Possession date of RIDDHI SIDDHI - III: 12 February 2029. This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under PR1190002501512, and currently active. Its completion date is now February 2029, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about RIDDHI SIDDHI - III?
How the possession date of RIDDHI SIDDHI - III has moved
12 October 2028
Completion date given when the project was registered
12 February 2029
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: RIDDHI SIDDHI - III’s extension records on MahaRERA (PR1190002501512), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on RIDDHI SIDDHI - III
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the February 2029 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- PR1190002501512
- Status
- Registered and active
- Builder
- DEVANG DEVELOPERS LLP
- Location
- Khamla, Nagpur · 440025
- Project type
- Residential / Group Housing
- Registered on
- 18 Nov 2025
- Completion date at registration
- October 2028
- Latest completion date
- February 2029
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 40
- Sold or booked
- 0%
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 3
Construction progress of RIDDHI SIDDHI - III, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| RIDDHI SIDDHI III | 100% | 72% | 0% | 0% |
Commencement certificate (CC), as filed on MahaRERA
- RIDDHI SIDDHI III: covers 12 floors
Latest CC order on MahaRERA: dated 07/08/2025.
Want to know when this changes? Kundli Watch sends a free WhatsApp update on RIDDHI SIDDHI - III every month.
RIDDHI SIDDHI - III: buildings, flats and land, as filed on MahaRERA
- Buildings: RIDDHI SIDDHI III (12 floors, 42 units)
- Car parking: 55 covered
- Land: 1,357 sq m (about 0.3 acres) · sanctioned built-up 6,157 sq m
The builder’s record and reviews
Devang Developers (a group of 2 linked companies) has 5 projects on MahaRERA since 2022, this one included. Of the 3 GharKundli has checked: 2 finished, all within the promised date; 1 still being built, none past the promised date yet. No complaints on MahaRERA.
Read Google reviews of RIDDHI SIDDHI - III →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
RIDDHI SIDDHI - III: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about RIDDHI SIDDHI - III
What is the possession date of RIDDHI SIDDHI - III?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for RIDDHI SIDDHI - III in Khamla, Nagpur is 12 February 2029, including MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for RIDDHI SIDDHI - III?
Builders and listing sites often quote an earlier "target" date for handover. The completion date RIDDHI SIDDHI - III's builder has filed on MahaRERA, the official one, is 12 February 2029, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
What is the RERA number of RIDDHI SIDDHI - III?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of RIDDHI SIDDHI - III in Khamla, Nagpur is PR1190002501512.
Is RIDDHI SIDDHI - III registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), RIDDHI SIDDHI - III is registered as PR1190002501512 and its status is "Registered and active".
What is the construction status of RIDDHI SIDDHI - III?
According to GharKundli's check of MahaRERA records (updated October 2026), RIDDHI SIDDHI - III's status on MahaRERA is "Registered and active". As filed by the builder, slab work on RIDDHI SIDDHI III is 72% done and internal work 0%. GharKundli's full report compares construction progress with the deadline.
Does RIDDHI SIDDHI - III have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is RIDDHI SIDDHI - III safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), RIDDHI SIDDHI - III is registered on MahaRERA as PR1190002501512, its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if RIDDHI SIDDHI - III's possession date changes?
The latest dates are on RIDDHI SIDDHI - III's MahaRERA page (PR1190002501512). GharKundli's Kundli Watch sends a free WhatsApp update on RIDDHI SIDDHI - III every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does RIDDHI SIDDHI - III have?
According to GharKundli's check of MahaRERA records (updated October 2026), RIDDHI SIDDHI - III has one building filed: RIDDHI SIDDHI III with 12 floors and 42 units.
How much parking does RIDDHI SIDDHI - III have?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 55 covered car parking spaces for RIDDHI SIDDHI - III.
How big is the land of RIDDHI SIDDHI - III?
According to GharKundli's check of MahaRERA records (updated October 2026), RIDDHI SIDDHI - III stands on 1,357 sq m of land (about 0.3 acres), with 6,157 sq m of sanctioned built-up area.
What is the track record of RIDDHI SIDDHI - III's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Devang Developers (a group of 2 linked companies) has 5 projects on MahaRERA since 2022, this one included. Of the 3 GharKundli has checked: 2 finished, all within the promised date; 1 still being built, none past the promised date yet. No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of RIDDHI SIDDHI - III?
Google Maps has reviews of RIDDHI SIDDHI - III written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is RIDDHI SIDDHI - III?
RIDDHI SIDDHI - III by DEVANG DEVELOPERS LLP is in Khamla, Nagpur (pincode 440025), near Neeri, Maharashtra, and is registered on MahaRERA as PR1190002501512, per GharKundli's check of MahaRERA records.
How many homes are in RIDDHI SIDDHI - III?
According to GharKundli's check of MahaRERA records (updated October 2026), RIDDHI SIDDHI - III has 40 homes in 1 tower registered on MahaRERA, and 0% of them are sold or booked.
When was RIDDHI SIDDHI - III registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), RIDDHI SIDDHI - III was registered on MahaRERA on 18 November 2025. GharKundli did not find a title report on the land on file there.
Are there court cases on RIDDHI SIDDHI - III?
No court cases are listed for RIDDHI SIDDHI - III on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder of RIDDHI SIDDHI - III?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is DEVANG DEVELOPERS LLP, which has 3 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of RIDDHI SIDDHI - III
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2029 in Nagpur →
Other projects in pincode 440025
- 1-DEV HEIGHTS
- SAI CHHAYA-2
- 129-RIDDHI SIDDHI HEIGHTS
- DIVYAM APARTMENTS
- Prathamesh Apartment
- PRAJAKTA LA MAISON
- Sayalee Apartment
- Trident Park
Other projects by DEVANG DEVELOPERS LLP
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.