ANMOLPRITI
by Muktistar Buildcon Private Limited VISHWANATH GAIKWAD · Charkop Kandivali West, MumbaiAlso near Borivali, Chikoowadi
Possession: ANMOLPRITI is marked completed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51800006598. Status: Completed. MahaRERA has issued a regulatory order on this project. 4 complaints are listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about ANMOLPRITI?
How the possession date of ANMOLPRITI has moved
31 December 2018
Completion date given when the project was registered
30 June 2021
Extended at the builder's request (MahaRERA application EXT51800000858)
Reason the builder gave MahaRERA:
“Reason for extension: Since our Project type is MHADA Redevelopment, we got our MHADA approval with prevailing policy with sharing in Sept 2016. Subsequently the same is approved in MCGM in 2017 & we started our commencement on site. In vie…” Read the full reason
“Reason for extension: Since our Project type is MHADA Redevelopment, we got our MHADA approval with prevailing policy with sharing in Sept 2016. Subsequently the same is approved in MCGM in 2017 & we started our commencement on site. In view of prevailing policy of 2016 govt. of Maharashtra amended DCR 33 (5) in July 2017 which allows redevelopment with premium which is principally applicable for our society & so society resolved the same for migration. We have submitted our proposal to MHADA for migration in December 2017. Due to pending EP’s of DCPR 2034, we have still not obtained revise…”30 June 2021
Extended at the builder's request (MahaRERA application EXT51800003938)
Reason the builder gave MahaRERA:
“Since our Project type is MHADA Redevelopment, we have initiated with construction of the project since 2014 as per prevailing approvals from MHADA as well as MCGM. In same regards MHADA Redevelopment policy has changed as per DCPR 2034. Fi…” Read the full reason
“Since our Project type is MHADA Redevelopment, we have initiated with construction of the project since 2014 as per prevailing approvals from MHADA as well as MCGM. In same regards MHADA Redevelopment policy has changed as per DCPR 2034. Finally we got our MHADA approval with prevailing policy with premium on 23/07/2019. In view of prevailing policy of DCPR 2034 MHADA Redevelopment DCPR 33(5) declared in November 2018. In same regards Gov. Proposed amendments with respect to Premium charges, Development Cess, Fungible Premium on 20th August 2019, to make all proposals Economical viable. The…”30 June 2024
Extended at the builder's request (MahaRERA application EXT51800012516)
Reason the builder gave MahaRERA:
“The Promoter has changed from Propreitorship into Private Limited Company. We have received approval from Maha RERA for the change of Promoter. The New Promoter is "Muktistar Buildcon Private Limited". Therefore, We hereby apply for extensi…” Read the full reason
“The Promoter has changed from Propreitorship into Private Limited Company. We have received approval from Maha RERA for the change of Promoter. The New Promoter is "Muktistar Buildcon Private Limited". Therefore, We hereby apply for extension under Section 6 of the Maharastra (Regulation and Development) Act, 2016.”30 June 2025
Extended at the builder's request (MahaRERA application EXT51800024172)
Reason the builder gave MahaRERA:
“The delay in the above-mentioned project is due to rainy season, permission to dig cement road is not granted. We have already applied for permission. But as the road in front is made of cement concrete, permission will be given only after…” Read the full reason
“The delay in the above-mentioned project is due to rainy season, permission to dig cement road is not granted. We have already applied for permission. But as the road in front is made of cement concrete, permission will be given only after monsoon. Drinking water and sewage as well as electricity supply cannot be obtained in accordance with the above subject. Thus, we are seeking extension of the date of completion of the project so as to not compromise with the quality of the work.”
Source: ANMOLPRITI’s extension records on MahaRERA (P51800006598), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on ANMOLPRITI
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 4 complaints, and how it ended
- Construction pace against the June 2025 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51800006598
- Status
- Completed
- Builder
- Muktistar Buildcon Private Limited VISHWANATH GAIKWAD
- Location
- Charkop Kandivali West, Mumbai · 400067
- Project type
- Residential / Group Housing
- Registered on
- 14 Aug 2017
- Completion date at registration
- December 2018
- Latest completion date
- June 2025
- Delay so far
- 78 months
- Towers
- 1
- Complaints on MahaRERA
- 4
- Court cases listed
- 0
- Appeals at the tribunal
- 2
- MahaRERA regulatory orders
- 1
- Title report on file
- Not found
Construction progress of ANMOLPRITI, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| ANMOLPRITI | 100% | 100% | 97% | 60% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on ANMOLPRITI every month.
ANMOLPRITI: buildings, flats and land, as filed on MahaRERA
- Buildings: ANMOLPRITI (26 floors)
- Land: 882 sq m (about 0.2 acres) · sanctioned built-up 1,050 sq m
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of ANMOLPRITI →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
ANMOLPRITI: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about ANMOLPRITI
What is the possession date of ANMOLPRITI?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for ANMOLPRITI in Charkop Kandivali West, Mumbai is 30 June 2025 — 78 months later than 31 December 2018, the date given at registration.
