SAFAL TRADEMARK
by JAI MATA DI HOME CONSTRUCTION PVT LTD · Chembur, MumbaiAlso near Bhandup West, Fort, Kurla
Possession date of SAFAL TRADEMARK: 30 April 2027, moved from 30 December 2023 (36 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51800003754, and currently active. Its completion date has moved from December 2023 to April 2027: 36 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects. 30 complaints are listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about SAFAL TRADEMARK?
How the possession date of SAFAL TRADEMARK has moved
30 December 2023
Completion date given when the project was registered
31 August 2024
Extended at the builder's request (MahaRERA application EXT51800018372)
Reason the builder gave MahaRERA:
“THE LOCKDOWNS LED TO CONSTRUCTION ACTIVITIES COMING TO A STANDSTILL DUE TO NON-AVAILABILITY OF LABOUR AND IMPACT ON THE MOVEMENT OF BUILDING MATERIAL. COVID-19 OUT BREAK DELAYED PROJECT COMPLETION TIMELINES, SALES ARE BADLY AFFECTED, EVEN W…” Read the full reason
“THE LOCKDOWNS LED TO CONSTRUCTION ACTIVITIES COMING TO A STANDSTILL DUE TO NON-AVAILABILITY OF LABOUR AND IMPACT ON THE MOVEMENT OF BUILDING MATERIAL. COVID-19 OUT BREAK DELAYED PROJECT COMPLETION TIMELINES, SALES ARE BADLY AFFECTED, EVEN WE ARE UNABLE TO RECOVER FUNDS EXISTING BUYERS AS FINANCIAL CRISIS ARE FACED BY ALMOST EVERYONE DUE TO FUND ISSUE, NOW WE HAVE TAKEN CONSTRUCTION FINANCE, CONSTRUCTION WORK IS IN PROGRESS.”31 March 2025
Extended at the builder's request (MahaRERA application EXT51800024702)
Reason the builder gave MahaRERA: “DUE TO FINANCIAL CONSTRAINTS FACED CONSTRUCTION WORK IS NOT COMPLETED THEREFORE REQUIRE EXTENSION UPTO 31ST MARCH 2025.”
31 December 2025
Extended at the builder's request (MahaRERA application EXT51800028240)
Reason the builder gave MahaRERA:
“DUE TO UNRESOLVED FINANCIAL CONSTRAINTS FACED , CONSTRUCTION WORK OF THE BUILDINGS ARE NOT COMPLETED . THEREFORE, WE REQUIRE ADDTIONAL TIME I.E EXTENSION UPTO 31ST DECEMBER 2025 TO COMPLETE THE CONSTRUCTION OF PROJECT. WE ARE COMMITTED TO R…” Read the full reason
“DUE TO UNRESOLVED FINANCIAL CONSTRAINTS FACED , CONSTRUCTION WORK OF THE BUILDINGS ARE NOT COMPLETED . THEREFORE, WE REQUIRE ADDTIONAL TIME I.E EXTENSION UPTO 31ST DECEMBER 2025 TO COMPLETE THE CONSTRUCTION OF PROJECT. WE ARE COMMITTED TO RESOLVE THE FINANCIAL MATTERS AT THE EARLIEST AND ENSURE TIMELY COMPLETION OF PROJECT.”31 May 2026
Extended at the builder's request (MahaRERA application EA17022619878)
Reason the builder gave MahaRERA:
“Due to financial constraints faced by us, the progress of the project was temporarily affected. We wish to inform you that all financial issues have now been resolved, and construction work has recommenced in full swing with adequate resour…” Read the full reason
“Due to financial constraints faced by us, the progress of the project was temporarily affected. We wish to inform you that all financial issues have now been resolved, and construction work has recommenced in full swing with adequate resources deployed at site. We assure you that the interests of the allottees / customers are fully secured, and the project shall be completed within the extended period.”31 December 2026
Extended at the builder's request (MahaRERA application EA05082622028)
Reason the builder gave MahaRERA:
“1. The structural construction of the project is fully completed. However, additional time of approximately7 (Seven Months) months is required to complete the remaining finishing works, Car Parking, testing, common area development, and rec…” Read the full reason
“1. The structural construction of the project is fully completed. However, additional time of approximately7 (Seven Months) months is required to complete the remaining finishing works, Car Parking, testing, common area development, and rectification of minor pending items and statutory inspections, compliance procedures, and obtaining the Occupancy Certificate from the competent authority. Please Grant extension upto 31st December 2026”30 April 2027
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: SAFAL TRADEMARK’s extension records on MahaRERA (P51800003754), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on SAFAL TRADEMARK
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 30 complaints, and how it ended
- Construction pace against the April 2027 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51800003754
- Status
- Registered and active
- Builder
- JAI MATA DI HOME CONSTRUCTION PVT LTD
- Location
- Chembur, Mumbai · 400071
- Project type
- Residential / Group Housing
- Registered on
- 6 Aug 2017
- Completion date at registration
- December 2023
- Latest completion date
- April 2027
- Delay so far
- 36 months
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 252
- Sold or booked
- 92%
- Towers
- 1
- Complaints on MahaRERA
- 30
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 1
Construction progress of SAFAL TRADEMARK, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| SAFAL TRADEMARK TOWER 1,2,3 4 WAMANDEV | 100% | 100% | 95% | 75% |
Commencement certificate (CC), as filed on MahaRERA
- SAFAL TRADEMARK TOWER 1,2,3 4 WAMANDEV: covers 19 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on SAFAL TRADEMARK every month.
