by Techops Infrastructure Pvt. Ltd. · Dighori, NagpurAlso near Mhalginagar

Possession date of TECHOPS ROYAL: 7 February 2027, moved from 14 February 2026 (12 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P50500051236, and currently active.

Source: GharKundli’s check of MahaRERA records, October 2026.

What do you want to know about TECHOPS ROYAL?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of TECHOPS ROYAL has moved

  1. 14 February 2026

    Completion date given when the project was registered

  2. 7 February 2027

    Extended at the builder's request (MahaRERA application EA17122518717)

    Reason the builder gave MahaRERA:
    “To The Maharashtra Real Estate Regulatory Authority (MahaRERA) Subject: Explanation for Delay and Request for Extension under Section 7(3) Respected Sir/Madam, We would like to submit this explanation regarding the delay in completion of ou…” Read the full reason“To The Maharashtra Real Estate Regulatory Authority (MahaRERA) Subject: Explanation for Delay and Request for Extension under Section 7(3) Respected Sir/Madam, We would like to submit this explanation regarding the delay in completion of our project registered under MahaRERA, which is due to expire on 14th February 2026. The delay has occurred solely due to unforeseen natural calamities that were entirely beyond our control, and we therefore request an extension under Section 7(3) of the Real Estate (Regulation and Development) Act, 2016. The city of Nagpur, where our project is located, ex…”

Source: TECHOPS ROYAL’s extension records on MahaRERA (P50500051236), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on TECHOPS ROYAL

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the February 2027 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P50500051236
Status
Registered and active
Builder
Techops Infrastructure Pvt. Ltd.
Location
Dighori, Nagpur · 440034
Project type
Others
Registered on
8 Jun 2023
Completion date at registration
February 2026
Latest completion date
February 2027
Delay so far
12 months
Homes
100
Sold or booked
78%
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
4

Construction progress of TECHOPS ROYAL, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
TECHOPS ROYAL100%100%95%0%

Commencement certificate (CC), as filed on MahaRERA

  • TECHOPS ROYAL: covers 10 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on TECHOPS ROYAL every month.

TECHOPS ROYAL: buildings, flats and land, as filed on MahaRERA

The builder’s record and reviews

Techops Infrastructure (a group of 2 linked companies) has 6 projects on MahaRERA since 2019, this one included. Of the 4 GharKundli has checked: 1 finished, all within the promised date; 3 still being built, 1 past the promised date (typically 9 months late). No complaints on MahaRERA.

Read Google reviews of TECHOPS ROYAL →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

TECHOPS ROYAL: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about TECHOPS ROYAL

What is the possession date of TECHOPS ROYAL?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for TECHOPS ROYAL in Dighori, Nagpur is 7 February 2027 — 12 months later than 14 February 2026, the date given at registration.

Is the builder's possession date different from the MahaRERA date for TECHOPS ROYAL?

Builders and listing sites often quote an earlier "target" date for handover. The completion date TECHOPS ROYAL's builder has filed on MahaRERA, the official one, is 7 February 2027, already 12 months later than the 14 February 2026 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of TECHOPS ROYAL extended?

According to GharKundli's check of MahaRERA records (updated October 2026), TECHOPS ROYAL's builder applied to MahaRERA to extend the completion date once: to 7 February 2027, giving the reason "To The Maharashtra Real Estate Regulatory Authority (MahaRERA) Subject: Explanation for Delay and Request for Extension under Section 7(3) Respected Sir/Madam, We would like to submit this explanation regarding the delay in completion of our project registered under MahaRERA, which is due to expire on 14th February 2026. The delay has occurred solely due to unforeseen natural calamities that were entirely beyond our control, and we therefore request an extension under Section 7(3) of the Real Estate (Regulation and Development) Act, 2016. The city of Nagpur, where our project is located, ex…".

What is the RERA number of TECHOPS ROYAL?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of TECHOPS ROYAL in Dighori, Nagpur is P50500051236.

Is TECHOPS ROYAL registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), TECHOPS ROYAL is registered as P50500051236 and its status is "Registered and active".

What is the construction status of TECHOPS ROYAL?

According to GharKundli's check of MahaRERA records (updated October 2026), TECHOPS ROYAL's status on MahaRERA is "Registered and active". As filed by the builder, slab work on TECHOPS ROYAL is 100% done and internal work 95%. GharKundli's full report compares construction progress with the deadline.

Does TECHOPS ROYAL have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is TECHOPS ROYAL safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), TECHOPS ROYAL is registered on MahaRERA as P50500051236, its completion date has moved 12 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if TECHOPS ROYAL's possession date changes?

The latest dates are on TECHOPS ROYAL's MahaRERA page (P50500051236). GharKundli's Kundli Watch sends a free WhatsApp update on TECHOPS ROYAL every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does TECHOPS ROYAL have?

According to GharKundli's check of MahaRERA records (updated October 2026), TECHOPS ROYAL has one building filed: TECHOPS ROYAL with 41 floors and 119 units.

How much parking does TECHOPS ROYAL have?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 58 covered car parking spaces for TECHOPS ROYAL.

How big is the land of TECHOPS ROYAL?

According to GharKundli's check of MahaRERA records (updated October 2026), TECHOPS ROYAL stands on 3,036 sq m of land (about 0.8 acres), with 10,451 sq m of sanctioned built-up area.

What is the track record of TECHOPS ROYAL's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Techops Infrastructure (a group of 2 linked companies) has 6 projects on MahaRERA since 2019, this one included. Of the 4 GharKundli has checked: 1 finished, all within the promised date; 3 still being built, 1 past the promised date (typically 9 months late). No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.

Where can I read reviews of TECHOPS ROYAL?

Google Maps has reviews of TECHOPS ROYAL written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is TECHOPS ROYAL?

TECHOPS ROYAL by Techops Infrastructure Pvt. Ltd. is in Dighori, Nagpur (pincode 440034), near Mhalginagar, Maharashtra, and is registered on MahaRERA as P50500051236, per GharKundli's check of MahaRERA records.

How many homes are in TECHOPS ROYAL?

According to GharKundli's check of MahaRERA records (updated October 2026), TECHOPS ROYAL has 100 homes in 1 tower registered on MahaRERA, and 78% of them are sold or booked.

When was TECHOPS ROYAL registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), TECHOPS ROYAL was registered on MahaRERA on 8 June 2023. GharKundli did not find a title report on the land on file there.

Are there court cases on TECHOPS ROYAL?

No court cases are listed for TECHOPS ROYAL on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder of TECHOPS ROYAL?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Techops Infrastructure Pvt. Ltd., which has 4 other projects registered on MahaRERA.

All projects with possession due in 2027 in Nagpur →

Other projects in Nagpur (Urban)

All 120 projects in Mhalginagar (440034) →

Other projects by Techops Infrastructure Pvt. Ltd.

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.