SAI CHHAYA-2
by ARIHANT INFRA PROJECTS · Mouza Somalwada, NagpurAlso near Beltarodi, Manish Nagar, Khamla
Possession date of SAI CHHAYA-2: 28 June 2027, moved from 30 June 2025 (20 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P50500052571, and currently active. Its completion date has moved from June 2025 to June 2027: 20 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about SAI CHHAYA-2?
How the possession date of SAI CHHAYA-2 has moved
30 June 2025
Completion date given when the project was registered
28 February 2026
Extended at the builder's request (MahaRERA application EA30072502256)
Reason the builder gave MahaRERA:
“To: Maharashtra Real Estate Regulatory Authority (MahaRERA) Mumbai, Maharashtra Subject: Declaration for Extension of Completion Date for the Project Sai Chhaya-2 RERA Registration Number: P50500052571. We, Arihant Infra Projects, the Promo…” Read the full reason
“To: Maharashtra Real Estate Regulatory Authority (MahaRERA) Mumbai, Maharashtra Subject: Declaration for Extension of Completion Date for the Project Sai Chhaya-2 RERA Registration Number: P50500052571. We, Arihant Infra Projects, the Promoter of the real estate project known as SAI CHHAYA-2, bearing MahaRERA Registration Number P50500052571, situated at PLOT NO.68,69,75,76 KH NO.94/2 at Nagpur (M Corp.), Nagpur (Urban), Nagpur, 440025, do hereby solemnly declare as under: 1. That the registration of the said project was granted under Section 5 of the Real Estate (Regulation and Development…”28 February 2027
Extended at the builder's request (MahaRERA application EA09042620590)
Reason the builder gave MahaRERA:
“We, ARIHANT INFRA PROJECTS, Promoter of the real estate project “SAI CHHAYA-2”, bearing MahaRERA Registration No. P50500052571, hereby submit this application seeking an extension of twelve (12) months for completion of the said project. Th…” Read the full reason
“We, ARIHANT INFRA PROJECTS, Promoter of the real estate project “SAI CHHAYA-2”, bearing MahaRERA Registration No. P50500052571, hereby submit this application seeking an extension of twelve (12) months for completion of the said project. The project progress has been affected due to unavoidable delays in obtaining statutory approvals, shortage of skilled and semi-skilled labour, disruptions in procurement and supply of construction materials, and additional time required for execution of infrastructure, amenities, and essential services in compliance with approved plans and applicable norms…”28 June 2027
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: SAI CHHAYA-2’s extension records on MahaRERA (P50500052571), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on SAI CHHAYA-2
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the June 2027 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
Other wings and phases of this project
Each is registered on MahaRERA separately, with its own possession date. Check the one your flat is in.
- SAI CHHAYA - 5P50500078755 · possession 30 Apr 2027
- MahaRERA registration
- P50500052571
- Status
- Registered and active
- Builder
- ARIHANT INFRA PROJECTS
- Location
- Mouza Somalwada, Nagpur · 440025
- Project type
- Residential / Group Housing
- Registered on
- 11 Sep 2023
- Completion date at registration
- June 2025
- Latest completion date
- June 2027
- Delay so far
- 20 months
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 14
- Sold or booked
- 93%
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 1
Construction progress of SAI CHHAYA-2, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| SAI CHHAYA-2 | 100% | 100% | 98% | 95% |
Commencement certificate (CC), as filed on MahaRERA
- SAI CHHAYA-2: covers 8 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on SAI CHHAYA-2 every month.
SAI CHHAYA-2: buildings, flats and land, as filed on MahaRERA
- Buildings: SAI CHHAYA-2 (8 floors, 14 units)
- Car parking: 1 covered
- Land: 512 sq m (about 0.1 acres) · sanctioned built-up 1,467 sq m
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
Arihant Infra Projects has 2 projects on MahaRERA since 2023, this one included. Of the 2 GharKundli has checked: 2 still being built, 1 past the promised date (typically 12 months late). No complaints on MahaRERA.
Read Google reviews of SAI CHHAYA-2 →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
SAI CHHAYA-2: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about SAI CHHAYA-2
What is the possession date of SAI CHHAYA-2?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for SAI CHHAYA-2 in Mouza Somalwada, Nagpur is 28 June 2027 — 20 months later than 30 June 2025, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for SAI CHHAYA-2?
Builders and listing sites often quote an earlier "target" date for handover. The completion date SAI CHHAYA-2's builder has filed on MahaRERA, the official one, is 28 June 2027, already 20 months later than the 30 June 2025 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of SAI CHHAYA-2 extended?
