Srushti Enclave
by Gadkari Builders & Associates · Chembur, MumbaiAlso near Kurla, Ghatla, Fci
Possession date of Srushti Enclave: 30 December 2025, moved from 31 December 2019 (72 months later). This is the latest completion date the builder has filed on MahaRERA, and it has already passed. How to check it yourself
Registered on MahaRERA under P51900011095. Status: Lapsed (registration period ended). MahaRERA has issued a regulatory order on this project. 12 complaints are listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, October 2026.
The latest completion date on MahaRERA (December 2025) has passed.
What do you want to know about Srushti Enclave?
How the possession date of Srushti Enclave has moved
31 December 2019
Completion date given when the project was registered
30 December 2020
Extended at the builder's request (MahaRERA application EXT51800005230)
Reason the builder gave MahaRERA: “Approval from MHADA pending”
31 December 2023
Extended at the builder's request (MahaRERA application EXT51800010094)
Reason the builder gave MahaRERA:
“We have faced many difficulties since the project started, Covid 19 , delay in approval from a government authority, financial problems, and because the project is expired in 2019 we are not able to sell the pending flats, once we get the e…” Read the full reason
“We have faced many difficulties since the project started, Covid 19 , delay in approval from a government authority, financial problems, and because the project is expired in 2019 we are not able to sell the pending flats, once we get the extension we are able to sell the pending flats and to complete the project at the earliest.”30 June 2025
Extended at the builder's request (MahaRERA application EXT51800019108)
Reason the builder gave MahaRERA:
“1. In 2020 due to the Pandemic situation of COVID-19 and the lockdown imposed by the government, we could not proceed with the construction activities. 2. Also, due to the pandemic, there was a shortage of Materials, Labour and transportati…” Read the full reason
“1. In 2020 due to the Pandemic situation of COVID-19 and the lockdown imposed by the government, we could not proceed with the construction activities. 2. Also, due to the pandemic, there was a shortage of Materials, Labour and transportation services. 3. After the impact of the pandemic, the increasing prices of construction materials such as cement, steel, copper, electrical, plumping and paints resulted in the shortage of the progress of new multi-storied apartment projects. We suffering from delays in terms of the number of months it takes for the arrival of the Construction Material on…”30 December 2025
Extended at the builder's request (MahaRERA application EA30062501863)
Reason the builder gave MahaRERA:
“a. An explanatory note setting out the grounds and reasons for the delay in the completion of the real estate project 1. In 2020 due to the Pandemic situation of COVID-19 and the lockdown imposed by the government, we could not proceed with…” Read the full reason
“a. An explanatory note setting out the grounds and reasons for the delay in the completion of the real estate project 1. In 2020 due to the Pandemic situation of COVID-19 and the lockdown imposed by the government, we could not proceed with the construction activities. 2. Also, due to the pandemic, there was a shortage of Materials, Labour and transportation services. 3. After the impact of the pandemic, the increasing prices of construction materials such as cement, steel, copper, electrical, plumping and paints resulted in the shortage of the progress of new multi-storied apartment projec…”
Source: Srushti Enclave’s extension records on MahaRERA (P51900011095), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Srushti Enclave
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 12 complaints and 2 court cases, and how it ended
- Construction pace against the December 2025 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51900011095
- Status
- Lapsed (registration period ended)
- Builder
- Gadkari Builders & Associates
- Location
- Chembur, Mumbai · 400071
- Project type
- Residential / Group Housing
- Registered on
- 31 Aug 2017
- Completion date at registration
- December 2019
- Latest completion date
- December 2025
- Delay so far
- 72 months
- Homes
- 59
- Sold or booked
- 86%
- Towers
- 1
- Complaints on MahaRERA
- 12
- Court cases listed
- 2
- Appeals at the tribunal
- 7
- MahaRERA regulatory orders
- 1
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 1
Construction progress of Srushti Enclave, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| Srushti Enclave | 100% | 100% | 100% | 100% |
Commencement certificate (CC), as filed on MahaRERA
- Srushti Enclave: covers 16 floors
Latest CC order on MahaRERA: dated 25/07/2024.
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Srushti Enclave every month.
Srushti Enclave: buildings, flats and land, as filed on MahaRERA
| Type | Carpet area (sq ft) | Units |
|---|---|---|
| 2 BHK | 626 – 660 | 57 |
| Other | 2,754 | 1 |
| 1 BHK | 517 | 1 |
- Buildings: Srushti Enclave (16 floors, 59 units)
- Car parking: 20 covered
- Land: 742 sq m (about 0.2 acres) · sanctioned built-up 5,052 sq m
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
Gadkari Builders & Associates has 2 projects on MahaRERA since 2017, this one included. Of the 2 GharKundli has checked: 1 still being built, 1 past the promised date (typically 78 months late); 1 lapsed. 12 complaints on MahaRERA across 1 project.
Read Google reviews of Srushti Enclave →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Srushti Enclave: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about Srushti Enclave
What is the possession date of Srushti Enclave?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Srushti Enclave in Chembur, Mumbai is 30 December 2025 — 72 months later than 31 December 2019, the date given at registration. That date has already passed.
