Nirmal Priti CHS LTD
by TRIDEVH CONSTRUCTION COMPANY · Mulund West, Mumbai 400080Also near Bhandup West, Sion, Off Dmart
What’s in the report? →Possession date of Nirmal Priti CHS LTD (MahaRERA P51800002769): 31 December 2025, moved from 30 December 2021 (48 months later), and it has already passed. It has 13 homes (2 BHK, 3 BHK and 4 BHK, 559–1485 sq ft carpet), 100% sold or booked. No complaints on MahaRERA. How to check it yourself
Registered on MahaRERA under P51800002769. Status: Lapsed (registration period ended).
Source: MahaRERA website — records for P51800002769, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.
The latest completion date on MahaRERA (December 2025) has passed.
What do you want to know about Nirmal Priti CHS LTD?
Completion date nikal chuki hai. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.
How the possession date of Nirmal Priti CHS LTD has moved
30 December 2021
Completion date given when the project was registered
30 June 2024
Extended at the builder's request (MahaRERA application EXT51800017152)
Reason the builder gave MahaRERA:
“Construction work of the building is completed in full and the same is evident from the Architect Certificate (Form 1) and Engineer Certificate (Form 2). The applicant has already made an application for Occupation Certificate (OC) and is i…” Read the full reason
“Construction work of the building is completed in full and the same is evident from the Architect Certificate (Form 1) and Engineer Certificate (Form 2). The applicant has already made an application for Occupation Certificate (OC) and is in the process of obtaining Occupation Certificate (OC) from MCGM. Registration in respect of one unit is yet to be executed and in light of the same applicant seek extension.”31 December 2025
Extended at the builder's request (MahaRERA application EXT51800028144)
Reason the builder gave MahaRERA:
“More than 95% of the building work is completed as evidenced by the latest Architect Certificate dated 24-12-2024. Further for completing the OC related compliances we seek extension of the said project completion date up-to 31-12-2025. Jus…” Read the full reason
“More than 95% of the building work is completed as evidenced by the latest Architect Certificate dated 24-12-2024. Further for completing the OC related compliances we seek extension of the said project completion date up-to 31-12-2025. Justification as to why project is delayed and details of balance work completion within extended time period is enclosed. Scan copy of original Notarized Affidavit cum declaration on Rs. 500/- stamp paper; in Form B with extension date is attached on the document section. Recent Sold/Booked inventory is also updated. All the forms, booked units, Task and ac…”
Source: Nirmal Priti CHS LTD’s extension records on MahaRERA (P51800002769), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Nirmal Priti CHS LTD
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the December 2025 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51800002769
- Status
- Lapsed (registration period ended)
- Builder
- TRIDEVH CONSTRUCTION COMPANY
- Location
- Mulund West, Mumbai · 400080
- Project type
- Others
- Registered on
- 4 Aug 2017
- Completion date at registration
- December 2021
- Latest completion date
- December 2025
- Delay so far
- 48 months
- Homes
- 13
- Sold or booked
- 100%
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 1
Construction progress of Nirmal Priti CHS LTD, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| NIRMAL PRITI CHS LTD | 100% | 100% | 100% | 97% |
Commencement certificate (CC), as filed on MahaRERA
- NIRMAL PRITI CHS LTD: covers 7 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Nirmal Priti CHS LTD every 1–2 months.
Nirmal Priti CHS LTD: buildings, flats and land, as filed on MahaRERA
| Type | Carpet area (sq ft) | Units |
|---|---|---|
| 2 BHK | 559 – 778 | 7 |
| 3 BHK | 701 – 900 | 5 |
| 4 BHK | 1,485 | 1 |
- Buildings: NIRMAL PRITI CHS LTD (9 floors, 13 units)
- Car parking: 11 covered, 1 open
- Land: 400 sq m (about 0.1 acres) · sanctioned built-up 497 sq m
- Boundaries filed include: BPS CROSS ROAD NO 4, BPS CROSS ROAD NO 5
- Land, as filed: 1089
- Map: the location the builder filed on MahaRERA · Get directions
The builder’s record and reviews
Tridevh Construction has 2 projects on MahaRERA since 2017, this one included. Of the 2 GharKundli has checked: 1 still being built, 1 past the promised date (typically 18 months late); 1 lapsed. 5 complaints on MahaRERA across 1 project.