SAFAL TRADEMARK: buildings, flats and land, as filed on MahaRERA
| Type | Carpet area (sq ft) | Units |
|---|---|---|
| 2 BHK | 635 – 782 | 165 |
| 3 BHK | 907 – 1,094 | 65 |
| 1 BHK | 352 – 360 | 21 |
| 4 BHK | 1,511 | 1 |
- Buildings: SAFAL TRADEMARK TOWER 1,2,3 4 WAMANDEV (19 floors, 252 units)
- Land: 4,411 sq m (about 1.1 acres) · sanctioned built-up 18,610 sq m · recreational space 756 sq m
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
Nav Durga Construction (a group of 4 linked companies) has 9 projects on MahaRERA since 2017, this one included. Of the 9 GharKundli has checked: 2 finished, 1 within the promised date and 1 needed more time (typically 3 months); 6 still being built, 6 past the promised date (typically 18 months late); 1 lapsed. 59 complaints on MahaRERA across 6 projects.
Read Google reviews of SAFAL TRADEMARK →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
SAFAL TRADEMARK: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about SAFAL TRADEMARK
What is the possession date of SAFAL TRADEMARK?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for SAFAL TRADEMARK in Chembur, Mumbai is 30 April 2027 — 36 months later than 30 December 2023, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for SAFAL TRADEMARK?
Builders and listing sites often quote an earlier "target" date for handover. The completion date SAFAL TRADEMARK's builder has filed on MahaRERA, the official one, is 30 April 2027, already 36 months later than the 30 December 2023 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of SAFAL TRADEMARK extended?
According to GharKundli's check of MahaRERA records (updated October 2026), SAFAL TRADEMARK's builder applied to MahaRERA to extend the completion date 5 times: to 31 August 2024, giving the reason "THE LOCKDOWNS LED TO CONSTRUCTION ACTIVITIES COMING TO A STANDSTILL DUE TO NON-AVAILABILITY OF LABOUR AND IMPACT ON THE MOVEMENT OF BUILDING MATERIAL. COVID-19 OUT BREAK DELAYED PROJECT COMPLETION TIMELINES, SALES ARE BADLY AFFECTED, EVEN WE ARE UNABLE TO RECOVER FUNDS EXISTING BUYERS AS FINANCIAL CRISIS ARE FACED BY ALMOST EVERYONE DUE TO FUND ISSUE, NOW WE HAVE TAKEN CONSTRUCTION FINANCE, CONSTRUCTION WORK IS IN PROGRESS."; to 31 March 2025, giving the reason "DUE TO FINANCIAL CONSTRAINTS FACED CONSTRUCTION WORK IS NOT COMPLETED THEREFORE REQUIRE EXTENSION UPTO 31ST MARCH 2025."; to 31 December 2025, giving the reason "DUE TO UNRESOLVED FINANCIAL CONSTRAINTS FACED , CONSTRUCTION WORK OF THE BUILDINGS ARE NOT COMPLETED . THEREFORE, WE REQUIRE ADDTIONAL TIME I.E EXTENSION UPTO 31ST DECEMBER 2025 TO COMPLETE THE CONSTRUCTION OF PROJECT. WE ARE COMMITTED TO RESOLVE THE FINANCIAL MATTERS AT THE EARLIEST AND ENSURE TIMELY COMPLETION OF PROJECT."; to 31 May 2026, giving the reason "Due to financial constraints faced by us, the progress of the project was temporarily affected. We wish to inform you that all financial issues have now been resolved, and construction work has recommenced in full swing with adequate resources deployed at site. We assure you that the interests of the allottees / customers are fully secured, and the project shall be completed within the extended period."; to 31 December 2026, giving the reason "1. The structural construction of the project is fully completed. However, additional time of approximately7 (Seven Months) months is required to complete the remaining finishing works, Car Parking, testing, common area development, and rectification of minor pending items and statutory inspections, compliance procedures, and obtaining the Occupancy Certificate from the competent authority. Please Grant extension upto 31st December 2026". MahaRERA also added its automatic 4-month extension for all eligible projects.
