B PARK
by VIDARBHA INFOTECH B PARK SPV LLP · Nagpur City, NagpurAlso near Bagadganj, Dr.Ambedkar Marg, Mahatma Fule Bazar
Possession date of B PARK: 14 November 2029. This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P50500079968, and currently active. Its completion date is now November 2029, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about B PARK?
How the possession date of B PARK has moved
14 July 2029
Completion date given when the project was registered
14 November 2029
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: B PARK’s extension records on MahaRERA (P50500079968), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on B PARK
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the November 2029 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P50500079968
- Status
- Registered and active
- Builder
- VIDARBHA INFOTECH B PARK SPV LLP
- Location
- Nagpur City, Nagpur · 440002
- Project type
- Commercial
- Registered on
- 8 Apr 2025
- Completion date at registration
- July 2029
- Latest completion date
- November 2029
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 35
- Sold or booked
- 0%
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of B PARK, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| B PARK | 89% | 9% | 0% | 0% |
Commencement certificate (CC), as filed on MahaRERA
- B PARK: covers 13 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on B PARK every month.
B PARK: buildings, flats and land, as filed on MahaRERA
- Buildings: B PARK (13 floors, 534 units)
- Land: 6,188 sq m (about 1.5 acres) · sanctioned built-up 27,302 sq m
- Boundaries filed include: KELIBAG ROAD
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of B PARK →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
B PARK: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about B PARK
What is the possession date of B PARK?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for B PARK in Nagpur City, Nagpur is 14 November 2029, including MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for B PARK?
Builders and listing sites often quote an earlier "target" date for handover. The completion date B PARK's builder has filed on MahaRERA, the official one, is 14 November 2029, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
What is the RERA number of B PARK?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of B PARK in Nagpur City, Nagpur is P50500079968.
Is B PARK registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), B PARK is registered as P50500079968 and its status is "Registered and active".
What is the construction status of B PARK?
According to GharKundli's check of MahaRERA records (updated October 2026), B PARK's status on MahaRERA is "Registered and active". As filed by the builder, slab work on B PARK is 9% done and internal work 0%. GharKundli's full report compares construction progress with the deadline.
Does B PARK have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is B PARK safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), B PARK is registered on MahaRERA as P50500079968, its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if B PARK's possession date changes?
The latest dates are on B PARK's MahaRERA page (P50500079968). GharKundli's Kundli Watch sends a free WhatsApp update on B PARK every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does B PARK have?
According to GharKundli's check of MahaRERA records (updated October 2026), B PARK has one building filed: B PARK with 13 floors and 534 units.
How big is the land of B PARK?
According to GharKundli's check of MahaRERA records (updated October 2026), B PARK stands on 6,188 sq m of land (about 1.5 acres), with 27,302 sq m of sanctioned built-up area.
Where can I read reviews of B PARK?
Google Maps has reviews of B PARK written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is B PARK?
B PARK by VIDARBHA INFOTECH B PARK SPV LLP is in Nagpur City, Nagpur (pincode 440002), near Bagadganj, Dr.Ambedkar Marg, Mahatma Fule Bazar, Maharashtra, and is registered on MahaRERA as P50500079968, per GharKundli's check of MahaRERA records. Its boundaries filed there include KELIBAG ROAD.
How many homes are in B PARK?
According to GharKundli's check of MahaRERA records (updated October 2026), B PARK has 35 homes in 1 tower registered on MahaRERA, and 0% of them are sold or booked.
When was B PARK registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), B PARK was registered on MahaRERA on 8 April 2025. GharKundli did not find a title report on the land on file there.
Are there court cases on B PARK?
No court cases are listed for B PARK on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder of B PARK?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is VIDARBHA INFOTECH B PARK SPV LLP.
Check it yourself on MahaRERA
- How to check the possession date of B PARK
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2029 in Nagpur →
Other projects in pincode 440002
All 7 projects in Nagpur City (440002) →Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.