildings, flats and land, as filed on MahaRERA

TypeCarpet area (sq ft)Units
2 BHK623 – 69340
Shops180 – 3586

The builder’s record and reviews

Maya Developers has 2 projects on MahaRERA since 2017, this one included. Of the 2 GharKundli has checked: 1 finished, 0 within the promised date and 1 needed more time (typically 34 months); 1 still being built, 1 past the promised date (typically 63 months late). No complaints on MahaRERA.

Read Google reviews of Maya Atharva →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Maya Atharva: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about Maya Atharva

What is the possession date of Maya Atharva?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Maya Atharva in Chembur, Mumbai is 31 July 2027 — 78 months later than 30 September 2020, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.

The date has already moved 78 months. Will it move again? Check the real pace of construction →

Is the builder's possession date different from the MahaRERA date for Maya Atharva?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Maya Atharva's builder has filed on MahaRERA, the official one, is 31 July 2027, already 78 months later than the 30 September 2020 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Maya Atharva extended?

According to GharKundli's check of MahaRERA records (updated October 2026), Maya Atharva's builder applied to MahaRERA to extend the completion date 4 times: to 30 September 2021, giving the reason "Change in policy by MHADA and COVID-19 Pandemic, We need an extension upto 31st December 2021"; to 31 December 2023, giving the reason "Due to COVID-19 pandemic, the regular flow of work is hampered on account of unavailability of labor on regular basis"; to 31 December 2025, giving the reason "We are in the process of obtaining a revised commencement certificate in accordance with the provisions of the RERA act and Rules & project is yet to complete."; to 31 March 2027, giving the reason "1) As the entire country including Mumbai Suburban were under a total lock-down; and the Government of India as well as the Government of Maharashtra had announced a slew of measures including “work from home” and “social distancing” to curb the spread of the COVID-19. 2) Inspite of best efforts, the said project was adversely affected due to unprecedented COVID-19 Pandemic which lasted for more than 2 years and are still facing aftermath of COVID Pandemic. 3) Initially, the project was sanctioned for Ground + Stilt + 7 Floors. Subsequently, the competent authority approved an amended plan…". MahaRERA also added its automatic 4-month extension for all eligible projects.

What is the RERA number of Maya Atharva?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Maya Atharva in Chembur, Mumbai is P51800005146.

Is Maya Atharva registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Maya Atharva is registered as P51800005146 and its status is "Registered and active".

What is the current construction status of Maya Atharva? How much work is done?

According to GharKundli's check of MahaRERA records (updated October 2026), Maya Atharva's status on MahaRERA is "Registered and active". As filed by the builder, slab work on ATHARVA is 85% done and internal work 70%. GharKundli's full report compares construction progress with the deadline.

Does Maya Atharva have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is Maya Atharva safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Maya Atharva is registered on MahaRERA as P51800005146, its completion date has moved 78 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in Maya Atharva?

Maya Atharva is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) in the Mumbai region, and price up to ₹45 lakh. Some flats in Maya Atharva are 623 sq ft carpet, small enough for 1% if the price is ₹45 lakh or less. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.

What is the stamp duty and registration cost for a flat in Maya Atharva?

For a flat in Maya Atharva (Mumbai), stamp duty is 6% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess. A woman buying in her own name pays 5%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹6 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator

Has Maya Atharva received its OC? Is it ready to move in?

Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Maya Atharva is still under construction, with 31 July 2027 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.

Is Maya Atharva a redevelopment or SRA project?

According to GharKundli's check of MahaRERA records (updated October 2026), Maya Atharva is a redevelopment: 12 of its flats are set aside for existing occupants (rehab), and the rest are for sale.

Has Maya Atharva uploaded its title report on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Maya Atharva was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.

No title report is on MahaRERA for this project. See which documents are missing →

How can I get updates if Maya Atharva's possession date changes?

The latest dates are on Maya Atharva's MahaRERA page (P51800005146). GharKundli's Kundli Watch sends a free WhatsApp update on Maya Atharva every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Maya Atharva have?

According to GharKundli's check of MahaRERA records (updated October 2026), Maya Atharva has one building filed: ATHARVA with 13 floors and 46 units.

What are the flat sizes (carpet area) in Maya Atharva?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for Maya Atharva: 2 BHK: 623 to 693 sq ft carpet (40 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.

How much parking does Maya Atharva have?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 7 covered and 12 open car parking spaces for Maya Atharva.

How big is the land of Maya Atharva?

According to GharKundli's check of MahaRERA records (updated October 2026), Maya Atharva stands on 913 sq m of land (about 0.2 acres), with 2,282 sq m of sanctioned built-up area.

What is the track record of Maya Atharva's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Maya Developers has 2 projects on MahaRERA since 2017, this one included. Of the 2 GharKundli has checked: 1 finished, 0 within the promised date and 1 needed more time (typically 34 months); 1 still being built, 1 past the promised date (typically 63 months late). No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.

What are the reviews of Maya Atharva?

Google Maps has reviews of Maya Atharva written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of Maya Atharva?

Maya Atharva by MAYA DEVELOPERS is in Chembur, Mumbai, pincode 400071 (near Bhandup West, Tilak Nagar, Panvel), Maharashtra, and is registered on MahaRERA as P51800005146, per GharKundli's check of MahaRERA records. GharKundli lists all 318 MahaRERA projects in Chembur (400071).

How many flats are in Maya Atharva, and how many are sold?

According to GharKundli's check of MahaRERA records (updated October 2026), Maya Atharva has 40 homes in 1 tower registered on MahaRERA, and 79% of them are sold or booked.

When was Maya Atharva registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Maya Atharva was registered on MahaRERA on 9 August 2017. GharKundli did not find a title report on the land on file there.

Does Maya Atharva have any legal issues or court cases?

No court cases are listed for Maya Atharva on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder / developer of Maya Atharva?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is MAYA DEVELOPERS, which has 1 other project registered on MahaRERA.

All projects with possession due in 2027 in Mumbai Suburban →

Other projects in Chembur (400071)

All 318 projects in Chembur (400071) →

Other projects by MAYA DEVELOPERS

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.