Read Google reviews of Nirmal Priti CHS LTD →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Nirmal Priti CHS LTD: buyers & owners
Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.
Common questions about Nirmal Priti CHS LTD
What is the possession date of Nirmal Priti CHS LTD?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Nirmal Priti CHS LTD in Mulund West, Mumbai is 31 December 2025 — 48 months later than 30 December 2021, the date given at registration. That date has already passed.
The date has already moved 48 months. Will it move again? Check the real pace of construction →
Is the builder's possession date different from the MahaRERA date for Nirmal Priti CHS LTD?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Nirmal Priti CHS LTD's builder has filed on MahaRERA, the official one, is 31 December 2025, already 48 months later than the 30 December 2021 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Nirmal Priti CHS LTD extended?
According to GharKundli's check of MahaRERA records (updated October 2026), Nirmal Priti CHS LTD's builder applied to MahaRERA to extend the completion date 2 times: to 30 June 2024, giving the reason "Construction work of the building is completed in full and the same is evident from the Architect Certificate (Form 1) and Engineer Certificate (Form 2). The applicant has already made an application for Occupation Certificate (OC) and is in the process of obtaining Occupation Certificate (OC) from MCGM. Registration in respect of one unit is yet to be executed and in light of the same applicant seek extension."; to 31 December 2025, giving the reason "More than 95% of the building work is completed as evidenced by the latest Architect Certificate dated 24-12-2024. Further for completing the OC related compliances we seek extension of the said project completion date up-to 31-12-2025. Justification as to why project is delayed and details of balance work completion within extended time period is enclosed. Scan copy of original Notarized Affidavit cum declaration on Rs. 500/- stamp paper; in Form B with extension date is attached on the document section. Recent Sold/Booked inventory is also updated. All the forms, booked units, Task and ac…".
What is the RERA number of Nirmal Priti CHS LTD?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Nirmal Priti CHS LTD in Mulund West, Mumbai is P51800002769.
Is Nirmal Priti CHS LTD registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Nirmal Priti CHS LTD is registered as P51800002769 and its status is "Lapsed (registration period ended)".
What is the current construction status of Nirmal Priti CHS LTD? How much work is done?
According to GharKundli's check of MahaRERA records (updated October 2026), Nirmal Priti CHS LTD's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work on NIRMAL PRITI CHS LTD is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.
Does Nirmal Priti CHS LTD have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is Nirmal Priti CHS LTD safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Nirmal Priti CHS LTD is registered on MahaRERA as P51800002769, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 48 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How much GST is payable on a flat in Nirmal Priti CHS LTD?
Nirmal Priti CHS LTD isn't marked completed on MahaRERA, so until the occupancy certificate is issued GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) in the Mumbai region, and price up to ₹45 lakh. Some flats in Nirmal Priti CHS LTD are 559 sq ft carpet, small enough for 1% if the price is ₹45 lakh or less. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.
What is the stamp duty and registration cost for a flat in Nirmal Priti CHS LTD?
For a flat in Nirmal Priti CHS LTD (Mumbai), stamp duty is 6% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess. A woman buying in her own name pays 5%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹6 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator
Has Nirmal Priti CHS LTD received its OC? Is it ready to move in?
Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Nirmal Priti CHS LTD isn't completed: its MahaRERA status is "Lapsed (registration period ended)", with 31 December 2025 as the latest completion date filed on MahaRERA, and that date has passed. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.
What does "lapsed" mean for Nirmal Priti CHS LTD?