Is the builder's possession date different from the MahaRERA date for Srushti Enclave?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Srushti Enclave's builder has filed on MahaRERA, the official one, is 30 December 2025, already 72 months later than the 31 December 2019 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Srushti Enclave extended?
According to GharKundli's check of MahaRERA records (updated October 2026), Srushti Enclave's builder applied to MahaRERA to extend the completion date 4 times: to 30 December 2020, giving the reason "Approval from MHADA pending"; to 31 December 2023, giving the reason "We have faced many difficulties since the project started, Covid 19 , delay in approval from a government authority, financial problems, and because the project is expired in 2019 we are not able to sell the pending flats, once we get the extension we are able to sell the pending flats and to complete the project at the earliest."; to 30 June 2025, giving the reason "1. In 2020 due to the Pandemic situation of COVID-19 and the lockdown imposed by the government, we could not proceed with the construction activities. 2. Also, due to the pandemic, there was a shortage of Materials, Labour and transportation services. 3. After the impact of the pandemic, the increasing prices of construction materials such as cement, steel, copper, electrical, plumping and paints resulted in the shortage of the progress of new multi-storied apartment projects. We suffering from delays in terms of the number of months it takes for the arrival of the Construction Material on…"; to 30 December 2025, giving the reason "a. An explanatory note setting out the grounds and reasons for the delay in the completion of the real estate project 1. In 2020 due to the Pandemic situation of COVID-19 and the lockdown imposed by the government, we could not proceed with the construction activities. 2. Also, due to the pandemic, there was a shortage of Materials, Labour and transportation services. 3. After the impact of the pandemic, the increasing prices of construction materials such as cement, steel, copper, electrical, plumping and paints resulted in the shortage of the progress of new multi-storied apartment projec…".
What is the RERA number of Srushti Enclave?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Srushti Enclave in Chembur, Mumbai is P51900011095.
Is Srushti Enclave registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Srushti Enclave is registered as P51900011095 and its status is "Lapsed (registration period ended)".
What is the construction status of Srushti Enclave?
According to GharKundli's check of MahaRERA records (updated October 2026), Srushti Enclave's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work on Srushti Enclave is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.
Does Srushti Enclave have complaints on MahaRERA?
12 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is Srushti Enclave safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Srushti Enclave is registered on MahaRERA as P51900011095, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 72 months since registration and 12 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if Srushti Enclave's possession date changes?
The latest dates are on Srushti Enclave's MahaRERA page (P51900011095). GharKundli's Kundli Watch sends a free WhatsApp update on Srushti Enclave every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Srushti Enclave have?
According to GharKundli's check of MahaRERA records (updated October 2026), Srushti Enclave has one building filed: Srushti Enclave with 16 floors and 59 units.
What are the flat sizes (carpet area) in Srushti Enclave?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for Srushti Enclave: 2 BHK: 626 to 660 sq ft carpet (57 homes); Other: 2754 sq ft carpet (1 homes); 1 BHK: 517 sq ft carpet (1 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.
How much parking does Srushti Enclave have?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 20 covered car parking spaces for Srushti Enclave.
How big is the land of Srushti Enclave?
According to GharKundli's check of MahaRERA records (updated October 2026), Srushti Enclave stands on 742 sq m of land (about 0.2 acres), with 5,052 sq m of sanctioned built-up area.
What is the track record of Srushti Enclave's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Gadkari Builders & Associates has 2 projects on MahaRERA since 2017, this one included. Of the 2 GharKundli has checked: 1 still being built, 1 past the promised date (typically 78 months late); 1 lapsed. 12 complaints on MahaRERA across 1 project. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of Srushti Enclave?
Google Maps has reviews of Srushti Enclave written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 12 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is Srushti Enclave?
Srushti Enclave by Gadkari Builders & Associates is in Chembur, Mumbai (pincode 400071), near Kurla, Ghatla, Fci, Maharashtra, and is registered on MahaRERA as P51900011095, per GharKundli's check of MahaRERA records.
How many homes are in Srushti Enclave?
According to GharKundli's check of MahaRERA records (updated October 2026), Srushti Enclave has 59 homes in 1 tower registered on MahaRERA, and 86% of them are sold or booked.
When was Srushti Enclave registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Srushti Enclave was registered on MahaRERA on 31 August 2017. GharKundli did not find a title report on the land on file there.
Are there court cases on Srushti Enclave?
2 court cases are listed for Srushti Enclave on MahaRERA, and 7 appeals at the tribunal, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.
Who is the builder of Srushti Enclave?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Gadkari Builders & Associates, which has 1 other project registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of Srushti Enclave
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in pincode 400071
- SHREE SARASWATI CHS LTD PLOT 8B
- TULSI CHAMBER PHASE II
- SAMPOORNA
- QUEENS PARK
- ARHAM MOURYA
- 71 Pardis
- ICONS 71
- Viera Golf Greens
Other projects by Gadkari Builders & Associates
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.