VARAD ENCLAVE
by VARAD CONSTRUCTIONS · Sarda Layout, NagpurAlso near Hazaripahad, Vayusena Nagar
Possession date of VARAD ENCLAVE: 25 March 2030. This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P50500080050, and currently active. Its completion date is now March 2030, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about VARAD ENCLAVE?
How the possession date of VARAD ENCLAVE has moved
25 November 2029
Completion date given when the project was registered
25 March 2030
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: VARAD ENCLAVE’s extension records on MahaRERA (P50500080050), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on VARAD ENCLAVE
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the March 2030 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P50500080050
- Status
- Registered and active
- Builder
- VARAD CONSTRUCTIONS
- Location
- Sarda Layout, Nagpur · 440007
- Project type
- Residential / Group Housing
- Registered on
- 21 Apr 2025
- Completion date at registration
- November 2029
- Latest completion date
- March 2030
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 84
- Sold or booked
- 13%
- Towers
- 2
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of VARAD ENCLAVE, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| WING A | 100% | 80% | 80% | 0% |
| WING B | 100% | 80% | 80% | 0% |
Commencement certificate (CC), as filed on MahaRERA
- WING A: covers 7 floors
- WING B: covers 7 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on VARAD ENCLAVE every month.
VARAD ENCLAVE: buildings, flats and land, as filed on MahaRERA
- Buildings: WING A (7 floors, 48 units) · WING B (7 floors, 36 units)
- Car parking: 40 covered, 44 open
- Land: 2,536 sq m (about 0.6 acres) · sanctioned built-up 7,296 sq m
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of VARAD ENCLAVE →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
VARAD ENCLAVE: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about VARAD ENCLAVE
What is the possession date of VARAD ENCLAVE?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for VARAD ENCLAVE in Sarda Layout, Nagpur is 25 March 2030, including MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for VARAD ENCLAVE?
Builders and listing sites often quote an earlier "target" date for handover. The completion date VARAD ENCLAVE's builder has filed on MahaRERA, the official one, is 25 March 2030, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
What is the RERA number of VARAD ENCLAVE?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of VARAD ENCLAVE in Sarda Layout, Nagpur is P50500080050.
Is VARAD ENCLAVE registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), VARAD ENCLAVE is registered as P50500080050 and its status is "Registered and active".
What is the construction status of VARAD ENCLAVE?
According to GharKundli's check of MahaRERA records (updated October 2026), VARAD ENCLAVE's status on MahaRERA is "Registered and active". As filed by the builder, slab work is 80% done across 2 towers. GharKundli's full report compares construction progress with the deadline.
Does VARAD ENCLAVE have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is VARAD ENCLAVE safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), VARAD ENCLAVE is registered on MahaRERA as P50500080050, its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if VARAD ENCLAVE's possession date changes?
The latest dates are on VARAD ENCLAVE's MahaRERA page (P50500080050). GharKundli's Kundli Watch sends a free WhatsApp update on VARAD ENCLAVE every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does VARAD ENCLAVE have?
According to GharKundli's check of MahaRERA records (updated October 2026), VARAD ENCLAVE has 2 buildings filed: WING A with 7 floors and 48 units; WING B with 7 floors and 36 units.
How much parking does VARAD ENCLAVE have?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 40 covered and 44 open car parking spaces for VARAD ENCLAVE.
How big is the land of VARAD ENCLAVE?
According to GharKundli's check of MahaRERA records (updated October 2026), VARAD ENCLAVE stands on 2,536 sq m of land (about 0.6 acres), with 7,296 sq m of sanctioned built-up area.
Where can I read reviews of VARAD ENCLAVE?
Google Maps has reviews of VARAD ENCLAVE written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is VARAD ENCLAVE?
VARAD ENCLAVE by VARAD CONSTRUCTIONS is in Sarda Layout, Nagpur (pincode 440007), near Hazaripahad, Vayusena Nagar, Maharashtra, and is registered on MahaRERA as P50500080050, per GharKundli's check of MahaRERA records.
How many homes are in VARAD ENCLAVE?
According to GharKundli's check of MahaRERA records (updated October 2026), VARAD ENCLAVE has 84 homes in 2 towers registered on MahaRERA, and 13% of them are sold or booked.
When was VARAD ENCLAVE registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), VARAD ENCLAVE was registered on MahaRERA on 21 April 2025. GharKundli did not find a title report on the land on file there.
Are there court cases on VARAD ENCLAVE?
No court cases are listed for VARAD ENCLAVE on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder of VARAD ENCLAVE?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is VARAD CONSTRUCTIONS.
Check it yourself on MahaRERA
- How to check the possession date of VARAD ENCLAVE
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2030 in Nagpur →
Other projects in Nagpur (Urban)
- ROYAL PARK
- GLOCAL SQUARE 3 RD FLOOR
- SHREE APARTMENTS
- Mithila Apartment
- EMPRESS ROYAL EFGH
- ROYAL PRIDE
- Swapnapurtee - A Project by NMC
- Devotie
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.