What is the RERA number of SAFAL TRADEMARK?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of SAFAL TRADEMARK in Chembur, Mumbai is P51800003754.
Is SAFAL TRADEMARK registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), SAFAL TRADEMARK is registered as P51800003754 and its status is "Registered and active".
What is the construction status of SAFAL TRADEMARK?
According to GharKundli's check of MahaRERA records (updated October 2026), SAFAL TRADEMARK's status on MahaRERA is "Registered and active". As filed by the builder, slab work on SAFAL TRADEMARK TOWER 1,2,3 4 WAMANDEV is 100% done and internal work 95%. GharKundli's full report compares construction progress with the deadline.
Does SAFAL TRADEMARK have complaints on MahaRERA?
30 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is SAFAL TRADEMARK safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), SAFAL TRADEMARK is registered on MahaRERA as P51800003754, its completion date has moved 36 months since registration and 30 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if SAFAL TRADEMARK's possession date changes?
The latest dates are on SAFAL TRADEMARK's MahaRERA page (P51800003754). GharKundli's Kundli Watch sends a free WhatsApp update on SAFAL TRADEMARK every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does SAFAL TRADEMARK have?
According to GharKundli's check of MahaRERA records (updated October 2026), SAFAL TRADEMARK has one building filed: SAFAL TRADEMARK TOWER 1,2,3 4 WAMANDEV with 19 floors and 252 units.
What are the flat sizes (carpet area) in SAFAL TRADEMARK?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for SAFAL TRADEMARK: 2 BHK: 635 to 782 sq ft carpet (165 homes); 3 BHK: 907 to 1094 sq ft carpet (65 homes); 1 BHK: 352 to 360 sq ft carpet (21 homes); 4 BHK: 1511 sq ft carpet (1 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.
How big is the land of SAFAL TRADEMARK?
According to GharKundli's check of MahaRERA records (updated October 2026), SAFAL TRADEMARK stands on 4,411 sq m of land (about 1.1 acres), with 18,610 sq m of sanctioned built-up area and 756 sq m of recreational open space.
What is the track record of SAFAL TRADEMARK's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Nav Durga Construction (a group of 4 linked companies) has 9 projects on MahaRERA since 2017, this one included. Of the 9 GharKundli has checked: 2 finished, 1 within the promised date and 1 needed more time (typically 3 months); 6 still being built, 6 past the promised date (typically 18 months late); 1 lapsed. 59 complaints on MahaRERA across 6 projects. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of SAFAL TRADEMARK?
Google Maps has reviews of SAFAL TRADEMARK written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 30 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is SAFAL TRADEMARK?
SAFAL TRADEMARK by JAI MATA DI HOME CONSTRUCTION PVT LTD is in Chembur, Mumbai (pincode 400071), near Bhandup West, Fort, Kurla, Maharashtra, and is registered on MahaRERA as P51800003754, per GharKundli's check of MahaRERA records.
How many homes are in SAFAL TRADEMARK?
According to GharKundli's check of MahaRERA records (updated October 2026), SAFAL TRADEMARK has 252 homes in 1 tower registered on MahaRERA, and 92% of them are sold or booked.
When was SAFAL TRADEMARK registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), SAFAL TRADEMARK was registered on MahaRERA on 6 August 2017. GharKundli did not find a title report on the land on file there.
Are there court cases on SAFAL TRADEMARK?
No court cases are listed for SAFAL TRADEMARK on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder of SAFAL TRADEMARK?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is JAI MATA DI HOME CONSTRUCTION PVT LTD, which has 1 other project registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of SAFAL TRADEMARK
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2027 in Mumbai Suburban →
Other projects in pincode 400071
- SHREE SARASWATI CHS LTD PLOT 8B
- TULSI CHAMBER PHASE II
- SAMPOORNA
- QUEENS PARK
- ARHAM MOURYA
- 71 Pardis
- ICONS 71
- Viera Golf Greens
Other projects by JAI MATA DI HOME CONSTRUCTION PVT LTD
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.