According to GharKundli's check of MahaRERA records (updated October 2026), SAI CHHAYA-2's builder applied to MahaRERA to extend the completion date 2 times: to 28 February 2026, giving the reason "To: Maharashtra Real Estate Regulatory Authority (MahaRERA) Mumbai, Maharashtra Subject: Declaration for Extension of Completion Date for the Project Sai Chhaya-2 RERA Registration Number: P50500052571. We, Arihant Infra Projects, the Promoter of the real estate project known as SAI CHHAYA-2, bearing MahaRERA Registration Number P50500052571, situated at PLOT NO.68,69,75,76 KH NO.94/2 at Nagpur (M Corp.), Nagpur (Urban), Nagpur, 440025, do hereby solemnly declare as under: 1. That the registration of the said project was granted under Section 5 of the Real Estate (Regulation and Development…"; to 28 February 2027, giving the reason "We, ARIHANT INFRA PROJECTS, Promoter of the real estate project “SAI CHHAYA-2”, bearing MahaRERA Registration No. P50500052571, hereby submit this application seeking an extension of twelve (12) months for completion of the said project. The project progress has been affected due to unavoidable delays in obtaining statutory approvals, shortage of skilled and semi-skilled labour, disruptions in procurement and supply of construction materials, and additional time required for execution of infrastructure, amenities, and essential services in compliance with approved plans and applicable norms…". MahaRERA also added its automatic 4-month extension for all eligible projects.
What is the RERA number of SAI CHHAYA-2?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of SAI CHHAYA-2 in Mouza Somalwada, Nagpur is P50500052571.
Is SAI CHHAYA-2 registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), SAI CHHAYA-2 is registered as P50500052571 and its status is "Registered and active".
What is the construction status of SAI CHHAYA-2?
According to GharKundli's check of MahaRERA records (updated October 2026), SAI CHHAYA-2's status on MahaRERA is "Registered and active". As filed by the builder, slab work on SAI CHHAYA-2 is 100% done and internal work 98%. GharKundli's full report compares construction progress with the deadline.
Does SAI CHHAYA-2 have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is SAI CHHAYA-2 safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), SAI CHHAYA-2 is registered on MahaRERA as P50500052571, its completion date has moved 20 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
Does SAI CHHAYA-2 have other wings or phases?
Yes. MahaRERA lists 1 other registration of the same project, each with its own possession date: SAI CHHAYA - 5 (P50500078755, possession 30 Apr 2027). Check that your agreement names the registration of your own wing.
How can I get updates if SAI CHHAYA-2's possession date changes?
The latest dates are on SAI CHHAYA-2's MahaRERA page (P50500052571). GharKundli's Kundli Watch sends a free WhatsApp update on SAI CHHAYA-2 every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does SAI CHHAYA-2 have?
According to GharKundli's check of MahaRERA records (updated October 2026), SAI CHHAYA-2 has one building filed: SAI CHHAYA-2 with 8 floors and 14 units.
How much parking does SAI CHHAYA-2 have?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 1 covered car parking spaces for SAI CHHAYA-2.
How big is the land of SAI CHHAYA-2?
According to GharKundli's check of MahaRERA records (updated October 2026), SAI CHHAYA-2 stands on 512 sq m of land (about 0.1 acres), with 1,467 sq m of sanctioned built-up area.
What is the track record of SAI CHHAYA-2's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Arihant Infra Projects has 2 projects on MahaRERA since 2023, this one included. Of the 2 GharKundli has checked: 2 still being built, 1 past the promised date (typically 12 months late). No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of SAI CHHAYA-2?
Google Maps has reviews of SAI CHHAYA-2 written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is SAI CHHAYA-2?
SAI CHHAYA-2 by ARIHANT INFRA PROJECTS is in Mouza Somalwada, Nagpur (pincode 440025), near Beltarodi, Manish Nagar, Khamla, Maharashtra, and is registered on MahaRERA as P50500052571, per GharKundli's check of MahaRERA records.
How many homes are in SAI CHHAYA-2?
According to GharKundli's check of MahaRERA records (updated October 2026), SAI CHHAYA-2 has 14 homes in 1 tower registered on MahaRERA, and 93% of them are sold or booked.
When was SAI CHHAYA-2 registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), SAI CHHAYA-2 was registered on MahaRERA on 11 September 2023. GharKundli did not find a title report on the land on file there.
Are there court cases on SAI CHHAYA-2?
No court cases are listed for SAI CHHAYA-2 on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder of SAI CHHAYA-2?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is ARIHANT INFRA PROJECTS, which has 1 other project registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of SAI CHHAYA-2
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2027 in Nagpur →
Other projects in Nagpur (Urban)
- SHUBH SWAPN ARCADE
- ROYAL PARK
- GLOCAL SQUARE 3 RD FLOOR
- SHREE APARTMENTS
- Mithila Apartment
- EMPRESS ROYAL EFGH
- ROYAL PRIDE
- Swapnapurtee - A Project by NMC
Other projects by ARIHANT INFRA PROJECTS
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.