Aveza Phase 1
by Tata Housing Development Company Limited · Mulund East, MumbaiAlso near Mulund West, Vile Parle East, Thane East
Possession date of Aveza Phase 1: 29 December 2024, moved from 30 December 2023 (12 months later). This is the latest completion date the builder has filed on MahaRERA, and it has already passed. How to check it yourself
Registered on MahaRERA under P51900007527. Status: Lapsed (registration period ended). MahaRERA has issued a regulatory order on this project. 3 complaints are listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, October 2026.
The latest completion date on MahaRERA (December 2024) has passed.
What do you want to know about Aveza Phase 1?
How the possession date of Aveza Phase 1 has moved
30 December 2023
Completion date given when the project was registered
29 December 2024
Extended at the builder's request (MahaRERA application EXT51800018436)
Reason the builder gave MahaRERA: “In accordance with circular no 28, we hereby apply for extension of our project u/s 6 in Format B.”
Source: Aveza Phase 1’s extension records on MahaRERA (P51900007527), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Aveza Phase 1
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 3 complaints and 2 court cases, and how it ended
- Construction pace against the December 2024 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
Other wings and phases of this project
Each is registered on MahaRERA separately, with its own possession date. Check the one your flat is in.
- Aveza Phase 2P51900007740 · possession 30 Dec 2025
- MahaRERA registration
- P51900007527
- Status
- Lapsed (registration period ended)
- Builder
- Tata Housing Development Company Limited
- Location
- Mulund East, Mumbai · 400081
- Project type
- Residential / Group Housing
- Registered on
- 17 Aug 2017
- Completion date at registration
- December 2023
- Latest completion date
- December 2024
- Delay so far
- 12 months
- Homes
- 592
- Towers
- 3
- Complaints on MahaRERA
- 3
- Court cases listed
- 2
- Appeals at the tribunal
- 4
- MahaRERA regulatory orders
- 1
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 2
Construction progress of Aveza Phase 1, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| Tower A | 100% | 45% | 12% | 0% |
| Tower B | 100% | 83% | 25% | 0% |
| Tower C | 100% | 44% | 15% | 0% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Aveza Phase 1 every month.
Aveza Phase 1: buildings, flats and land, as filed on MahaRERA
- Buildings: Tower A (49 floors) · Tower B (41 floors) · Tower C (48 floors)
- Land: 35,122 sq m (about 8.7 acres) · sanctioned built-up 44,822 sq m · recreational space 5,014 sq m
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
Tata Housing Development (a group of 2 linked companies) has 5 projects on MahaRERA since 2017, this one included. Of the 5 GharKundli has checked: 2 finished, all within the promised date; 2 still being built, none past the promised date yet; 1 lapsed. 35 complaints on MahaRERA across 3 projects.
Read Google reviews of Aveza Phase 1 →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Aveza Phase 1: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about Aveza Phase 1
What is the possession date of Aveza Phase 1?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Aveza Phase 1 in Mulund East, Mumbai is 29 December 2024 — 12 months later than 30 December 2023, the date given at registration. That date has already passed.
Is the builder's possession date different from the MahaRERA date for Aveza Phase 1?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Aveza Phase 1's builder has filed on MahaRERA, the official one, is 29 December 2024, already 12 months later than the 30 December 2023 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Aveza Phase 1 extended?
According to GharKundli's check of MahaRERA records (updated October 2026), Aveza Phase 1's builder applied to MahaRERA to extend the completion date once: to 29 December 2024, giving the reason "In accordance with circular no 28, we hereby apply for extension of our project u/s 6 in Format B.".
What is the RERA number of Aveza Phase 1?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Aveza Phase 1 in Mulund East, Mumbai is P51900007527.
Is Aveza Phase 1 registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Aveza Phase 1 is registered as P51900007527 and its status is "Lapsed (registration period ended)".
What is the construction status of Aveza Phase 1?
According to GharKundli's check of MahaRERA records (updated October 2026), Aveza Phase 1's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work ranges from 44% to 83% across 3 towers. GharKundli's full report compares construction progress with the deadline.
Does Aveza Phase 1 have complaints on MahaRERA?
3 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is Aveza Phase 1 safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Aveza Phase 1 is registered on MahaRERA as P51900007527, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 12 months since registration and 3 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
Does Aveza Phase 1 have other wings or phases?
Yes. MahaRERA lists 1 other registration of the same project, each with its own possession date: Aveza Phase 2 (P51900007740, possession 30 Dec 2025). Check that your agreement names the registration of your own wing.
How can I get updates if Aveza Phase 1's possession date changes?
The latest dates are on Aveza Phase 1's MahaRERA page (P51900007527). GharKundli's Kundli Watch sends a free WhatsApp update on Aveza Phase 1 every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Aveza Phase 1 have?
According to GharKundli's check of MahaRERA records (updated October 2026), Aveza Phase 1 has 3 buildings filed: Tower A with 49 floors; Tower B with 41 floors; Tower C with 48 floors.
How big is the land of Aveza Phase 1?
According to GharKundli's check of MahaRERA records (updated October 2026), Aveza Phase 1 stands on 35,122 sq m of land (about 8.7 acres), with 44,822 sq m of sanctioned built-up area and 5,014 sq m of recreational open space.
What is the track record of Aveza Phase 1's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Tata Housing Development (a group of 2 linked companies) has 5 projects on MahaRERA since 2017, this one included. Of the 5 GharKundli has checked: 2 finished, all within the promised date; 2 still being built, none past the promised date yet; 1 lapsed. 35 complaints on MahaRERA across 3 projects. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of Aveza Phase 1?
Google Maps has reviews of Aveza Phase 1 written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 3 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is Aveza Phase 1?
Aveza Phase 1 by Tata Housing Development Company Limited is in Mulund East, Mumbai (pincode 400081), near Mulund West, Vile Parle East, Thane East, Maharashtra, and is registered on MahaRERA as P51900007527, per GharKundli's check of MahaRERA records.
How many homes are in Aveza Phase 1?
According to GharKundli's check of MahaRERA records (updated October 2026), Aveza Phase 1 has 592 homes in 3 towers registered on MahaRERA.
When was Aveza Phase 1 registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Aveza Phase 1 was registered on MahaRERA on 17 August 2017. GharKundli did not find a title report on the land on file there.
Are there court cases on Aveza Phase 1?
2 court cases are listed for Aveza Phase 1 on MahaRERA, and 4 appeals at the tribunal, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.
Who is the builder of Aveza Phase 1?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Tata Housing Development Company Limited, which has 2 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of Aveza Phase 1
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in pincode 400081
- Kam Ganesh Co-operative Housing Society Ltd and Nav Amardeep Co-operative Housing Society Limited
- RBI EMPLOYEES SHREE SAHAWAS CO OP HSG SOC LTD
- GOVIND PRAKASH SRA CHS LTD
- BIMAL APARTMENT CHSL
- Ganesh Dham
- SATRE ELITE
- PEARL
- New Usha Vihar Chsl
Other projects by Tata Housing Development Company Limited
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.