Is the builder's possession date different from the MahaRERA date for ANMOLPRITI?
Builders and listing sites often quote an earlier "target" date for handover. The completion date ANMOLPRITI's builder has filed on MahaRERA, the official one, is 30 June 2025, already 78 months later than the 31 December 2018 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of ANMOLPRITI extended?
According to GharKundli's check of MahaRERA records (updated October 2026), ANMOLPRITI's builder applied to MahaRERA to extend the completion date 4 times: to 30 June 2021, giving the reason "Reason for extension: Since our Project type is MHADA Redevelopment, we got our MHADA approval with prevailing policy with sharing in Sept 2016. Subsequently the same is approved in MCGM in 2017 & we started our commencement on site. In view of prevailing policy of 2016 govt. of Maharashtra amended DCR 33 (5) in July 2017 which allows redevelopment with premium which is principally applicable for our society & so society resolved the same for migration. We have submitted our proposal to MHADA for migration in December 2017. Due to pending EP’s of DCPR 2034, we have still not obtained revise…"; to 30 June 2021, giving the reason "Since our Project type is MHADA Redevelopment, we have initiated with construction of the project since 2014 as per prevailing approvals from MHADA as well as MCGM. In same regards MHADA Redevelopment policy has changed as per DCPR 2034. Finally we got our MHADA approval with prevailing policy with premium on 23/07/2019. In view of prevailing policy of DCPR 2034 MHADA Redevelopment DCPR 33(5) declared in November 2018. In same regards Gov. Proposed amendments with respect to Premium charges, Development Cess, Fungible Premium on 20th August 2019, to make all proposals Economical viable. The…"; to 30 June 2024, giving the reason "The Promoter has changed from Propreitorship into Private Limited Company. We have received approval from Maha RERA for the change of Promoter. The New Promoter is "Muktistar Buildcon Private Limited". Therefore, We hereby apply for extension under Section 6 of the Maharastra (Regulation and Development) Act, 2016."; to 30 June 2025, giving the reason "The delay in the above-mentioned project is due to rainy season, permission to dig cement road is not granted. We have already applied for permission. But as the road in front is made of cement concrete, permission will be given only after monsoon. Drinking water and sewage as well as electricity supply cannot be obtained in accordance with the above subject. Thus, we are seeking extension of the date of completion of the project so as to not compromise with the quality of the work.".
What is the RERA number of ANMOLPRITI?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of ANMOLPRITI in Charkop Kandivali West, Mumbai is P51800006598.
Is ANMOLPRITI registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), ANMOLPRITI is registered as P51800006598 and its status is "Completed".
What is the construction status of ANMOLPRITI?
According to GharKundli's check of MahaRERA records (updated October 2026), ANMOLPRITI's status on MahaRERA is "Completed". As filed by the builder, slab work on ANMOLPRITI is 100% done and internal work 97%. GharKundli's full report compares construction progress with the deadline.
Does ANMOLPRITI have complaints on MahaRERA?
4 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is ANMOLPRITI safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), ANMOLPRITI is registered on MahaRERA as P51800006598, its MahaRERA status is "Completed", its completion date has moved 78 months since registration and 4 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if ANMOLPRITI's possession date changes?
The latest dates are on ANMOLPRITI's MahaRERA page (P51800006598). GharKundli's Kundli Watch sends a free WhatsApp update on ANMOLPRITI every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does ANMOLPRITI have?
According to GharKundli's check of MahaRERA records (updated October 2026), ANMOLPRITI has one building filed: ANMOLPRITI with 26 floors.
How big is the land of ANMOLPRITI?
According to GharKundli's check of MahaRERA records (updated October 2026), ANMOLPRITI stands on 882 sq m of land (about 0.2 acres), with 1,050 sq m of sanctioned built-up area.
Where can I read reviews of ANMOLPRITI?
Google Maps has reviews of ANMOLPRITI written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 4 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is ANMOLPRITI?
ANMOLPRITI by Muktistar Buildcon Private Limited VISHWANATH GAIKWAD is in Charkop Kandivali West, Mumbai (pincode 400067), near Borivali, Chikoowadi, Maharashtra, and is registered on MahaRERA as P51800006598, per GharKundli's check of MahaRERA records.
When was ANMOLPRITI registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), ANMOLPRITI was registered on MahaRERA on 14 August 2017. GharKundli did not find a title report on the land on file there.
Are there court cases on ANMOLPRITI?
No court cases are listed for ANMOLPRITI on MahaRERA, and 2 appeals at the tribunal, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.
Who is the builder of ANMOLPRITI?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Muktistar Buildcon Private Limited VISHWANATH GAIKWAD.
Check it yourself on MahaRERA
- How to check the possession date of ANMOLPRITI
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in pincode 400067
- PRIME SQUARE
- LA SERENA Tower 5, Tower 6 and Tower 7
- CHARKOP SHREE GANESH CHS LTD
- MPR SHRI PARAS DARSHAN
- SAFFRONWOODS CHSL
- SIGMA AMBER
- Avenue Wing B phase 2
- JAYAKAR HOUSE
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.