According to GharKundli's check of MahaRERA records (updated October 2026), Nirmal Priti CHS LTD's registration shows as lapsed on MahaRERA. Lapsed means the completion date on MahaRERA (31 December 2025) passed without the project being marked complete or the registration being extended. Before paying anything, ask the builder in writing whether an extension has been applied for.
Has Nirmal Priti CHS LTD uploaded its title report on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Nirmal Priti CHS LTD was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.
No title report is on MahaRERA for this project. See which documents are missing →
How can I get updates if Nirmal Priti CHS LTD's possession date changes?
The latest dates are on Nirmal Priti CHS LTD's MahaRERA page (P51800002769). GharKundli's Kundli Watch sends a free WhatsApp update on Nirmal Priti CHS LTD every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Nirmal Priti CHS LTD have?
According to GharKundli's check of MahaRERA records (updated October 2026), Nirmal Priti CHS LTD has one building filed: NIRMAL PRITI CHS LTD with 9 floors and 13 units.
What are the flat sizes (carpet area) in Nirmal Priti CHS LTD?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for Nirmal Priti CHS LTD: 2 BHK: 559 to 778 sq ft carpet (7 homes); 3 BHK: 701 to 900 sq ft carpet (5 homes); 4 BHK: 1485 sq ft carpet (1 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.
How much parking does Nirmal Priti CHS LTD have?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 11 covered and 1 open car parking spaces for Nirmal Priti CHS LTD.
How big is the land of Nirmal Priti CHS LTD?
According to GharKundli's check of MahaRERA records (updated October 2026), Nirmal Priti CHS LTD stands on 400 sq m of land (about 0.1 acres), with 497 sq m of sanctioned built-up area.
What is the track record of Nirmal Priti CHS LTD's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Tridevh Construction has 2 projects on MahaRERA since 2017, this one included. Of the 2 GharKundli has checked: 1 still being built, 1 past the promised date (typically 18 months late); 1 lapsed. 5 complaints on MahaRERA across 1 project. GharKundli's full report covers the builder's record in detail.
What are the reviews of Nirmal Priti CHS LTD?
Google Maps has reviews of Nirmal Priti CHS LTD written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
What is the address and pincode of Nirmal Priti CHS LTD?
Nirmal Priti CHS LTD by TRIDEVH CONSTRUCTION COMPANY is in Mulund West, Mumbai, pincode 400080 (near Bhandup West, Sion, Off Dmart), Maharashtra, and is registered on MahaRERA as P51800002769, per GharKundli's check of MahaRERA records. Its boundaries filed there include BPS CROSS ROAD NO 4, BPS CROSS ROAD NO 5. Its land is filed as 1089. GharKundli lists all 303 MahaRERA projects in Mulund West (400080).
How many flats are in Nirmal Priti CHS LTD, and how many are sold?
According to GharKundli's check of MahaRERA records (updated October 2026), Nirmal Priti CHS LTD has 13 homes in 1 tower registered on MahaRERA, and 100% of them are sold or booked.
When was Nirmal Priti CHS LTD registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Nirmal Priti CHS LTD was registered on MahaRERA on 4 August 2017. GharKundli did not find a title report on the land on file there.
Does Nirmal Priti CHS LTD have any legal issues or court cases?
No court cases are listed for Nirmal Priti CHS LTD on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder / developer of Nirmal Priti CHS LTD?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is TRIDEVH CONSTRUCTION COMPANY, which has 1 other project registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of Nirmal Priti CHS LTD
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in Mulund West (400080)
- Malhar Guide
- Arihant Royale
- The Sanctuary - Tower 5
- Keshavpada
- Dhanraj Tower
- Old Hemant Villa Co. Op. Housing Soc. LTD.
- Madhuvan Nivanta
- Shraddha Paradise Enclave
Other projects by TRIDEVH CONSTRUCTION COMPANY
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.