Possession date of Uttara Heights: 30 April 2027. This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P50500053245, and currently active. Its completion date is now April 2027, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time.

Source: GharKundli’s check of MahaRERA records, November 2026.

What do you want to know about Uttara Heights?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of Uttara Heights has moved

  1. 31 December 2026

    Completion date given when the project was registered

  2. 30 April 2027

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: Uttara Heights’s extension records on MahaRERA (P50500053245), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Uttara Heights

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the April 2027 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P50500053245
Status
Registered and active
Builder
Sundershilp Buildcon
Location
Near Tahsil Office, Nagpur · 441110
Project type
Residential / Group Housing
Registered on
23 Oct 2023
Completion date at registration
December 2026
Latest completion date
April 2027
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
52
Sold or booked
0%
Towers
2
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found

Construction progress of Uttara Heights, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
Wing A100%100%51%29%
Wing B100%61%10%0%

Commencement certificate (CC), as filed on MahaRERA

  • Wing A: covers 8 floors
  • Wing B: covers 8 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Uttara Heights every month.

Uttara Heights: buildings, flats and land, as filed on MahaRERA

  • Buildings: Wing A (8 floors, 32 units) · Wing B (8 floors, 26 units)
  • Land: 1,815 sq m (about 0.4 acres) · sanctioned built-up 4,065 sq m
  • Boundaries filed include: Kanholibara Road, Pandhan Road

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of Uttara Heights →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Uttara Heights: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about Uttara Heights

What is the possession date of Uttara Heights?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for Uttara Heights in Near Tahsil Office, Nagpur is 30 April 2027, including MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for Uttara Heights?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Uttara Heights's builder has filed on MahaRERA, the official one, is 30 April 2027, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

What is the RERA number of Uttara Heights?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of Uttara Heights in Near Tahsil Office, Nagpur is P50500053245.

Is Uttara Heights registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Uttara Heights is registered as P50500053245 and its status is "Registered and active".

What is the construction status of Uttara Heights?

According to GharKundli's check of MahaRERA records (updated November 2026), Uttara Heights's status on MahaRERA is "Registered and active". As filed by the builder, slab work ranges from 61% to 100% across 2 towers. GharKundli's full report compares construction progress with the deadline.

Does Uttara Heights have complaints on MahaRERA?

No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.

Is Uttara Heights safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), Uttara Heights is registered on MahaRERA as P50500053245, its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if Uttara Heights's possession date changes?

The latest dates are on Uttara Heights's MahaRERA page (P50500053245). GharKundli's Kundli Watch sends a free WhatsApp update on Uttara Heights every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Uttara Heights have?

According to GharKundli's check of MahaRERA records (updated November 2026), Uttara Heights has 2 buildings filed: Wing A with 8 floors and 32 units; Wing B with 8 floors and 26 units.

How big is the land of Uttara Heights?

According to GharKundli's check of MahaRERA records (updated November 2026), Uttara Heights stands on 1,815 sq m of land (about 0.4 acres), with 4,065 sq m of sanctioned built-up area.

Where can I read reviews of Uttara Heights?

Google Maps has reviews of Uttara Heights written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is Uttara Heights?

Uttara Heights by Sundershilp Buildcon is in Near Tahsil Office, Nagpur (pincode 441110), Maharashtra, and is registered on MahaRERA as P50500053245, per GharKundli's check of MahaRERA records. Its boundaries filed there include Kanholibara Road, Pandhan Road.

How many homes are in Uttara Heights?

According to GharKundli's check of MahaRERA records (updated November 2026), Uttara Heights has 52 homes in 2 towers registered on MahaRERA, and 0% of them are sold or booked.

When was Uttara Heights registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Uttara Heights was registered on MahaRERA on 23 October 2023. GharKundli did not find a title report on the land on file there.

Are there court cases on Uttara Heights?

No court cases are listed for Uttara Heights on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).

Who is the builder of Uttara Heights?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is Sundershilp Buildcon.

All projects with possession due in 2027 in Nagpur →

Other projects in Hingna

All 164 projects in Hingna (441110) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.